Renewable Energy related Research and Development ( R & D) organizations in Bangladesh
Local Government Engineering Department (LGED)
LGED designed Water pumping Windmill
Technical Information Water pumping Windmill
Design and Installed by Local Government Engineering Department :
Introduction :
-
Low cost
Locally manufactured
-
Minimal maintenance
-
20,000 of water per day at 4.0 m/s wind velocity

Water Pumping Windmill, designed by LGED
-
10 m head
Technical Data :
- Rotor dia 2.75m
-
No of blades 24
-
Starting wind speed 1.8 m/s
-
Pump type semi rotor reciprocating suction pump
-
Output 20,000 litters/day, 10m head at 4.0 m/s wind velocity
Uses of Windpump :
- Villages
-
Schools
-
Rural Clinics
-
Farms (irrigation & livestock)
-
Small scale industries
-
Nature/Wildlife reserves
-
Land Drainage
-
Salt Production
-
Waste water treatment
-
Aerations
Wind speed data for 1 year :
| SL | Location | Average Wind Speed (M/S) | Sensor Height (M) | Data Acquisition Period |
| 1 | Kuakata | 4.54 | 25 | 1996-97 |
| 2 | Kutubdia | 4.18 | 25 | 1996-97 |
| 3(a) | Char Fassion 1 | 3.28 | 10 | 1996-97 |
| 3(b) | Char Fassion 2 | 4.07 | 25 | 1996-97 |
| 4 | Patenga | 3.84 | 25 | 1996-97 |
| 5 | Cox's Bazaar | 3.34 | 25 | 1996-97 |
| 6 | NoakhaliI | 2.96 | 25 | 1996-97 |
| 7 | Teknaf | 2.96 | 25 | 1996-97 |
Basic concepts of windpump :
Wind energy is converted into rotary mechanical motion of wind turbine
-
Rotary motion of the wind turbine is converted into reciprocating motion
The pump sucks water and delivers into storage tank
Different parts of a windpump system :
|
The
Well
The Wheel or Rotor The Transmission Linkages The Tail The Turbine The Pump The Pump Rod Assembly Bearings Tower Storage Tank
|
|
| Different Parts of Windpump System |
Materials & Manufacture :
-
Most of the materials is steel angle sections, steel plates, chains with sprocket, G.I. Sheet etc.
-
Few ball bearings and guides are required
-
Little machining is required
-
Few turning ,boring ,drilling and welding
Installation and Maintenance :
-
Total weight of machine including the tower is under 800 kg
-
Easy and safe installation using chain pulley mechanism and sometimes using a winch
-
Maintenance is limited to greasing the ball bearings once a year
-
Touching up or repainting every few year
-
Servicing of pump (change seals only) every few years
Advantages :
-
Low cost
-
Low maintenance cost
-
No fuel cost
-
Minimal maintenance
-
No pollution
-
Ergonomic design
Conclusion :
-
Proved functional to supply water in rural areas
-
Should be disseminated in our country to meet the need of water to the rural people
-
Design should be updated applying special thrust by observing its performance