National Exhibition and Seminar (Title : Climate Change Mitigation : Role of Renewables) on Renewable Energy . Dhaka, Bangladesh, 24-25 March, 2008
USE OF
EARTH AIR TUNNEL AND CAVITY WALL AS PASSIVE COOLING IN A
GARMENT FACTORY OF BANGLADESH FOR ENERGY CONSERVATION
INTRODUCTION
ü
Any
building or factory with a large number of occupants in the
hot and humid regions can reach high level of thermal
stress.
ü
One of
the major design criteria of a building in a warm and humid
climate is its cooling system.
ü
The
cooling load is a predominant factor in terms of energy
consumption.
ü
Adoption
of passive cooling as an alternative to artificial cooling
can bring important benefits to the energy, environmental
and financial sectors.
ü
Only
passive cooling alone cannot provide the appropriate thermal
comfort standard without addition of active cooling.
ü
Addition
of active cooling system using air-conditioning and
refrigeration generate multiple impacts on stratospheric
ozone layer.
ü
Release
of refrigerants and emission of green house gases (GHG) make
combined contribution to global warming.
ü
Buildings that operates on a mixed cooling system in a
warm-humid climates are able to balance the need for
comfort, eco friendliness and energy efficiency through the
year.
ü
Little
work has been reported in the thermal performance of
building that utilizes active and passive cooling in
Bangladesh.
MOTIVATION
●
Per
capita energy consumption in Bangladesh is only 157 kgoe
(2003).
●
Per
capita electricity generation is 167 kWh and per capita
consumption is 136 kWh (2005-2006)
●
Average
electricity demand is 4500 MW and generation capacity is
only 3300 MW
●
It is an
energy crisis situation
●
With
increased demand for energy, the cost of energy is also
increasing
●
Steps
should be taken for adoption of various mechanism towards an
effective and significant saving of conventional energy
OBJECTIVES
●
Cost
effective active and passive cooling system design for a
garment factory
●
Cool
comfortable and dust free environment inside production
floors
●
Low
installation cost, energy conservation and easy maintenance
for sustainability
SPECIFIC REQUIREMENTS OF THE USER
The
desired temperature and humidity level to be achieved for
indoor comfort was set as 28-29°C and humidity level 60-65%.
DESIGN CONCEPTS
●
To
achieve the set conditions a dual cooling system was
designed and installed in a four-storied garment factory
named Section Seven Ltd. at Chittagong, Bangladesh
●
In our
design of cooling system we have utilized the following
steps:
Cooling
load reduction by architecture
►
Ground coupled EAT as passive cooling
►
Programmed active cooling and dehumidification
SITE
LOCATION
SITE
LOCATION
CHITTAGONG – The port city of Bangladesh
SITE
INFORMATION
Location
of the Site:
Chittagong – The main port city of
Bangladesh.
●
Geographical position:
Latitude: 22°-16’ north
Longitude: 91°-82’ east
●
Climate Condition:
Mostly hot and humid apart from few months of
winter.
●
The mean temperature:
In January: 20°C
In July: 27.5°C
●
Section Seven Ltd. Is a garment factory located in
Chittagong Export Processing Zone (CEPZ).
PRODUCTION ROOM DIMENSIONS (COOLING LOAD)
●
52 meter
wide facing west as front and east as rear per floor.
●
30 meter
long sides facing as north and south per floor.
●
4.3
meter room height
●
Total
number of floors: 3
COOLING LOAD REDUCTION BY ARCHITECHTURE
●
Reduction of heat gain by cavity wall facing east and west
sides
●
Increase
of Room Height for Air Circulation
●
Reduction of window size facing east and west sides
●
Recessed
window filled with tinted glass
HEAT
GAIN DUE TO SUNSHINE HOUR IN USUAL BUILDING CONCEPT (Design
considerations)
Exposed solid wall along Sun-path results 5°-7° Celsius room
heat gain. Temperature rises from 31°-38° Celsius within
building envelope due to long Sun-exposed solid wall and
large windows in east and west sides.
INTERNAL HEAT GAIN (Design considerations)
●
Heat
gain due to occupants
●
Heat
gain due to Machine Operation
●
Convection
●
Temperature rises from 31°-38° Celsius
CONSTRUCTION OF CAVITY WALL (PASSIVE COOLING)
●
Reduced
heat transmission
●
Removes
heated air through natural air movement
●
Internal
wall works as condenser or heat absorber
GROUND COUPLED EAT AS PASSIVE COOLING
Earth
Air Tunnel (EAT) is a large underground tunnel composed of
number of smaller tunnel.
The
use of Earth Air Tunnel (EAT) technology as a ground coupled
building as passive cooling system have been employed in
many parts of the world.
The
ground has infinite heat absorbing capacity. Therefore, room
air if made to circulate through an appropriate inlet and
outlet duct and passed into the EAT, that ground coupled
under the ground floor of a building would attain the same
temperature of the ground temperature.
The
continuous forced circulation of room air through EAT would
maintain the air temperature closed to that of Earth
temperature.
GROUND
COUPLED EAT SYSTEM DESIGN
GROUND COUPLED EAT SYSTEM OPERATION
●
Circulating the hot air from room (32°-33°) through earth
air tunnel (25°-26°)
●
Keeping
room temperature within 29°-30° through continuous
conduction
●
Addition
of fresh air
FORCED AIR CIRCULATION OF ROOM AIR THROUGH EAT
●
Blower
used : 16 (big) – 4000 CFM - 2 hp, 3 phase motors, 1200 RPM
●
Booster
blower used : 16 (small) – 300 CFM, 200 watt single phase,
400 RPM
●
Operation time : 10 hr per day
ADDITION OF WINDOW TYPE AIR-CONDITIONER AS ACTIVE COOLING
AND DEHUMIDIFICATION
●
18 ACs
of 27,000 Btu/hr cooling capacity were installed in each
floor
●
2 ACs
were installed face to face in the rear and front wall as
one modular set
●
The
cooling outlet of 2 ACs were connected by a duct for uniform
air discharge by mixing with air of EAT
●
Operating hour : 8 hr per day
●
Total
active cooling installed in 3 floors (18x3)
= 54 ACs equivalent to 122 tons
ADDITION OF WINDOW TYPE AIR-CONDITIONER AS ACTIVE COOLING
AND DEHUMIDIFICATION
OPERATION OF WINDOW TYPE AIR-CONDITIONER AS ACTIVE COOLING
AND DEHUMIDIFICATION
●
Applying
active cooling using 18 nos Air-conditioner (27000 B.T.U.
per AC)
●
Placing
Two AC Face-to-Face (9 set) reducing the requirement of
additional blower for air distribution
●
Removal
of moisture and dehumidification
PROGRAMMED ACTIVE COOLING AND DEHUMIDIFICATION
Window type room air-conditioner (AC) were added to each
floor to provide a programmed (35 minutes ON and 7 minutes
OFF) active cooling and dehumidification inside the room.
The
room air discharge system were designed to deliver the air
by combining the air from AC and EAT.
OPERATION OF THE DESIGNED SYSTEM
Continuous uniform suction of room air at the ceiling
level to EAT
Ground conduction and dust removal through EAT by
blowers
A
fraction of fresh air intake
Mixing of incoming air from EAT with cold and
dehumidified air from AC
Discharge of processed air uniformly from little above
the human height level through AC to AC duct slits
ESTIMATION OF COOLING LOAD
Room
area load
52 meter width x 30 meter length x 4.3 meter
height
Total 6,700 cubic meter room volume per floor
For 3 floor = 20,100 cubic meter room volume
ESTIMATION OF COOLING LOAD
Human
load
550 workers (80% female and 20% male) per floor
Total for 3 floors=1650 workers
ESTIMATION OF COOLING LOAD
Internal machine heat generation load
ü
300
motor driven sewing machines
ü
500pcs
of 40 watt tube lights
ü
50pcs of
steam iron
ü
few heat
generating fusing machines
ü
and
miscellaneous equipments
ESTIMATION OF COOLING LOAD
ü
Considering total electrical load computed as 250 KW and
fresh air intake and number of door opening as additional
load.
ü
The
calculated cooling load per floor=120 ton
ü
Total
estimated cooling load for 3 floor = 360 ton
ü
The
ground floor space was not included in the estimation due to
its uses as storage purposes only
OUTLINE OF COOLING LOAD, ACTIVE AND PASSIVE COOLING
CAPACITY, ENERGY EXPENSES AND ENERGY SAVING
●
Total
requirement of the cooling load = 360 ton
●
Cooling
load reduced by cavity wall = 60 tons
●
Cooling
load reduced by EAT (300-180) = 120 tons
●
Balance
120 ton cooling should be covered by Active Cooling
OUTLINE OF COOLING LOAD, ACTIVE AND PASSIVE COOLING
CAPACITY, ENERGY EXPENSES AND ENERGY SAVING
RUNNING COST OF ACTIVE COOLING SYSTEM
Tk
1,46,400 for AC + Tk 30,240 for large blower
+ Tk 4,032 for small blower + maintenance cost
= Tk 2 lacs per month
Per
unit cost of electricity in CEPZ = Tk 4.50
OUTLINE OF COOLING LOAD, ACTIVE AND PASSIVE COOLING
CAPACITY, ENERGY EXPENSES AND ENERGY SAVING
ENERGY SAVING
60
ton from cavity wall construction for reduced heat gain
180
ton from EAT for reduction of room temperature
1 ton
= 1.2 kW energy requirement, 8 hrs per day, 28 days per
month
= 1.2 kW x 8 hours x 28 days = 270 kW-h
Energy saving in case of 60 ton cooling load reduction
by cavity wall = 13,440 kW-h
Total
saving of electricity cost due to passive cooling
= Tk
2,20,000 per month
INSTALLATION COST OF COOLING SYSTEM
●
Tk
70,00,000 (equivalent to US$ 1,00,000)
[1 US$=Tk 70 only]
●
Payback
period in terms of energy saving = 3.5 years
Construction of custom-made Earth Air Tunnel (EAT)
Building construction underway
100
feet of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
Construction of custom-made Earth Air Tunnel (EAT)
Earth
removal
100
feet of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
Construction of custom-made Earth Air Tunnel (EAT)
Earth
removal – Block-by-Block
100
feet of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
Construction of custom-made Earth Air Tunnel (EAT)
Round
R.C.C pipe laying (1 meter bellow the ground floor)
100
feet of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
Construction of custom-made Earth Air Tunnel (EAT)
Round
R.C.C pipe laid in one Block
100
feet of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
Construction of custom-made Earth Air Tunnel (EAT)
Filling with clay over R.C.C pipe
100
feet of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
Construction of custom-made Earth Air Tunnel (EAT)
Water
curing of clay
100
feet of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
Construction of custom-made Earth Air Tunnel (EAT)
Construction of maintenance channel of R.C.C pipes (East)
100 feet
of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
Construction of custom-made Earth Air Tunnel (EAT)
Construction of maintenance channel of R.C.C pipes (West)
100
feet of 96 line 9” diameter R.C.C pipe round as EAT Tunnel
GI
SHEET DUCT COUPLING FOR AIR SUPPLY AND DELIVERY FROM EAT
FORCED CIRCULATION OF AIR USING BLOWER
FORCED CIRCULATION OF AIR THROUGH EAT USING BLOWER
AC TO
AC DUCT WITH AIR DISCHARGE SLITS INSIDE PRODUCTION FLOOR
AC TO
AC DUCT INSIDE PRODUCTION FLOOR
WINDOW TYPE AC POSITION - FLOOR WISE
RECESSED WINDOW FILLED WITH TINTED GLASS
FRESH
AIR INTAKE MECHANISM USING GI PIPE
FRESH
AIR INTAKE MECHANISM USING GI PIPE
ROOM
ENVIRONMENT WITH COOLING SYSTEM IN OPERATION
Light
load = 550 nos 40 watt tube lights per floor
ROOM
ENVIRONMENT WITH COOLING SYSTEM IN OPERATION
Light
load = 550 nos 40 watt tube lights per floor
ROOM
ENVIRONMENT WITH COOLING SYSTEM IN OPERATION
Noise
free environment
PERFORMENCES OF COOLING SYSTEM
Room
environment without any cooling system on and with all
windows/doors open
Month /Day
Time
Outside Temp.
°C
Inside Temp.
°C
Humidity outside
%
Humidity inside %
Worker per floor
Comment
5 Jul.06
9 AM
30
38
71
88
530
Very hot and humid condition productivity 60%
Room
environment with passive cooling (Blowers) on and active
cooling (AC) off
Month/
Day
Time
Outside Temp.
°C
Inside Temp.
°C
Humidity outside
%
Humidity inside %
Worker per floor
Comment
11 Jul.06
12PM
33
31
75
82
520
Humid condition, productivity 75%
Room
environment with passive cooling (Blowers) off and active
cooling (AC) on
Month/
Day
Time
Outside Temp.
°C
Inside Temp.
°C
Humidity outside
%
Humidity inside %
Worker per floor
Comment
12 Jul.06
11PM
31
34
73
64
530
Hot but non-humid condition, productivity 68%
Performance of cooling system-(Active and Passive on) - Data
collection -incomplete
Month
Day
Time
Outside Temp.
°C
Inside Temp.
°C
Humidity outside
%
Humidity inside
%
person per floor
Comment
15 Jul.06
12PM
33
29
79
63
530
Pleasant environment, Productivity
90%
10 Aug.06
2PM
28.6
28.2
74
57
490
Do
20 Sep.06
3PM
31.7
28.6
81
66
550
Do
11 Oct.06
2PM
33.4
29.2
73
61
530
Do
14 Nov.06
11AM
32.2
28.8
78
63
500
Do
22 Dec.06
3PM
28
27.5
85
62
490
Do
30% AC off
16 Jan.07
10AM
26
27
78
61
510
Do
50% AC off
6 FEB.07
12PM
19
26
88
67
500
Do
50% AC off
10 Mar.07
2PM
29
28
60
64
510
Do
30% AC off
ASPECTS OF SUSTAINABILITY AND DEVELOPMENT
Control of demand, conservation, minimization of waste and
conservation of natural resource
ACHIEVEMENTS
●
Power
savings (energy conservation)
●
Reduced
Green House Gas emission
●
Easy
maintenance due to Modular Design
●
Low
maintenance cost
●
Total
shut-down (characteristics of central A/C system) may not
happen.
●
Approximate running cost of designed system
●
Tk 2
lacs per month (US$ 2,857)
●
Energy
saving per month = 50 MW-h due to reduction of cooling load
by passive cooling
●
Equivalent amount of carbon emission saving 261 ton per year
(RETSCREEN)
●
Electricity saved per year = 600 MW-h per year
●
Average
production target per day = 11,000-12,000 pieces of gents
shirt per day based on design, 90% achieved
INSTALLATION COST OF COOLING SYSTEM
●
Tk 70
lacs only (US$ 100,000)
●
Tk 50
lacs saved (US$ 71,429) due to non-conventional cooling
system design
OTHER
FEATURES ADDED OR TO BE ADDED IN THE BUILDING
●
Rain
water harvesting from rooftop to ground water reservoir tank
as a source of iron free water for the boiler during rainy
season (added)
●
Installation of small scale PV panel for power generation to
operate LED security lighting (added)
●
Installation of solar water heater for boiler (proposed)
CONCLUSION
Since
it is a recently installed project the collection of
essential data are still ongoing. Necessary modification is
also going on to optimize the designed system floor wise.
Initial findings of various performances in terms of energy
conservation and other associated factors are very
encouraging. The detail performance results would be
complete after one full year of operation on 15th June 2008.
This
hybrid cooling system may continue to demonstrate a
commercially preferable, environmentally benign,
aesthetically pleasing way of reducing carbon emission
through industrial, institutional energy conservation and
many other kinds of buildings for sustainable development.
To
serve every potential eco-aware consumer in such
implementations trained human resources are essential, where
the joint role of investor and academics could be enormous.
Ultimately it could provide incentive for motivation, design
innovation, integrity, efficacy, courage and reliability for
the growing youth force of the country.































