Context : Energy Situation in Bangladesh
l Around 100 Million people have no access to grid electricity
l Only 3% people have access to gas through pipelines
l Lack of energy is one of the major reasons for rural backwardness
l There is potential of 4 million biogas plants in the country
l Climate in Bangladesh is suitable for biogas production
Conventional Use of Cattle Dung

Conventional Use of Poultry Litter

Grameen Shakti Programs
q Extension of Solar Home Systems
q Wide Dissemination of Biogas Technology
q Establishing Grameen Technology Centers
q Popularizing Improved Cook Stoves
q Training and Capacity Building
Organizational Status
-
Total Staff : 1278
-
Division Offices : 4
-
Regional Offices : 39
-
Unit Offices : 252
Strategies
• Follow SNV/IDCOL model for all the plants up to 4.8 m3 size
• Follow GS model for all the plants above 4.8 m3 size
• Provide credit support in all the cases as per rule where necessary
Ongoing Projects
|
Sl |
Name of the project |
Achievements |
Status |
|
1 |
Addressing Famine |
12 |
Ongoing |
|
2 |
GTZ/PURE |
99 |
Ongoing |
|
3 |
MoEF IPSU |
5 |
Ongoing |
|
4 |
NDBMP by IDCOL/SNV |
250 |
Ongoing |
|
5 |
GS Own Program |
449 |
Ongoing |
|
|
Total |
815 |
|
Capacity Building
l Training of GS Engineers and Field Assistants at home and abroad
l Training of Masons
l Users Training
l Orientation and Awareness Razing
Target
v 10,000 plants by the year 2009 under
SNV/IDCOL program
v 10,000 plants by the year 2010 under
GTZ/GS program
v 100% utilization of slurry
v Power generation using biogas
v 100% plants are in operation
Financial Approach for GS Model
|
Option |
Down payment |
Installments |
Service Charge (Flat rate) |
Technical Fee |
|
Option-1 |
25% |
24 months |
6% |
10% |
|
Option-2 |
Cash payment |
10% |
||

Recent Improvements
• Mixing Device
• Turret
• Pipeline
• Hydraulic Chamber
• Burner
• Slurry Processing
• Water Drain
• Cooking Practice
A Complete Plant (Old)

A Complete Plant (New)

Digester Bottom and Wall

Digester Wall and Outlet Passage

Top Dome

Inlet (Old)

Mixing Device

Inlet (New)

Inlet (New)

Center Pipe (Old)

Turret

Turret and Valve

Pipe Line

Hydraulic Chamber

Hydraulic Chamber (New)

Slurry Pit

MoU on Slurry Processing and Marketing

Slurry Processing

Water Drain

Burner
.

Using Biogas in a Tea Stall