Renewable energy related publications
(
Common)
Study on the Present Power Supply
Situation and its Impacts on the Readymade Garment
Sector in
Abbreviation..........................................................................................................................
1-2
Glossary................................................................................................................................
1-1
Executive Summary
.............................................................................................................
1-5
Chapter-1: The
Study..........................................................................................................
..1
1.1
Background................................................................................................................
..1
1.2
The
Study.....................................................................................................................
3
1.3
Methodology..................................................................................................................
3
1.3.1 Data/Information
Collection.................................................................................
3
1.3.2 Study
Population..................................................................................................
3
1.3.3 Study
Area...........................................................................................................
4
1.3.4 Sample
Size........................................................................................................
4
1.3.5 Allocation of Samples and
Calculations..............................................................
4
1.3.6 Instruments
Used................................................................................................
5
1.4
Implementation.............................................................................................................
5
1.4.1
Planning...............................................................................................................
5
1.4.1.1 Design, Pre-test and
Finalization of Survey
Instruments........................ 5
1.4.1.2 Recruitment and
Training of Field
Staff...................................................
6
1.4.2 Field
Work...........................................................................................................
6
1.4.3 Data
Management...............................................................................................
6
1.4.3.1 Recording of Filled
Instruments..............................................................
6
1.4.3.2 Editing of Filled-in
Questionnaire.............................................................
6
1.4.3.3 Preparation of Data
Entry
Format...........................................................
6
1.4.3.4 Data
Entry................................................................................................
7
1.4.3.5 Data Analysis
..........................................................................................
7
1.4.3.6 Focus Group Discussion
…………………………………………………. 7
1.4.3.7 Key Informants
Interview …………………………………………………..7
1.5
Limitations of the Study
...............................................................................................
8
Chapter-2: National Power
Demand and Supply Situation in
2.1
Market Composition, Spread and
Saturation...............................................................
1
2.2
Power Demand and Generation
Capacity...................................................................
1
2.3
Shortfall in Generation
Capacity...................................................................................
2
2.4
Load Shedding and its Impact on National
Economy..................................................
7
2.5
Load
Management........................................................................................................
8
2.6
Seasonal Variation of Load
factor................................................................................
8
2.7
Prospect of
Mitigation...................................................................................................
9
2.8
Prospect for Improvement of Power
Supply..............................................................
10
Chapter-3: Demand and Supply
of Power in RMG Factories...........................................
1
3.1 Present Electrical
Load......................................................................................................
1
3.1.1
Lighting......................................................................................................................
1
3.1.2
Machines...................................................................................................................
2
3.1.3 Fans and
Blowers.....................................................................................................
3
3.1.4
Air-conditioners..........................................................................................................
4
3.1.5 Other Electrical
Loads...............................................................................................
7
3.1.6 Estimation of Total
Present Demand of RMG
Industries.......................................... 7
3.1.7 Future Growth of Power
Demand of RMG
Industries...............................................
6
3.2 Power Supply to Garment
Industries.................................................................................
7
3.3 Power Demand and Supply
Situation of Garment
Factories............................................. 7
Chapter-4:
Capacity of Captive and Standby Generation and
Consumption of Primary Energy by RMG Sector and its
Financial Implication
....................................................................................
1
4.1 Capacity of Captive and
Standby Generation of RMG
Sector........................................... 1
4.2 Use of Diesel for Own
Generation as Standby
Power.......................................................
1
4.3 Use of Gas for Own
Generation as Captive
Power...........................................................
1
4.4 Financial Implication due
to Use of Diesel for Own
Generation......................................... 2
Chapter-5: Load Shedding and
its Impact on RMG Industries
....................................... 1
5.1
Load
Shedding..............................................................................................................
1
5.1.1 Frequency and
Impact.........................................................................................
1
5.2
Loss of
Production.......................................................................................................
1
5.3
Interruption due to
Holidays/Strikes..............................................................................
2
5.4
Investment in Standby/Captive
Generation..................................................................
2
5.5
Higher Production Cost in a Competitive
Environment................................................
2
5.6
Cost of ENS (Energy Not Served) to Garment
Factories............................................ 2
5.7
Loss of
Revenue..........................................................................................................
3
5.8
Decreased Competitiveness and Lost
5.9
Wasted Energy and Cost of Alternative Power
Generation......................................... 3
5.10
Damage of Equipment/ Decreased Equipment
Life....................................................
3
5.11
Mitigation of Power Supply Crisis due to Load
Shedding............................................. 4
5.11.1 Load Management
............................................................................................
4
Chapter-6:
Recommended Strategies and Action Plans for in Improving
the Power & Energy Supply in RMG Sector
...........................................................................................................................
1
6.1
Current Difficulties and
Prospects...............................................................................
1
6.2
Recommendations.......................................................................................................
2
6.2.1 Short Term (Fast-track)
Actions.........................................................................
2
6.2.2 Medium Term
Actions.........................................................................................
3
6.2.3 Long Term
Actions..............................................................................................
4
6.2.3.1
Strategy...................................................................................................
4
6.2.3.2 Action
Plans............................................................................................
5
Tables:
Table 1.1
:
Concentration of RMG Industries
Table 2.1
:
Demand Forecast and Demand Served
Table 2.2
:
Installed Capacity, Generation Capability, Demand
Forecast, Demand Served and Load Shedding
Table 2.3
:
Load Forecast and Net Planned Generation Capacity
Table 2.4
:
3-year Generation Addition Program
Table 3.1
:
The Category-wise Estimated Lighting Loads
Table 3.2
:
The Category-wise Estimated Machine Loads
Table 3.3
:
The Category-wise Estimated Fan and Blower Loads
Table 3.4
:
The Category-wise Estimated Air Conditioner Loads
Table 3.5
:
The Estimated Total Present Demand
Table 5.1
:
Estimation of Total Cost of Generation due to Load
Shedding
Figures:
Figure-1
:
Figure-2
:
Annexure:
Annexure-A
:
Terms of Reference
Annexure-1.1 :
Sample Questionnaire
Annexure-3.1 :
RMG Survey Database
Annexure-3.2 :
Calculated Average Load Demand
Annexure-3.3 :
Determination of Estimated Present Demand of RMG
Factories in Operation
Annexure-3.4 :
Forecast of Expansion of RMG Industries in
Annexure-3.5 :
Determination of Lighting Load of RMG Factories in
Operation
Annexure-3.6 :
Determination of Machine Load of RMG Factories in
Operation
Annexure-3.7 :
Determination of Fans & Blowers Load of RMG Factories in
Operation
Annexure-3.8 :
Determination of Air Conditioners Load of RMG Factories
in Operation
Annexure-3.9 :
Determination of Office Equipment Load of RMG Factories
in Operation
Annexure-3.10:
Lighting Load of a Large Size, Medium Size and Small
Size Factory
Annexure-3.11:
Mechanical Load of a Large Factory, Medium Factory and
Small Factory
Annexure-5.1 :
Chronological Record of Load Shedding of May 2008
Annexure-6.1 :
Number of Machines wise Distribution of RMG (Knit,
Sweater, Woven and Mixed)
ABBREVIATIONS
|
AC |
: |
Alternating Current |
|
ADB |
: |
Asian Development Bank |
|
AMP |
: |
Ampere |
|
APPAREL |
: |
Designed Dresses Like
Coats etc. |
|
BGMEA |
: |
|
|
BKNEA |
: |
|
|
BBS |
: |
|
|
BAPEX |
: |
|
|
BDT |
: |
Bangladeshi Taka |
|
BOGMC |
: |
|
|
BPDB |
: |
|
|
CFL |
: |
Compact Fluorescent
Lamp |
|
CC |
: |
Combined Cycle |
|
DESA |
: |
|
|
DESCO |
: |
Dhaka Electric Supply
Company Limited |
|
FY |
: |
Financial Year |
|
FGD |
: |
Focus Group Discussion |
|
FTL |
: |
Fluorescent Tube Lamp |
|
KII |
: |
Key Information |
|
GDP |
: |
Gross Domestic Product |
|
GJ |
: |
Gigajoule |
|
GOB |
: |
Government of |
|
GTCL |
: |
Gas Transmission
Company Limited |
|
GWH |
: |
Gigawatt Hour |
|
IOC |
: |
International Oil
Company |
|
IPP |
: |
Independent Power
Producer |
|
kA |
: |
Kiloampere |
|
KCAL |
: |
Kilocalorie |
|
kJ |
: |
Kilojoule |
|
km |
: |
Kilometer |
|
KNITWEAR |
: |
Knitted Fabrics |
|
kV |
: |
Kilovolt |
|
kVA |
: |
Kilovolt Ampere |
|
kVAR |
: |
Kilovolt Ampere
Reactive |
|
kW |
: |
Kilowatt |
|
kWH |
: |
Kilowatt Hour |
|
MJ |
: |
Megajoule |
|
MMSCFD |
: |
Million Standard Cubic
Feet per Day |
|
MVA |
: |
Megavolt Ampere |
|
MVAR |
: |
Megavolt Ampere
Reactive |
|
MW |
: |
Megawatt |
|
MWH |
: |
Megawatt Hour |
|
NPV |
: |
Net Present Value |
|
OPEC |
: |
Organization of
Petroleum Export Countries |
|
O&M |
: |
Operation and
Maintenance |
|
PBS |
: |
Palli Biddut Samity (a
form of rural electrification cooperative) |
|
PCB |
: |
Project Concept Paper |
|
PGCB |
: |
Power Grid Company of
Bangladesh Limited |
|
PP |
: |
Project Pro-forma |
|
REB |
: |
Rural Electrification
Board |
|
SCF |
: |
Standard Cubic Foot |
|
SCGT |
: |
Simple Cycle Gas
Turbine |
|
TSCF |
: |
Trillion Standard Cubic
Feet |
|
TOR |
: |
Terms of Reference |
|
|
: |
|
|
US |
: |
|
|
WOVEN |
: |
Fabric Clothes |
|
EU |
: |
European Union |
|
|
: |
United State of |
|
RMW |
: |
Ready Mode Warmth |
|
PSMP |
: |
Power Sector Master
Plan |
|
ENS |
: |
Energy Not Served |
|
USAID |
: |
|
|
BPDB |
: |
|
|
SPP |
: |
Small Power Plant |
|
CCPP |
: |
Combined Cycle Power
Plant |
|
MMCFD |
: |
|
|
RPCL |
: |
|
|
NEPC |
: |
|
Chapter-1
The Study
1.1
Background
Ready-made Garments (RMG)
sector is grappling with looming power crisis. The
impact of frequent outage of electricity has been
detrimental to growth of this sector as well as national
economy. Bracing all odds, the sector made
significant strides despite serious power interruptions.
Presently, the power situation
has further deteriorated, due to a shortfall in supply
of natural gas which is reportedly depleting fast. The
country is reeling under a daily ‘load-shedding’ that
ranges between 600-1,200 MW, the average being of the
order of about 1000 MW.
Energy and power, on the other
hand, are very basic inputs to industrial production in
general and to the Readymade Garment (RMG) industries in
particular, in which over 20% of the production costs
are on account of the costs for energy. The power
consumption in a typical RMG industry is predominantly
divided into lighting and sewing operations, both of
which are critical to productivity.
The cost of power
failures/load-shedding are very high and its impacts are
reflected through loss of production, machinery
depreciation, cost of alternative (emergency generator)
fuels, like diesel, impact on the continuity of
production lines and a series of high cost consequential
damages, including delays in shipment schedules, loss of
commitment and business goodwill, which can often be
irreversible. The cost of not supplying power to the
production units is as high as Tk.15-30 per kWh.
However, surveys/studies need to be conducted with
reference to specific and nationally important
production sectors as the RMG, to quantify such
economic/ financial impacts, which are necessary as
valuable feedback for a ‘course-correction’ for
nationally initiating appropriate strategies and action
plans to improve such unacceptable power/energy
situations.
With this end in view,
Bangladesh Garments Manufacturers Association (BGMEA)
decided to take up a study in order to measure and gauge
the impacts of power situation on the readymade garment
sector in
650 factories were selected at
random during this study for sample survey. From the
survey data, database was prepared and on the basis of
this data were generated for 2509.
For the study, BETS Consulting
Services Ltd. was engaged by BGMEA as a consultant under
the following terms of reference (TOR):
(1)
To identify and quantity
the National Demand-Supply for Power
vis-à-vis the same specific to the ‘micro’ sector under
question i.e. the RMG Industries.
(2)
Estimate the power
consumption of RMG Industries, based on
representative sampling of 25% of the operating RMG
Industries (taking the total updated number of
operating RMG industries in the country). Also, work out
the specific power consumption.
(3)
Typical 24-hour
load-profile (Sub-station support in a
sampling area of populated RMG Industries may be geared
up for this).
(4)
Typical Electrical load
and consumption (with approximate
average hours of operation of the following in RMG
factories:
-
Lighting (Type of lights, their
numbers, type of ballasts used, i.e. whether magnetic
electronic etc.)
-
Electric Motors (with
production/sewing machines)
-
Fans/Blowers (e.g. Exhausts,
Boiler forced draft fans)
-
Air-conditioners
-
Other Electrical loads (to be
specified)
(5)
Capacity & Consumption
profiles of other Primary and Secondary
Energy (Natural Gas, Petroleum Fuels, Steam, Hot Water
etc.)
-
Natural gas for Captive Power
Generation (e.g. Gas Engines); kW and kWh
-
Diesel (Standby or Emergency)
generators-Capacity (kW) and Consumption kW including
the volume of diesel and costs (average litres/costs).
-
Steam requirements/consumption,
including natural gas use/cost for same
-
Hot water requirements, if any
(e.g. for Washing Plants).
(6)
‘Load-shedding’ – its
frequency and profile (over typical
production routine of RMG industries), vis-à-vis
national ‘load-shedding’ and also seasonal profile of
load-shedding (e.g. summer/winter, irrigation seasons
etc.), based on last 2-3 years operational experience.
(7)
Collect information/data
from the sampled RMG operators and analyze/evaluate and
study the Impacts of the present Power & Energy
supply situation, including, but not
limited to the following aspects, both in
physical/technical and/or financial terms:
· Loss
of production caused by power interruption
·
Interruption due to holiday staggering policy in
different areas
·
Production & financial losses and machinery depreciation
due to use of standby generators.
·
Damages of equipment
· Other
consequential losses, such as:
-
Labor and line managers’
motivation and productivity
-
Loss of goodwill due to
commitment failure
-
Impact and lead time
(8)
Potential Threats
to sustainable growth of RMG sector due to
lack of power
(9)
Relevant Policy Analysis
in the light of interest of the RMG sector
(10)
Recommended Strategies &
Action Plans for improving the Power & Energy supply
situation (energy security) in the RMG sector:
·
‘Fast-track’ (short term)
solutions (example: Energy Efficiency)
·
Medium Term measures (example;
Cogeneration-captive power & steam/hot water from waste
heat of captive power plants
·
Long term solutions/best
practices (Industrial Parks/Mono-economic Zones).
1.2
The Study
The basis of the report is the
survey and study that was taken up by the consultants
during the period, August through October 2008. The
study was supported by BGMEA and Gtz, German Technical
Assistance Programme. However, this does not include the
factories under BKMEA.
This report is an account of
looming power crisis and its consequential effect on the
ready made garment sector of
1.3
Methodology
Methodology is the most
important component in any study since it explains the
procedure and methods through which a particular study
was carried out. The chapter includes a discussion on
study population, sampling frame, sample size, stages of
sample selection, methods of data collection, data
compilation, data analysis and data quality etc.
1.3.1 Data /
Information Collection
Data are the raw materials for
any study. Relevant data for the study were collected
from both secondary and primary sources. Secondary data
were collected from BGMEA, BBS, PDB, DESA etc. The
collected secondary data were reviewed and analyzed in
the office by the consultants. The consultants also
reviewed all sorts of RMG/Industrial operation, impacts
due to power interruption, scope for improvement and
measures to be undertaken for it.
Two types of primary data were
collected in the study-quantitative and qualitative.
Quantitative data were gathered from survey of active
RMG factories using random sampling procedures.
Qualitative data were collected from Key Informant
Interviews (KIIs) and Focus Group Discussions (FGDs).
1.3.2 Study
Population
As of June 2008, there are
about 4075 members of BGMEA. Out of them, about 60% are
woven manufacturers, 22% knitwear manufacturers and the
remaining 18% sweater producers. But all these members
are not active, 64% of them are active. The active BGMEA
members constitute the main study population of our
study.
1.3.3 Study
Area
The RMG factories constituting
study population are mostly located in and around Dhaka
and
Table 1.1- Concentration of RMG
Industries
|
|
Woven |
Knitwear |
Sweater |
Total |
|
|
1769 |
657 |
535 |
2961 (72.7 %) |
|
Narayanganj |
34 |
70 |
11 |
115 (2.8 %) |
|
Gazipur |
73 |
48 |
67 |
188 (4.6 %) |
|
Subtotal: |
1876 |
775 |
613 |
3264 (80.1 %) |
|
|
521 |
86 |
73 |
680 (16.7 %) |
|
Others |
67 |
19 |
45 |
131 (3.2 %) |
|
Total |
2464 (60.5 %) |
880 (21.6 %) |
731 (17.9 %) |
4075 (100 %) |
Source:
BGMEA Member List, Supplied by BGMEA
1.3.4 Sample
Size
According to the Terms of
Reference (TOR), the survey should cover at least 25% of
the active RMG manufacturing factories at Dhaka and
1.3.5
Allocation of Samples and Calculations
The samples for the survey were
selected using three stage stratified sampling scheme
(proportional allocation). In the first stage, the
samples were selected proportionately according to the
region- that is the stratums are Dhaka and
Survey was conducted over 319
RMG factories and average load was calculated over 319
factories. The total population size was 2509 active
factories. However, the area wise list of RMG factories
was available and all calculations were done in
accordance with area.
Loads for lighting, machines,
fans and blowers, air-conditioners and other electrical
loads were also calculated. Load of different items as
above, were calculated from field survey data, averaged
over 319 surveyed factories, and applied to 2509 active
factories
Factories were classified as
K1-knitting small, K2-Knitting medium, and K3-knitting
large S1-sweater small, S2-sweater medium, and S3-sweter
large and W1-Woven small, W2-woven medium, and W3-woven
large, WK1-woven-knitting mixed small,
WK2-woven-knitting/mixed medium, and WK3-woven-knitting
mixed large. City wise factory list was available and so
calculations were done area wise.
Number of Machine wise
distribution of Knitting, Sweater, Woven and mixed
(Woven-Knitting) are represented graphically in
Annexsure-6.
Group samples are defined as
follows:
Knitting small
(K1) - Small knitting factories having up to 150
machines,
Knitting medium
(
Knitting large
(K3) - Large knitting factories having 400 machines and
above,
Sweater small
(S1) - Small sweater factories having up to 150
machines,
Sweater medium
(S2) - Medium sweater factories having 150 to 400
machines,
Sweater large
(S3) - Large sweater factories having 400 machines and
above,
Woven small
(W1) - Small woven factories having up to 150 machines,
Woven medium
(W2) - Medium woven factories having 150 to 400
machines,
Woven large
(W3) - Large woven factories having 400 machines and
above,
Woven-knitting mixed small
(WK1) - Small woven-knitting mixed factories having
Up to 150 machines,
Woven-knitting mixed
Medium.
(WK2) - Medium woven-knitting mixed factories having
150 to 400 machines,
Woven-knitting mixed large
(WK3) - Large woven-knitting mixed factories having
400 machines and above,
1.3.6
Instruments Used
Checklist
was used which provided pointers to the type of
information being sought. Also it was used to check
compliance with certain procedures, where ‘yes’ or ‘no’
answers can be given.
Focus Group Discussion (FGD)
was organized with owners and workers
of RMG manufacturers. A total of 5 Focus Group
Discussions were organized with workers in Dhaka and
Key Informants’ Interviews
(KII) was also conducted and information was
collected by interviewing knowledgeable persons in
various fields associated with RMG export. Apart from
informal consultations with a number of stakeholders,
three main interviews were carried out.
1.4
Implementation
For implementation the study
consists of 4 broad activities: planning, field work,
data management and report writing. Planning stage
includes recruitment and training of field staff;
design, pretest and finalization of instruments, and
determination of study samples. Field work includes data
collection and quality control. Data management includes
registration of filled in instruments in the office,
editing of filled in instruments, preparation of data
entry format, data entry and its verification, and data
analysis.
1.4.1
Planning
1.4.1.1 Design, Pre-test and
Finalization of Survey Instruments
Study instruments (survey
questionnaire, FGD guidelines and KII checklist) were
designed after giving due attention to the objectives
and scope of the study. Before design the consultants
reviewed the similar studies and also arranged some
brain-storming session. After design the
instruments were sent to BGMEA for comments.
Meetings were arranged between consultant team and BGMEA
to discuss about the instruments. The instruments were
pre-tested with some of RMG factories near
1.4.1.2 Recruitment and
Training of Field Staff
In order to undertake field
work, a total of 20 enumerators were recruited for a
period of 5 weeks including training period. 10 teams
were formed, each consisting one engineer and one
statistician. For conducting FGDs, two teams consisting
of two FGD facilitators and two note-takers were formed.
Note takers were recruited from among the graduates with
some experience, while FGD facilitators were recruited
from semi-professionals working in survey research. Key
Informants’ Interviews were conducted by the
consultants.
The consulting firm organized
an orientation and training course for the field staff
describing the objectives, importance and methodology of
the study. The training also conducted on collection,
identification, verification and recording of data on
questionnaire/instruments prior to sending the field
staff to the project areas. The trainees were guided to
arrive at solution of filling up questionnaire,
compilation and to fetch real information from the
survey population using personal skills and expertise.
After completion of the training the field enumerators
were led to the project areas.
1.4.2 Field
Work
The field staff collected data
according to the set program by personally visiting,
observing, interviewing and recording data from relevant
respondents. They did not deviate from set program. The
collected data were sent to the office every week, where
in turn each filled in instrument were checked for
consistency. Errors, if detected were rectified.
Besides, the consultant team members also undertook some
field visit for quality checks.
1.4.3 Data
Management
Data management consists of 4
activities, which were performed under the leadership of
Data Management Specialist. Team Leader provided some
guidance. Data management activities were as follows:
-
recording of filled in
instruments in the office
-
editing of filled in instruments
-
preparation of data entry format
-
data entry
-
data analysis
1.4.3.1 Recording of Filled
Instruments
Each filled in instruments were
duly recorded in the office of BETS Consulting Services
Ltd. In
1.4.3.2 Editing of Filled-in
Questionnaire
Field edit was done by the
enumerator administering the questionnaire; verification
of information is also conducted by survey coordinator.
Each and every filled in questionnaire were checked for
error and consistency in the office. For serious error
if detected, the questionnaire were re-administered.
1.4.3.3 Preparation of Data
Entry Format
The data entry formats were
prepared with the help of MS ACCESS, versatile data
entry software. The format ensured correct entry of the
data. For open-ended responses the editors assigned code
numbers.
1.4.3.4 Data Entry
Data from the filled in
questionnaires were entered by the trained entry
operators according to data entry plan. At the end of
the day operators handed over the data to the Data
Management Specialist, who prepared up to date situation
for information. Using some consistency check, data
entry was verified.
1.4.3.5 Data Analysis
The data analysis was carried
out using SPSS. The team leader prepared the format of
output tables and the data analyst brought out the
analytical output in tabular as well as graphical form
where required.
The machine loads for different
type of factories like knitting, sweater, woven and
woven-knitting mixed for respective large, medium and
small sizes were calculated using database and are
compiled in Annexure 5.1. With average values
from Annexure 5.2, the category-wise present
demand for machine loads of active industries was
calculated.
It may be mentioned here that,
this survey did not include the factories under BKMEA.
From the sample survey carried out in 319 factories,
demands of each factory were determined by counting
method applying appropriate demand and diversity
factors. Counting was applied on every element of power
consuming devices such as lights, fans, machines,
exhaust fans, air conditioners etc. The database of the
survey is presented in Annexure-3.1.This includes
the terms B code and the name of RMG industry, its
location, type size TS i.e. small, medium and large,
types of RMG industry, i.e. knitting, sweater, woven and
woven-knitting mixed. The power demand in watt (TPDW)
has been calculated in accordance with types of devices.
From the survey data, database
was prepared and on the basis of this data were
generated for 2509 active factories classified into
small, medium and large, under respective types of i)
woven, ii) knitwear iii) sweater and iv) woven-knitting
mixed. The mixed are where weaving, knitting, dying,
calendaring and readymade garments are prepared.
Further classifications were
made on the basis of number of machines, which are
supposed to be determinant variables for other
electrical loads such as lights fans, etc. Accordingly,
different types of factories were further grouped in
small, medium and large factories to include their
respective average demands. The calculated average load
demands for knitting, sweater, woven and woven-knitting
mixed industries for small, medium and large groups have
been applied to total population.
1.4.3.6 Focus Group Discussion
Five Focus Group Discussions
were held with workers. The sessions were attended by
15-20 workers representing different garment factories.
The study team also organized an interactive session
with RMG stakeholders in order to validate and share
some of the key findings of the study. A
Focus Group Discussion (FGD) was held at
1.4.3.7 Key Informant’s
Interview
Eight key informants were
interviewed from DESA, DESCO and Power Cell. The
Key Informant Interview (KII) was conducted in order to
elicit relevant information on issues being
investigated. Interviews were undertaken with key
personal, having sound knowledge on power sector, in a
dynamic and interactive environment. Discussion went on
in an exploratory fashion. The selection criteria for
interviewees were based on their responsibilities and
function and involvement in the sector. Key Informant
Interview didn’t provide much information and enabled
the study team to gain further insights into the
pertinent issues. (The findings of Key
Informant Interview has been summarized in Annex-B).
1.5
Limitations of the Study
The study resulted in huge
number of non-responses. Out of 650 samples, information
of only 319 was obtained, the other factories refused to
give any information. The enumerators visited those
non-responsive RMG factories several times, but due to
non-cooperation from the authorities of the selected RMG
factories, they failed to collect any information.
Chapter-2
National Power Demand
and Supply
Situation in
Bangladesh
2.1
Market Composition, Spread and Saturation
Investment Climate Assessment
(2004) report describes that seventy–eight percent of
firms have identified electricity as a major impediments
on their road map to expansion. However, the garment
industries rely heavily on small scale back-up
generators for keeping their production ongoing and
avert the consequential effects. It was revealed
during key informant interview that more than 30%
generation capacity is “captive”. There is a huge gap
between incremental growth of demand and generation. The
power sector reform policies have crept onto agenda
since 1996. Over the years, several changes have taken
place. Independent Power Producers (IPP), alongside
state-owned facilities, came forward since 1997-1998.
However, IPP investment was thwarted and made no
meaningful progress to9 make up deficits.
Electric power supply is
provided by various utility organizations in their
respective areas. The market is composed of residential,
agricultural, commercial, industrial and institutional
consumers. The respective shares of energy are 43%, 4%,
7.5%, 43.6% and 1.9%, as of 2005. Garment industries are
included in industrial category.
Consumers are also classified
for voltages such as low tension, high tension, extra
high-tension etc. Consumers having demand above 49kW
must receive their supply at 11kV, those above 2500kW at
33kV. There exists peak hour tariff from 5 pm to 11pm.
Small garment factories receive power at low voltage
(400/230 volts) and large to medium factories at high
voltage (11kV).
Electricity supply has been
extended to about 33-35% of population so far. From per
capita generation of 170kWh, it may be assumed that the
electricity market is far from saturation, and demand
will therefore to increase at the stipulated rate.
2.2
Power Demand and Generation Capacity
Power Sector Master Plan-1995
would be referred to for comparison according to which
generation expansion programme is supposed to have taken
up for implementation.
Power Demand
The actual power demand against
forecast demand by PSMP (Power Sector Master Plan) 1995
from FY 1995 to 2007 are shown in the Table 2.1.
Table – 2.1:
Demand Forecast and Demand
Served
|
FY |
PSMP 1995 Demand Forecast Gross
(MW) |
Predicted Growth Rate |
Demand Served (MW) |
Actual Growth Rate |
|
1995 |
2,038.00 |
|
1,970.00 |
|
|
1996 |
2,220.00 |
|
2,087.00 |
|
|
1997 |
2,419.00 |
|
2,114.00 |
|
|
1998 |
2,638.00 |
|
2,136.00 |
|
|
1999 |
2,881.00 |
|
2,449.00 |
|
|
2000 |
3,149.00 |
|
2,665.00 |
|
|
2001 |
3,394.00 |
|
3,033.00 |
|
|
2002 |
3,659.00 |
|
3,217.50 |
|
|
2003 |
3,947.00 |
|
3,428.00 |
|
|
2004 |
4,259.00 |
|
3,592.00 |
|
|
2005 |
4,597.00 |
|
3720.80 |
|
|
2006 |
4,967.00 |
|
3782.00 |
|
|
2007 |
5,367.00 |
8.40% |
3717.80 |
5.43% |
Source:
PSMP-1995
It may be seen from the
historical data of demand served that weighted average
compound rate of growth has been only @5.43% per annum
during the last 13 years. The growth is much lower than
the forecast (8.4%) as per Power System Master Plan-1995
study. This is due to shortage of supply (generation) to
meet the demand that existed. Actual demand is seen to
have gone down in 2007 from that of 2006, which was
obviously due to shortage of available generation
capacity. It may be concluded that generation capacity
is too short to meet the demand of the market.
Generation Capacity
The total installed capacity as
of August 2008 was about 5405 MW including IPP in
utility service. There are about 550 MW in captive
generation capacity (excluding those having unit
capacity less than 500 kW) owned by industries. The
plants are predominantly thermal, and natural gas fired.
Natural gas is an indigenous fuel. The largest size is
450MW of combined cycle power plants and smallest is of
10MW unit of diesel generators. Since power sector
reforms in 1998, Independent Power Producers (IPP) have
been investing capital to build, own & operate power
stations. Total capacity under private ownership for
utility service is 1542 MW including small IPP and
rental, i.e. 28% of total. The largest power station so
far built is the Meghnaghat Power station with a
capacity of 450MW in one block. Estimated capability is
about 4300 MW, out of this, daily availability is only
about 3700 MW.
2.3
Shortfall in Generating Capacity
Against current demand of about
5000 MW estimated, an average of about 1000 MW has
fallen short in capability out of 5400 installed
capacity due to old age. Additionally, about 1300 MW has
fallen short in availability out of 4400 MW of
capability due to lack of maintenance and shortage of
gas supply.
Table-2.2 shows that Maximum
available generation capacity were fully utilized to
meet only part of the demand, since FY2000, that is,
demand had remained supply constrained during eight
years since FY2000. It is interesting to note that
generation capability available has constrained the
supply. It is further seen that in FY 2006-2007, maximum
load shedding was 1345 MW. This is attributed to failure
in implementing the proposed power plants, over the
years.
Table – 2.2:
Installed Capacity, Generation
Capability, Demand Forecast,
Demand served and Load
Shedding.
|
Year |
Installed Capacity (1) (MW) |
Generation Capability
(2) (MW) |
Total Demand Forecast (3) |
Demand Served (4) (MW) |
Load Shedding (MW) (5) |
|
|
Max |
Min |
|||||
|
1994-95 |
2,908.00 |
2,133.00 |
2,038.00 |
1,970.00 |
537 |
10 |
|
1995-96 |
2,908.00 |
2,105.00 |
2,220.00 |
2,087.00 |
545 |
10 |
|
1996-97 |
2,908.00 |
2,148.00 |
2,419.00 |
2,114.00 |
674 |
20 |
|
1997-98 |
3,091.00 |
2,320.00 |
2,638.00 |
2,136.00 |
711 |
32 |
|
1998-99 |
3,603.00 |
2,850.00 |
2,881.00 |
2,449.00 |
774 |
16 |
|
1999-00 |
3,711.00 |
2,665.00 |
3,149.00 |
2,665.00 |
536 |
10 |
|
2000-01 |
4,005.00 |
3,033.00 |
3,394.00 |
3,033.00 |
663 |
15 |
|
2001-02 |
4,230.00 |
3,217.50 |
3,659.00 |
3,217.50 |
367 |
5 |
|
2002-03 |
4,680.00 |
3,428.00 |
3,947.00 |
3,428.00 |
468 |
5 |
|
2003-04 |
4,680.00 |
3,592.10 |
4,259.00 |
3,592.00 |
694 |
2 |
|
2004-05 |
4,995.00 |
3,720.00 |
4,597.00 |
3720.80 |
770 |
7 |
|
2005-06 |
5,245.00 |
3,782.00 |
4,693.00 |
3782.00 |
1312 |
15 |
|
2006-07 |
5,202.00 |
3,717.80 |
5,367.00 |
3717.80 |
1345 |
40 |
Source:
BPDB Annual Report 2006-2007
1
Installed capacity as of June of the fiscal year
2
Generation capability is the maximum available
generation capacity in the year.
3
Gross Demand forecast is the Base Forecast of Power
System Master Plan, 1995.
4
The dates of maximum demand served and maximum available
generation capacity may not be the same.
5
Load shedding is the range of maximum and minimum
throughout the year.
A comparative study of load
forecast, generation additions plan (PSMP-1995), and
actual achievement between 1995 and 2007 shows
(Table-2.3 and Chart- 2.1) a wide gap between
planned generation capacity and actual achieved. This
explains the present crisis.




Chart-2.2: DAILY LOAD CURVE
Date : Sun 06-Jul-08

![]()
Chart-2.3: DAILY LOAD CURVE
Date : Tue 06-Jan-09
![]()

![]()



Table-2.3:
Load Forecast and net planned
Generation Capacity
(As per Power System Master
Plan Study, 1995)
|
FY |
Load Forecast Gross MW |
Growth Rate % |
Planned Generation Capacity (1) MW |
Growth Rate % |
Actual Capacity (2) Achieved MW |
Growth Rate % |
|
1995 |
2038 |
|
2251 |
|
2908 |
|
|
1996 |
2220 |
|
2339 |
|
2908 |
|
|
1997 |
2419 |
|
2402 |
|
2908 |
|
|
1998 |
2638 |
|
2780 |
|
3091 |
|
|
1999 |
2881 |
|
3358 |
|
3603 |
|
|
2000 |
3149 |
|
3550 |
|
3711 |
|
|
2001 |
3394 |
|
4021 |
|
4005 |
|
|
2002 |
3659 |
|
4399 |
|
4230 |
|
|
2003 |
3947 |
|
4748 |
|
4680 |
|
|
2004 |
4259 |
|
5137 |
|
4680 |
|
|
2005 |
4597 |
|
5572 |
|
4995 |
|
|
2006 |
4693 |
|
6356 |
|
5245 |
|
|
2007 |
5367 |
8.4% |
6786 |
9.6% |
5202 |
5% |
(1)
Net after station use.
(2)
Gross generation
capacity
2.4
Load Shedding and its Impact on National Economy
The power supply is now in a
crisis. This will continue to worsen further beyond
2008. Steps taken now for increasing generation capacity
can not make up the lost opportunities of past years.
There has been prevailing an
acute generation shortfall vis-à-vis power demand of the
country for the last 7 years. So, nationwide power
supply system is facing inevitable load shedding. Load
shedding has to be resorted to in order to save the
generators from damage due to over load. No consumer
groups are spared except the agricultural consumers
during irrigation season from February-March. To effect
load shedding the 11kV and 33kV feeders are switched off
from the substations by the distribution companies as
required by the National Load Dispatch Centre when
situation arises.
Impact of Load Shedding
The load shedding implicates
among others, energy shedding as well. This attributes
to Energy Not Served (ENS) to all categories of
consumers. The overall cost of ENS in the amount of ENS
times its unit cost. The unit cost is a measure of the
economic impact of not meeting the electricity demand.
In other words, the unit cost of ENS is the costs that a
consumer does incur when electricity is not available
that he would avoid if electricity were available,
divided by his amount of ENS. The economic impact that
may come from interruption to industrial output,
commercial activity, residential services and public
safety are extremely costly and some are inherently
difficult to quantify. A simple approach is to find out
the cost of alternative generation for all the aforesaid
activities to be sustained. The Power System Master Plan
(PSMP) study, 2005 adopted the above method to quantify
the unit cost of ENS which is $0.43 per kWh i.e.
equivalent to about Tk.30.00 per kWh (1US$= Tk.70.00).
This implies that if a consumer is deprived of one unit
of energy (kWh) he has to incur a cost of Tk.30.00 for
that. This study estimates for unit cost of ENS for
garment industries of about Tk.15.00/kWh.
2.5
Load Management
Load management is the tool to
modify energy usage to maximize energy efficiency. It
derives benefit out of existing energy resources.
Load management is no doubt a
good initiative for meeting demand in the peak hours. It
is a method meeting the demand without new investment.
Load shedding by switching off feeders is not really
load management. Rather, load management helps reduce
load shedding to a minimum level and improve load
factor. Power usage pattern determine load factor. It
also depends on socio-economic as well as cultural
pattern of a society or country. In
Historically daily load curve
was characterized by two peaks, smaller peak occurring
in the mid-morning and the higher one in the early
evening. It is never practical to achieve a technically
ideal flat load curve for the electric utility. BPDB
took efforts in the past to improve performance of the
system by adopting measures to shift the peak and to
reduce capital investment on peak power generation.
Measures taken for Load
Management
The following are some measures
that have been taken to control peak hour demand:
a)
Shifting irrigation load from
peak hour to off peak hour.
b)
By rationalizing the use of
electricity by all consumers by switching off the
non-essential loads e.g. iron, air-conditioners, welding
machines etc. during peak-hour.
c)
Operating industries having two
shifts during off peak hour.
d)
Operating large commercial
customers like shopping malls using own Generation.
e)
Closing the commercial
establishments at 8 P.M.
f)
Staggering the holidays area-wise
in different weekdays for different category of
consumers.
g)
Motivating the consumers to use
Compact Fluorescent Lamps (CFL) replacing the
conventional incandescent lamps.
Some effect of the above must
have taken place, but it is difficult to identify the
same as simultaneous load shedding at peak hours
over-shadows the effect of load management. However,
from the daily load curves of recent years it appears
that usage pattern of electricity has taken place quite
significantly. From the fact that loads are being shed
in the mid-night, it is concluded that many consumers
have shifted from evening to mid-night.
The present load curve of April
21, 2007 and previous load curves of 1994 and 2000 may
be seen in Chart-2.2, 2.3, 2.4, 2.5, 2.6 and 2.7.
2.6
Seasonal Variation of Load Factor
An investigation of daily load
curves of year 2000 (Chart-2.3) was carried out.
Past seven years were excluded from the study. From the
seasonal variations in load curves, it is seen that
nightly load was much depressed in winter and load
feeder was also lower by 15 percentage points than in
summer. Winter weekday nightly load appears to have
fallen to 65% of peak. Thus more load i.e. more
consumers could be accommodated in the nights from 12mn
through 4pm. That means, more load from evening peak
hours (5 pm-11pm) could be shifted to 12mn to 8am to
4pm. However, this is a short period of two months-
mid-December to mid-February next year only.
Domestic loads cannot be
shifted, only industrial loads, such as garment
factories if any, operating in the evening, could be
shifted to mid-night. However, due to acute shortage of
generation capacity in the recent years, the daily load
curve pattern has changed. Therefore, seasonal variation
has no significance any more.
2.7
Prospect of Mitigation
In the midst of this dismal
situation, investigation was made in order to understand
the prospect of mitigating this situation. Foreign
direct investment has been taken place since 1998 by
participation of foreign IPPs. This has also slowed down
since 2001. Thus the generation addition programmes have
suffered an unprecedented set-back due to fund shortage.
In 2000, BPDB undertook a program to raise generation
capacity to 7463MW, 5413MW in public sector and 2050MW
in private sector, but this program could not be
implemented. Later on, Government developed a Power
Sector Master Plan in 2005 for addition of 17,700 MW of
generating capacity by 2025. This envisaged a short-term
programme of setting up 3500 MW new capacity during
2005-2010. But no significant progress has been made
towards this. To overcome this situation, a new 3-year
generation addition plan was undertaken in 2007.
The plan stipulates a total of
4322 MW to be added by 2012. Out of these, some small
IPP and rental power plants have been commissioned so
far (200MW). The effect of generation addition of about
537MW by December 2008, on present load shedding problem
would be partial and will not last long. Due to
uncertainties of large plants including 150MW projects,
only about 1802MW may be implemented by 2012. With
increasing load demand, currently estimated at about 450
MW per year, this cannot raise the generation capacity
to desirable level to improve power supply by 1012.
Gas Constraint for Power
Generation
Recent report of power system
operation of 22 Sept, 2008 shows Haripur 100MW, Raozan
No.1 210MW, Sikalbaha steam 60MW have been kept out of
operation on account of shortfall in gas supply. In
addition, a total of 444MW was short generated at
6 power plants of Ghorasal, Raozan # 2, RPCL,
Siddhirganj 210MW, Haripur 360MW combined cycle, NEPC
Haripur barge-mounted power plants.
Future Prospect for Gas
Gas situation may improve by
2011 marginally, when about 320 MMCFD would be added to
the existing production. This is not sufficient for the
generation capacity (over 400 MW) remaining out of
stream and new demand to come up. However, as per
Petrobangla substantial improvement is expected by the
year 2016. Therefore, prospect of new gas fired
power plant is bleak.
Coal Resources
It is estimated that an annual
production of 1.0 million tons of coal will be available
from to feed 2x125 MW at the power plant of Barapukuria
for 30 years which is already in operation producing
about 5% of total utility sector electricity.
Extensive use of coal is
essential to substitute for gas. Addition of coal-fired
power plant depends on further mine development which
will take time. It took about 8 years to develop the
mine at Barapukuria. A coal fired steam power plant
takes about 4-5 years to implement after work order.
2.8
Prospect for Improvement of Power Supply
From the foregoing facts it may
be concluded that power supply situation could not be
improved unless fuel supply is ensured i.e. before 2016.
On the other hand long gestation period for development
of coal mines will also retard the desired power
development. Therefore, other alternative may be
investigated in to.
The shortage is attributed to
non implementation of generation addition programme due
to lack of adequate finance, delay in implementation,
lack of maintenance, aging of machines and shortage of
natural gas, the prime fuel for generation.
The fragile power supply
situation will continue to worsen further beyond 2008
even if steps are taken now for increasing generation
capacity. Program that is required to make up for lost
opportunities is too much to implement in too short a
time. This would continue to affect the industrial
growth and the economic development of the country.
However, substantial improvement is not expected before
2016.
Myriad of policies being framed
up by the government has not brought about any marked
changes in power generation scenario. Until 2006, the
policies being adopted by the government includes IPP
policy, Small Power Plant Policy, Captive Power Policy,
Power Sector Master Plan and Power Sector Reform Road
Map. However, most of these policies have either been
shelved or gaining dust. In stead of creating an
ambience for investments by private sector, deeply
entrenched institutional barriers shied away the
investors who came forward to make up the gaps in the
market. Having reviewed policy guidelines and
plans, we would like to identify the key factors which
may trigger the policy lobbying in order to ensure
uninterrupted power supply in RMG as well as other
industries.
Chapter-3
Demand and Supply of Power in
RMG Factories
3.1
Present Electrical Load
Database was compiled on the
basis of agreed classification (Chapter-2 sec-2.3.5)
with regard to types of factories such as (i) knitting
(ii) sweater (iii) woven and (iv) woven-knitting mixed.
From the sample survey, average demands for machines,
lighting etc. of a group of factories (say, small
knitting) have been calculated as representative models.
Then, this was multiplied by the number of factories of
this group, to calculate the total demand of the group.
The calculated average load demands for knitting,
sweater, woven and woven-knitting mixed industries for
small, medium and large groups are presented in
Annexure 3.2.
Findings of sample survey of
garment industries are summarized below.
3.1.1
Lighting
Lighting load for the different
type of industries like knitting, sweater, woven and
woven-knitting mixed for large, medium and small size
were calculated based on survey data. (Annexure 3.1).
The average lighting load demands for all categories of
industries were also calculated (Annexure 3.2.).
However, illumination recommended for such factories at
working level is 700 lux as per Bangladesh National
Building Code (1993).
The category-wise present
demand for lighting of 2509 active industries was
ascertained based on average values (Annexure 3.5).
The total present lighting load
demand for 2509 active industries comes to 74605 kW i.e.
about 75 MW and the corresponding energy consumption
comes to about 224 MkWh per year (Table-3.1).
Table-3.1:
The Category-wise Estimated
Lighting Loads
|
Sl No. |
Item |
Small kW |
Medium kW |
Large kW |
Total kW |
Energy Consumed MkWh |
|
1 |
Knitting |
1260 |
2535 |
7975 |
11770 |
35 |
|
2 |
Sweater |
66 |
693 |
19272 |
20031 |
60 |
|
3 |
Woven |
986 |
4017 |
27936 |
32939 |
99 |
|
4 |
Woven-knitting mixed |
323 |
1394 |
8148 |
9865 |
30 |
|
Total: |
74605 |
224 |
||||

Typical lighting load for
large, medium and small size RMG industries may be seen
in Table-3.1, 3.2 and 3.3 (Annexure 3.10).
3.1.2 Machines
The machine load is
predominantly the motor load of the different types of
machines used in an RMG factory. In an RMG factory, the
major load is required for the sewing section. The
sewing section is composed of a production line having
20-30 sewing machines each rated 0.25 kW at 220volts ac
in one line to complete a particular job. Cutting and
ironing section is also an integral part of the sewing
section. So, any shortage of power supply results in
shut down of a line of the sewing section resulting
stoppage of production. The motors are single-phase
motors with direct on line starting.
In RMG industries the cutting
section, sewing section and the ironing section
constitute total machine load. The machine loads for
different type of factories like knitting, sweater,
woven and woven-knitting mixed for respective large,
medium and small sizes were calculated using database
and are compiled in Annexure 3.1. The average
machine load demands for cutting, sewing and the ironing
sections for each of all types of industries were
calculated and compiled in Annexure 3.2. With
these average values from Annexure 3.2, the
category-wise present demand for machine loads of 2509
active industries were calculated and shown in
Annexure 3.6. The total present machine load demand
for the 2509 active industries come to 316609 kW i.e.
317MW and the corresponding energy consumption come to
about 950 MkWh per year (Table-3.2).
Table-3.2:
The Category-wise Estimated
Machine Loads
|
Sl No. |
Item |
Small kW |
Medium kW |
Large KW |
Total kW |
Energy Consumed MkWh |
|
1 |
Knitting |
2590 |
9464 |
47025 |
59079 |
177 |
|
2 |
Sweater |
108 |
1176 |
32850 |
34134 |
102 |
|
3 |
Woven |
5046 |
25956 |
157140 |
188142 |
565 |
|
4 |
Woven-knitting mixed |
238 |
9020 |
25996 |
35254 |
106 |
|
Total: |
316609 |
950 |
||||

![]()
![]()
![]()
Typical machine load for large,
medium and small size RMG factory may be seen in
Table 3.4, 3.5 and 3.6 (Annexure 3.11).
3.1.3 Fans
and Blowers
In an RMG factory a large
number workers are engaged in sewing and operating
machines continuously. The internal temperature of the
factory therefore rises to a great extent for which a
large numbers of ceiling fans as well as exhaust fans
and blowers are required for proper ventilation. These
fans and blowers remain are in continuous operation in
different sections of the factory, and as such, consumes
some energy. This power consumption is also very
essential for the factory workers to maintain their
health.
The load of fans and blowers in
different type of industries likes knitting, sweater,
woven and woven-knitting mixed for large, medium and
small size were calculated. (Annexure 3.1) The
average load demands for cutting, sewing and the ironing
sections of all types of industries were calculated (Annexure
3.2.) The category-wise present demand for fans and
blowers for 2509 active industries were calculated (Annexure
3.7). The total present fan load demand for the 2509
active industries come to 46821kW i.e. 47MW and the
corresponding energy consumption comes to about 140 MkWh
per year (Table-3.3).
Table- 3.3:
The Category-wise Estimated Fan
and Blower Loads
|
Sl No. |
Item |
Small kW |
Medium kW |
Large kW |
Total kW |
Energy Consumed MkWh |
|
1 |
Knitting |
630 |
1690 |
4125 |
6445 |
19 |
|
2 |
Sweater |
45 |
462 |
14454 |
14961 |
45 |
|
3 |
Woven |
1102 |
3090 |
16587 |
20779 |
62 |
|
4 |
Woven-knitting mixed |
272 |
1066 |
3298 |
4636 |
14 |
|
Total: |
46821 |
140 |
||||
Source:
Field survey, 2008

3.1.4 Air
Conditioners
Air conditioners both window
type and split type are generally used in the office
rooms. This constitutes only a small part of load. Power
supply to the air conditioners is essential during the
office hours only.
The average load demands for
air conditioners of all types of industries were
calculated and compiled in Annexure 3.2. With
these average values from Annexure 3.2, the
category-wise present demand for air conditioners for
2509 active industries were calculated and placed in
Annexure 3.8. The total present Air-conditioners
demand for the 2509 active industries come to 28897 kW
i.e about 29MW and the corresponding energy consumption
comes to about 86 MWh per year (Table-3.4).
Table-3.4:
The Category-wise Estimated Air
Conditioner Loads
|
Sl No. |
Item |
Small kW |
Medium kW |
Large kW |
Total kW |
Energy Consumed MkWh |
|
1 |
Knitting
|
280 |
1014 |
3300 |
4594 |
14 |
|
2 |
Sweater |
18 |
168 |
5256 |
5442 |
16 |
|
3 |
Woven |
580 |
2472 |
11349 |
14401 |
43 |
|
4 |
Woven-knitting mixed |
170 |
410 |
3880 |
4460 |
13 |
|
Total: |
28897 |
86 |
||||
Source:
Field survey, 2008

3.1.5 Other
Electrical Loads
In an RMG factory the major
electrical loads are consumed by the lightings, fans &
blowers and motors, which cover more than 95% of the
load. Other than this, only a very small load is there,
for security lights and office equipment etc. The
average load for office equipment from the Annexure
3.2 was used to calculate the category-wise present
demand for office equipment of 2509 active industries
and are shown in Annexure 3.9. The total demand
for other electrical loads for 2509 active industries
come to about 9561kW i.e. about 10 MW and the
corresponding energy consumption comes to about 29 MkWh
per year.
3.1.6
Estimation of total present demand of RMG Industries
The total present maximum
demand for 2509 active industries was calculated from
the above average values. The calculated total maximum
demand comes to be 619771 kW i,e 620 MW and the
corresponding energy consumption per year is 1858 MkWh.
The category-wise present kW demand for knitting,
sweater, woven and woven-knitting mixed industries for
small, medium and large factories and the corresponding
energy consumption per year for each type of industry
have been calculated (Annexure 3.3). The results
of these calculations are shown in Table-3.5.
Table-3.5:
The Estimated Total Present
Demand
|
Sl No. |
Item |
Small kW |
Medium kW |
Large kW |
Total kW |
Energy Consumed MkWh |
|
1 |
Knitting |
4550 |
40560 |
121000 |
166110 |
498 |
|
2 |
Sweater |
312 |
3297 |
91542 |
95151 |
285 |
|
3 |
Woven |
10382 |
64581 |
224361 |
299324 |
898 |
|
4 |
Woven-knitting mixed |
1326 |
12464 |
45396 |
59186 |
177 |
|
Total: |
619771 |
1858 |
||||
Source:
Field survey, 2008

From the above, area-wise
present demand for 2509 active RMG industries have been
calculated considering demand factor of 0.9 which are
shown below:
Gazipur
-
33 MW
Narayanganj -
20 MW
620 MW
The area wise coincident
present demands at power station terminals for above
2509 active garment factories have then been calculated
by considering diversity factor of 1.6 which are shown
below.
Gazipur
-
21 MW
Narayanganj -
13 MW
388
389
390
MW
3.1.7 Future
growth of power Demand of RMG Industries
The forecast for future load is
based on 10%-15% annual growth in all categories of
factories in operation. For the purpose of forecast both
future and reactivated factories have been considered.
Load has been calculated on the basis of average load of
each category as found from sample survey for the next 5
(five) years. Future maximum demand has been calculated
for each category of factory after applying a diversity
factor of 0.9. The total future demand upto next 5 years
thus calculated as 1000MW. The maximum coincident demand
at generation end has been calculated, considering
diversity factor of 1.6, as 625 MW.
3.2
Power Supply to Garment Industries
The garment industries,
according to respective sizes, receive power supply from
the public utility services at 400 volt or 11000 volt.
Consumers having demand over 49 kW have to get their
supply at 11000 volt or above. However, supply voltages
are always poor and continuity of supply has all along
been interrupted by system disturbances. From the survey
it was further learnt that for the last few years the
factories have been facing frequent load shedding due to
power cuts. Previously there was no schedule for such
cuts. But now a day the utilities seem to follow some
routine. However, power cuts had become so intolerable
that the garment factories were compelled to establish
standby diesel/gas generators to maintain production to
meet the orders of their foreign buyers at a higher
production cost. Average price for each unit of
electricity (kWh) that they have to pay to utilities was
found to be Tk.3.70.
3.3
Power Demand and Supply Situation of Garment Factories
a) Lighting Demand
The total present lighting load
demand for 2509 active industries comes to about 75 MW
and the corresponding energy consumption comes to about
224 MkWh per year.
b) Machine load
The total present machine load
demands for the 2509 active industries come to 317MW and
the corresponding energy consumption come to about 950
MkWh per year.
c) Fans and Blowers
The total present fan load
demand for the 2509 active industries come to 47MW and
the corresponding energy consumption comes to about 140
MkWh per year.
d) Air Conditioners
The total present
Air-conditioners demand for the 2509 active industries
come to about 29 MW and the corresponding energy
consumption comes to about 86 MkWh per year.
e) Other Electrical Loads
The total demand for other
electrical loads for 2509 active industries come to
about 9561kW i.e. about 10 MW and the corresponding
energy consumption comes to about 29 MkWh per year.
f) Estimation of total present
demand of RMG Industries
The total present maximum
demands for each of 2509 active industries were
calculated with demand factor of 0.9. The aggregated
respective maximum demands come to be 620 MW and the
corresponding energy consumption per year is 1858 MkWh.
g) Future growth of power
Demand of RMG Industries
At an increase of 10%-15% per
year the aggregated future load demands for RMG sector
comes to be about 1000 MW as compared to existing demand
of 620 MW and the maximum coincidental demand at
generation end comes to 625MW.
Chapter-4
Capacity of Captive and Standby Generation and
Consumption of Primary Energy by RMG sector and its
Financial Implication
4.1
Capacity of Captive and Standby Generation of RMG
Sector
Most of the RMG Factories have installed their own Captive or Standby Generators to protect their production during load shedding. The captive generators use gas as the fuel and the standby ones use diesel oil.
Presently, active factories are 2509 in numbers and almost all of them have their own generators to maintain production target as well as to fulfill the contract requirement for the buyers.
During the sample survey of 319 garment industries it was observed that about 304 industries have installed standby diesel generators having total capacity of 73459 kW, the average capacity of each being 242 kW. On this basis, out of the total active 2509 industries, the number of industries having standby diesel generators is 2391, the total capacity estimated as 578622 kW i.e. 580MW.
Further, 30 industries have installed captive generators using gas as fuel. The total capacity of the standby generators are about 60MW.
4.2
Use of Diesel for Own Generation as Standby Power
Most of the RMG factories have installed their own standby Diesel generators, in view of load shedding by utility companies. This requires space for storing at least 3-months requirement of Diesel. The price for diesel is Tk. 55/- per litre at the time of survey. This obviously has a great influence on the unit cost of production and causes high cost for electricity generation. The cost of fuel (Diesel) alone comes to about Taka 11.00 per kWh generated.
4.3
Use of Gas for Own Generation as Captive Power
Due to major shortfall in generation, RMG sector is facing acute load shedding. To protect the industrial production, some of the RMG factories installed their own gas fired captive generation. The main benefit of using gas is it does not require storage facility and easy to use. The production cost of electricity by Gas is about 3/- per kWh. However, this rate is higher than the unit cost supplied by different utilities. The cost of gas will be further increased in future.
4.4
Financial Implication due to use of Diesel for Own
Generation
The cost of own electricity generation by the RMG factories is much higher than the billing rates of different utilities. The cost of fuel (Diesel) alone comes to about Tk. 11.00 per kWh generated. Moreover, the RMG factories require a large amount of investment for electricity generation. This adds to the fuel cost to inflate it further. Total cost of own generation by diesel oil including O&M cost has been calculated to be Tk. 15/- per kWh. The RMG market being very much competitive, the contract rates with the buyers for cost of production declines by a large amount causing a critical situation for the RMG factories. As a result, a good number of small RMG factories have been closed during last few years. According to BGMEA, the number of closed RMG factories is 1542, which is about 38% of the total 4051.
Chapter-5
Load Shedding and its Impact on
RMG Industries
5.1
Load Shedding
There has been prevailing an acute generation shortfall vis-à-vis power demand of the country for the last 7 years. So, nationwide power supply system is facing inevitable load shedding. Load shedding has to be resorted to in order to save the generators from damage due to over load. No consumer groups are spared except the agricultural consumers. Even in the midnight, load shedding becomes necessary almost everyday.
Load shedding has been created by acute generation shortfall as generating capability has continuingly fallen short of the forecast demand as discussed in Chapter-2. As a result, indiscriminate load shedding has been resorted to by the utilities causing great distress to the industry
5.1.1
Frequency and Impact
From the survey it is observed that
the feeders supplying power to RMG factory are switched
off 3 to 5 times a day during the production time of the
factories. Some factories particularly in
Almost all the RMG factories are now equipped with their own captive generation to maintain their supply order in proper time and saving loss of reputation among international buyers. However, small factories without such standby generators face production loss.
It is also found that, even if there is captive power generation having full capacity, the RMG factory suffers loss of about half an hour for the workers to restart and came to full production.
The cost of electricity produced by diesel oil has been estimated to be Tk.11 to 15 per kWh which is 3 to 4 times higher than that supplied by utilities. This additional cost of electricity generation has significant impact on the cost of production of RMG sector.
Normally a supply order follows a tight schedule for a particular time period. So a continuous and reliable power supply is very much essential for a garment factory.
Unless there is captive power generation having full capacity as required by the factory, the main production line gets stopped.
5.2
Loss of Production
Load shedding causes both time and production loss for the RMG factories and as a result they fail to maintain timely production and contract schedule for shipment.
Financial implication of load shedding can be explained by ENS or ‘energy not served’. The implication of ENS has been discussed in Chapter-2 (Section 2.1.4).
The situation of load shedding is such that it happens 3 to 5 times or even more a day causing 3 to 5 hrs. of interruption to the RMG Industries. Daily working hours are 8 hours. So loss of 3 to 5 hours during a period of 8 hours shift obviously creates a difficult situation for the RMG Industries. As a result, the cost of production increases. As a consequence, most of the factories have installed standby diesel generators to avoid production loss. Small factories however, suffer, as they can not afford to such alternatives for various reasons.
5.3
Interruption due to Holidays/Strikes
The workers in RMG Industries enjoy the national holidays. To cope with tight shipment schedule, if the workers are engaged in works in national holidays, the RMG industry needs to pay them overtime. During strikes, the workers seize to work and as a result the RMG industry faces loss of production. To overcome this situation the RMG industry need to engage the workers beyond working hours and pay in overtime. This causes increased production cost for the RMG industry.
5.4
Investment in Standby/Captive Generation
Increasing reliance on captive or stand by power supply, results from frequent load shedding, costs have increased about 1.75% during 2007-2008. As a result, the total production cost has increased substantially. Most of the factories are forced to shutdown part of the production and assembly line during load shedding which has a direct bearing on production rates and production volume. Against backdrop of the situation, all categories of factories have invested in standby/captive generating stations.
Investment in these standby and captive power varies in accordance with types of factory.
5.5
Higher Production Cost in a Competitive
Environment
The power interruption due to load shedding has the direct impact on cost of production. The production cost increases is due to decrease in productivity which is attributed by increase in idle manpower, corrective maintenance and the diverting of resources.
5.6
Cost of ENS (Energy Not Served)
to Garment Factories
A significant loss of industrial output can be directly attributed to energy shortages. A USAID study of the impact of power outages resulted in a substantial economic loss in the industrial sector amounting to US$778 million a year. This translates into 11.54 percent of the industrial sector GDP or 1.72 percent of national GDP. The scale of shortages has increased as demand continues to outstrip supply, and power cuts are long and frequent. Garment factories have been suffering from direct financial loss on account of generation from stand-by diesel sets. This study has found the cost of energy not served (ENS) to garment industry as Tk. 15/ kWh.
From the sample survey it appear that the loss of production due to load shedding in the RMG sector is made up by own generation of electricity at a higher cost of production. A few small factories would do not have standby generators have to face loss of production. This accounts for a fraction of the total. The total cost of generation incurred by RMG sector due to load shedding has been estimated to be Tk. 6138 million per year as shown below (Table-5.1):
Table-5.1 Estimation of Total Cost of
Generation due to Load Shedding
Summation of estimated demands at Factories end: 620 MW
(For Factories in operation, 2509 Nos.)
Operating days 300 days per year.
Lost hours due to load shedding 3 hours per day
Total hours lost due to load shedding 300´3= 900 hours
Total whir lost due to load shedding 620x900×103 =558,000,000 kWh.
Unit cost of Energy not served (ENS) due to
load shedding. Tk 15/ kWh.
Differential cost per unit Tk. (15-4) for energy
not served (ENS) due to load shedding on top
of unit price of utilities (Tk. 4/kWh). Tk. 11/kWh.
Total estimated cost incurred by RMG industries
due to load shedding Tk. 11 x 558,000,000.00
= Tk. 6138, 000, 000.00 per year
= Tk. 6138 million per year
5.7
Loss of Revenue
The power interruption has direct impact on loss of revenue.
Cost of energy produced by gas and diesel for running the captive and standby generators has been estimated which could have been averted if the industries were given the uninterrupted power supply from the existing sources. This is about 6138 Million Taka in a year which is 1.75% of total cost of production of 350 billion Taka.
The garment factories also incur revenue loss due to delayed production schedules, failure to meet deadlines and delayed shipment.
5.8
Decreased Competitiveness and Lost
Power interruptions are deemed to be a menace to any production environment. Most of the small factories are forced to shut down their production line due to power outage and inability to afford alternative power cost for the whole production process. With regard to uninterrupted power supply, the reliability factors also contribute with regard to increasing dependence on alternative power generation.
The production environment is seriously hampered due to power interruptions. Load shedding has forced the factory management to take alternative measures like holiday staggering and re-arrangements in shifts (production schedule). Power interruption often results in buyer’s dissatisfaction and as well as delayed production schedules. These shortcomings certainly decrease competitiveness and very costly.
5.9
Wasted Energy and Cost of Alternative Power
Generation
The interruption to manufacturing process results in a waste of energy in the restart process. This adds to the increase in production cost of RMG sector. Generation by stand-by diesel generators is about four times as costly as average cost of utility power supply.
5.10
Damage of Equipment / Decreased Equipment Life
The load shedding in the garment factories affect some life of the equipment. This is attributed by switching on and off several times during load shedding. However, this is negligible.
5.11
Mitigation of Power Supply Crisis due to Load
Shedding
The present crisis in power supply is primarily attributed to generation shortage. This resulted in inevitable load shedding which affect all consumer groups including RMG industries. This situation will continue to worsen further beyond 2008. Therefore, for immediate mitigation of the power supply the following measures may be taken up.
5.11.1 Load
Management
Load management is a tool to control the load demand and thus meeting the demand without new investment. Some measures that have been taken by the utilities were discussed in Chapter-2 (Section-2.1.5).
The replacement of Incandescent Lamps by Compact Fluorescent Lamps (CFL) is very important. It will substantially reduce the total lighting demand of the country considering about 80 lac domestic consumers nationwide and reduction of 100W for each consumer, a total of about 320MW lighting load may be reduced with diversity factor of 40%. Vigorous campaign may be taken up to aware the consumers about this. However, to increase the affordability to purchase the CFL by consumers particularly rural ones, CFLs may be given to them either free or on loan.
In an RMG factory a series of standard tube lights with magnetic ballasts are used. These are appropriate for using in production lines of RMG industries. However, it is recommended to use electronic ballasts in place of magnetic ballasts to reduce power loss by about 12 watts per unit. It will reduce the power demand on account of lighting by 20 percent without sacrificing illumination. This may be perused nationally also which will reduce about 100MW of total national demand.
Further, if one tube light from each fixture is replaced by a 7 watt CFL fitted on the body of each machine, this will reduce the lighting load demand of RMG industries by about 56%. As a result the power demand for lighting load of 2509 RMG factories will come down from 75MW to about 33MW.
Other measures like, shifting irrigation load from peak hour to off peak hour, switching off the non-essential loads, e.g. iron, air-conditioners, welding machines etc. during peak hour, holiday staggering, operating industries having two shifts during off peak hour, operating large commercial establishment using own generation should be pursued vigorously.
The present measure of closing the commercial establishment at 8 P.M will not result the desired goal. It should be effected from the starting time of the peak load i.e. 5 P.M in the evening during winter period and 7 P.M in the summer period. This will help reduce the peak load substantially which may be used for the RMG sector and other consumers.
Chapter-6
Recommended
Strategies and Action Plans for Improving the Power &
Energy Supply Situation in RMG Sector
6.1
Current Difficulties and Prospects
The study identified the
problems of power supply; the actions necessary for
improving power supply; and to this end employed
consultant to do the needful. As per the terms of
reference of the service, the consultants took up study
to identify the difficulties presently faced by RMG
industries under BGMEA in respect of power supply, and
recommend strategies and action plans for improvement.
Sample survey was taken up on the basis of which data
and information were collected, difficulties identified
and losses quantified.
The power crisis in
As part of divulging into
multi-faceted ramification of consistent power outage on
growing RMG industries of
Also an attempt was made to
examine the policy issues, shaping up and regulating the
power generation and distribution markets of
The fragile power supply
situation will continue to worsen further beyond 2008
even if pragmatic steps are not taken now for increasing
generation capacity. As yet, there is no immediate
solution with regard to making up deficits. This would
continue to affect the industrial growth and the
economic development of the country.
Power supply in
As against the projected demand
increase from 1997 to 2007 of (5367-2419) = 2948 MW, a
capacity of only 2294 MW has been added during the same
period causing a short fall of 654 MW. Shortfall of
capacity has been further increased due to aging of
generators, total estimated to about.700 MW. Gas supply
shortage has caused another shortfall of 440 MW in daily
availability of generation capacity. All these add to
about 1700 MW.
Despite a lot of barriers in
private investments as IPP and for captive power
generation, the possibility of investment can be
explored in areas where there is higher concentration of
garment factories. The government has produced a 3-Year
Road Map for Power Sector Reform (2008 - 2010), which
may create an ambience in attracting investors. However,
acute gas shortage is a major impediment for such
investments to take place. Pertinent to mention that,
“Private Sector Power Generation Policy of Bangladesh”
was adopted in 1996. The Government approved “Policy
Guidelines for Small Power Plants (SPP) in Private
Sector” in 1998. Government should be persuaded
strongly implement the above mentioned policies.
In view of this situation
following recommendations have been drawn from the
analysis of study findings
6.2
Recommendations
On the basis of the above
findings the following recommendations are proposed
6.2.1 Short
Term (Fast-track) Actions
There is no magic to combat the
crisis of power supply in a short time. However, some
mitigation measures can be taken up to partly remove the
difficulties in the short term as proposed below:
1)
Load Management programme now in hand nationwide should
continue
In addition, following are
recommended:
2)
Garment Sector
a)
Replace the magnetic ballasts of
florescent lamps with electronic ballasts
RMG Industries use standard
4-ft. fluorescent tube lights, two per fixture with
magnetic ballasts.
The ballasts consume power @15
to 21 each. These may be replaced with electronic
ballasts thereby reducing power loss by about 12 watts
per unit, which means it will reduce the power demand by
20% of lighting load i.e. about 15 MW. As a result,
energy bill will also be reduced by Tk.222 million. This
may cost about Tk 125 per lamp.
Alternatively, retrofit the
sewing machine with integral lamps of low wattage (say,
7 watts) eliminating one of the two standard tubes from
the ceiling fixtures.
This would save about 50% of
lighting load. As a result, demand will come down to 37
MW and energy consumption reduced by 152 MkWh which will
reduce the energy bill by Tk. 562 million. This needs an
investment of Tk. 150 per machine.
However, this will house very
little effect on load shedding problem.
3)
Utilities
a)
Shut down all shopping malls at 5 p.m in winter and 7
p.m in summer.
The on going measure of closing
the commercial establishment at 8 P.M will not result
the desired goal. It should be effected from the
starting time of the peak load i.e. 5 P.M in the evening
during winter period and 7 P.M in the summer period.
This will help reduce the peak hour load substantially.
b)
Replace all incandescent light bulbs with CFL in
residential lighting.
Replacement of incandescent
lamps by compact fluorescent lamps (CFL), is an
important measure to take for reducing the load demand
on account of lighting load. It is estimated to reduce
about 320MW lighting load from the system. However, to
increase the affordability of the consumers to purchase
the CFL particularly by rural ones, these may be given
to them on loan at a subsidized price. Loan may be
recovered with electric bills within a year.
6.2.2
Medium Term Actions
Some energy conservation and
Efficiency improvement measure may be taken up under
mid-term programme such as.
a)
Co-generation
b)
Heat recovery boiler for hot
water supply
c)
Replace existing diesel engines
with gas engines for standby generation
Item (a) and (b) are same thing
(symbiotic). Prospect of co-generation is discussed
below:
(a) Co-generation / (b)
Heat Recovery Boiler for Hot Water Supply
Cogeneration is the use of a
heat engine such as diesel engine, gas turbine etc.
simultaneously generating electricity and heat. The heat
of exhaust hot gas raising steam or hot water for steam
turbine in combined cycle, district heating, and for
process heat in textile mills, chemical industries etc.
Garment factories co-generates process steam or hot
water for calendaring of fabrics, sweaters and woven
products. Use of co-generation is worth considering.
However, it may be recommended only for the large
factories, which have large diesel generators so that
their exhaust gas may be passed through a heat recovery
boiler to raise steam or hot water for various use in
the factories. This would reduce the consumption of fuel
and thus the production cost would reduce.
In the RMG factories having
captive power generation in the range of 2000 to 3000
kW, with heat recovery boiler, generation of hot water
utilizing the waste heat is a possibility.
For installation of such
additional facilities, sufficient space shall be
earmarked. But while surveying the RMG factories it is
observed that there is space constraints which will be a
general problem. However, it will need separate survey
for specific industries having large captive generation.
·
Therefore, the possibility of
co-generation may be examined in depth by the owners of
the large factories as to its technical and economic
feasibility and may be implemented accordingly.
(b) Replacement of Existing
Diesel Engines by Gas Engines
Diesel engine operation using
diesel oil as fuel to generate electricity is costly as
fuel is costly.
At current (during survey)
price of Tk. 55/litres of diesel oil entails fuel cost
of about Tk.11/kWh generated. Even at reduced price of
Tk. 48/lit, fuel cost comes to about Tk.9.6/kWh.
Compared to this, use of natural gas at Tk. 150/MCF will
cost about Tk. 1.5/kWh.
In view of less cost of fuel,
the existing diesel engines may be replaced by new gas
engines. This will save about Tk.10.00 per kWh generated
by standby generating.
If a 500KW diesel generator is
replaced by same capacity of gas generator the capital
cost (Tk. 12.5 million), shall be recovered within 3
(Three) years, considering energy generation per year
(500kW x 900 hrs) 450,000 kWh, and savings per year
shall be about Tk. 4.5 million.
·
Therefore, it is recommended to
replace the old diesel generators with new gas engine
generators. Owners may examine the option to select the
least cost solution for their respective factories.
·
GOB should consider unrestricted
supply of gas to these factories at the same price as
for BPDB.
6.2.3 Long
Term Actions
6.2.3.1 Strategy
Following strategy is proposed for improvement of power
supply to garment industry.
Assumption: Power plant to be
developed on IPP basis anywhere.
Case-1:
Power plants to be developed on distributed basis
sponsored by Garment Manufacturers Co-operative (GAMCO)
to be organized and incorporated (See Option-1 Action
Plans).
Power plants of appropriate
capacities would be developed in Savar, Mirpur,
Kaliakoir, Gazipur, Sonargoan, Kantchpur areas. Output
of these power plant would be delivered to 33kV system
of REB.
The sending end switches at 33kV substations and
receiving end switches at garment factories will be kept
“ON” all the time. Any surplus capacity whenever
available will be absorbed by REB.
The Commercial arrangement may
be as follows:
-
GAMCO will sell power to PBSs at
a tariff based on power purchase agreement (PPA) between
PBS and GAMCO. The PBSs will sell power to RMG
industries at existing tariff.
Case-2:
A central power station of appropriate capacity
may be developed by a IPP anywhere exclusively for an
industry located at
-
Power plants dedicated to the
garment industry, rated adequately to the requirement.
-
Generated power will be evacuated
to national grid system existing in the country.
-
Contracted power will be
delivered to the industry at a nominal wheeling charge.
-
To ensure delivery of contracted
power all is required is to keep the receiving end
switch “ON”.
-
In case where the industries are
scattered, all is required is to keep the supply feeders
to these industries “ON” all the time.
Thus, supply of power from a
dedicated power plant located anywhere in the system to
the beneficiary/client is ensured.
The commercial arrangement may
be as follows:
All the generated power is to
be purchased by the single buyer BPDB. It will buy all
power from the power producer at a tariff based on power
purchase agreement (PPA) between BPDB and IPP. BPDB will
sell net power to the PBSs/Regional distribution
companies, and pay wheeling charges to grid company. In
their turn, PBSs/Regional distribution companies will
sell power to the garment factories at existing tariff.
The power plant may be
sponsored/ developed by a co-operative of the garment
industry owners with equity arrangement with a foreign
development partner. In this case GoB may provide all
support to the developer.
The above are oversimplified
description of strategies. If it is agreed in principle,
detailed plans on the agreed option can be worked out
for implementation. GOB has to adopt a new policy where
required.
6.2.3.2 Action Plans
Recommended action plans are as
follows:
A.
Installation of Generating Stations Exclusively for
Garment Industries
Option-1
Steps may be taken to install
gas turbine generating stations in areas where garment
industries are concentrated, under BOO
(Built-Own-Operate) arrangement. Entrepreneurs may be
the garment manufacturers cooperative(s) to be formed,
or others may be interested to install these power
plants under the existing IPP policy of the country.
Output of these power plants would be catered to the
garment factories through existing networks isolated
from the grid.
2x20MW power plant each at
Savar, Mirpur, Kaliakoir, Gazipur, Sonargaon, Kanchpur
may be considered. Total estimated cost shall be about
US$ 96 million and time required shall be 18 months.
Option-2
In case gas is not available
the following option may be considered.
Build an imported coal based
power plant of 300MW capacity at
The output of these power
plants shall be used by the RMG industries at usual rate
through the existing distribution system of BPDB / REB
at agreed wheeling charge. Appropriate policy may be
developed in this respect.
B
Installation of Generating Stations as Planned by the
Govt.
A pragmatic and whole-hearted
effort should be made to implement the generating
projects as planned, which have been discussed in
Chapter-4, so that those are commissioned at scheduled
times.
C
Improving Power Supply Situation through Load Management
Investigate whether power
supply to garment industries can be improved by reducing
load shedding to the feeders supplying RMG factories.
Our observations are that the locations of the RMG
industries are such that the feeders supplying RMG
industries cannot be separated from other consumers and
hence cannot be relived from load shedding. However, if
shopping malls are closed before the peak time occurs
during a day some load shedding may be avoided.
D
Exemption of Levies and Taxes for Installation of Own
Generation by RMG Factories
To overcome the crisis of load
shedding most of the RMG Industries have installed their
own generation either, standby or captive. For standby
generators imported Diesel oil is used as fuel, whereas
the captive generators use indigenous gas. This may be
persuaded during the coming years until the national
generation capability improves. To encourage the RMG
industries to this effect, Govt. should render all-out
support by withdrawing all taxes & levies on the import
of generators, by supplying gas at a rate earmarked for
BPDB and by providing loans at lower interest rates.
Annexure-3.10:
Lighting Load of a Large Size,
Medium Size and Small Size Factory
Table - 3.1: Lighting load of a Large Size Factory
|
Type of Light |
Rated watt of light |
Type of ballasts (if
tube light) |
Rated watt of ballast |
Total watt/ lamp |
Qty |
Total connected load
(kW) |
Running hour in a day |
Diversity factor |
Total power demand (kW) |
|
TL |
40 |
M |
20 |
60 |
1450 |
87 |
8 |
0.9 |
78 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table - 3.2: Lighting load of a Medium Size Factory
|
Type of Light |
Rated watt of light |
Type of ballasts (if
tube light) |
Rated watt of ballast |
Total watt/ lamp |
Qty |
Total connected load
(kW) |
Running hour in a day |
Diversity factor |
Total power demand (kW) |
|
TL |
40 |
M |
20 |
60 |
885 |
53.1 |
10 |
0.9 |
48 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table - 3.3 Lighting Load of a Small Size Factory
|
Type of Light |
Rated watt of light |
Type of ballasts (if
tube light) |
Rated watt of ballast |
Total watt/ lamp |
Qty |
Total connected load
(kW) |
Running hour in a day |
Diversity factor |
Total power demand (kW) |
|
TL |
40 |
M |
20 |
60 |
200 |
12 |
10 |
0.9 |
11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Annexure- 3.11:
Mechanical Load of a Large
Factory, Medium Factory and Small Factory
Table - 3.4:
Machine Load of a Large Factory
|
Machine Type |
Built in PFI (Yes/ No) |
Rated power hp/ watt |
Quantity |
Total connected Load kW |
Running hour in a day
hrs |
Diversity factor |
Total power demand (kW) |
|
Cutting Section |
- |
1600 |
3 |
4.8 |
10 |
0.9 |
4.32 |
|
Sewing Section |
- |
250 |
1200 |
300 |
10 |
0.9 |
270 |
|
Total |
|
274 |
|||||
Table - 3.5:
Machine Load of a Medium Factory
|
Machine Type |
Built in PFI (Yes/ No) |
Rated power hp/ watt |
Quantity |
Total connected Load kW |
Running hour in a day
hrs |
Diversity factor |
Total power demand (kW) |
|
Cutting Section |
- |
1600 |
4 |
6.4 |
8 |
0.9 |
5.76 |
|
Sewing Section |
- |
250 |
355 |
88.75 |
8 |
0.9 |
78.88 |
|
Total |
(Including two other
cutting & sewing sections) |
86 |
|||||
Table - 3.6:
Machine Load of a Small Factory
|
Machine Type |
Built in PFI (Yes/ No) |
Rated power hp/ watt |
Quantity |
Total connected Load kW |
Running hour in a day
hrs |
Diversity factor |
Total power demand (kW) |
|
Cutting Section |
- |
746 |
4 |
2.98 |
4 |
0.9 |
2.68 |
|
Sewing Section |
- |
250 |
230 |
57.50 |
7 |
0.9 |
51.75 |
|
Total |
|
54 |
|||||
| Number of Machines wise Distribution of RMG (Knit, Sweater, Woven and Mixed) | ||||||||||||||||||||||||||||||||||
| Total | IND_TYPE | <> | Less than 50 | 50 | 100 | 150 | 200 | 250 | 300 | 350 | 400 | 450 | 500 | 550 | 600 | 650 | 700 | 750 | 800 | 850 | 900 | 950 | 1000 | 1050 | 1100 | 1150 | 1200 | 1250 | 1300 | 1350 | 1400 | 1450 | 1500 + | |
| 917 | Knit | 40 | 47 | 244 | 195 | 128 | 74 | 47 | 29 | 22 | 20 | 13 | 11 | 10 | 4 | 4 | 2 | 3 | 4 | 2 | 4 | 1 | 1 | 4 | 3 | 1 | 4 | |||||||
| 4% | 5% | 27% | 21% | 14% | 8% | 5% | 3% | 2% | 2% | 1% | 1% | 1% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | |||
| 686 | Sweater | 8 | 4 | 14 | 31 | 51 | 62 | 51 | 77 | 65 | 47 | 34 | 41 | 26 | 24 | 21 | 14 | 16 | 7 | 9 | 11 | 7 | 9 | 7 | 5 | 3 | 5 | 1 | 3 | 2 | 3 | 1 | 27 | |
| 1% | 1% | 2% | 5% | 7% | 9% | 7% | 11% | 9% | 7% | 5% | 6% | 4% | 3% | 3% | 2% | 2% | 1% | 1% | 2% | 1% | 1% | 1% | 1% | 0% | 1% | 0% | 0% | 0% | 0% | 0% | 4% | |||
| 2133 | Woven | 78 | 33 | 279 | 496 | 396 | 266 | 177 | 101 | 64 | 58 | 30 | 20 | 21 | 17 | 9 | 8 | 11 | 13 | 5 | 4 | 4 | 7 | 1 | 3 | 3 | 3 | 2 | 1 | 4 | 1 | 1 | 17 | |
| 4% | 2% | 13% | 23% | 19% | 12% | 8% | 5% | 3% | 3% | 1% | 1% | 1% | 1% | 0% | 0% | 1% | 1% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 1% | |||
| 450 | WK(Mixed) | 3 | 5 | 61 | 100 | 86 | 51 | 37 | 21 | 13 | 14 | 8 | 12 | 4 | 9 | 1 | 4 | 5 | 1 | 4 | 1 | 2 | 1 | 1 | 1 | 5 | ||||||||
| 1% | 1% | 14% | 22% | 19% | 11% | 8% | 5% | 3% | 3% | 2% | 3% | 1% | 2% | 0% | 1% | 1% | 0% | 1% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 1% | |||
| 4186 | Total RMG | 129 | 89 | 598 | 822 | 661 | 453 | 312 | 228 | 164 | 139 | 85 | 84 | 61 | 54 | 35 | 28 | 35 | 25 | 20 | 19 | 12 | 19 | 10 | 12 | 7 | 11 | 4 | 5 | 6 | 4 | 2 | 53 | |
| 3% | 2% | 14% | 20% | 16% | 11% | 7% | 5% | 4% | 3% | 2% | 2% | 1% | 1% | 1% | 1% | 1% | 1% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 0% | 1% | |||


Last Updated: 16 March, 2009
