Skip to main content.

Demonstration of Micro hydro power unit in  Bangladesh: 

Micro hydro Power Programme by Bangladesh Power Development Board (BPDB)


Demonstration of Micro hydro power unit in Bamerchara lake, Banshkhali, Chittagong district in  Bangladesh ( UNDP supported) 

 

 Micro Hydro Resource Potentials in Bangladesh  

Micro Hydro power potential sites in Bangladesh

  Appropriate Low Head Micro Hydro Systems for Bangladesh  ( A.K.M. Sadrul Islam, M. Q. Islam, M. Z. Hossain, M. I. Khan and S. A. UddinDept. of Mechanical Engineering, Bangladesh University of Engg. & Technology Dhaka 1000, Bangladesh )

 

 

 

At present only 230 MW of conventional hydro power is utilized in the Karnafuli Hydro Station, which is the only conventional hydro-electric power plant in the country operated by Bangladesh Power Development Board (BPDB). BPDB is considering extension of Karnafuli Hydro Station to augment another 100 MW capacity which will add energy marginally, but will be effective to operate it as a peaking power plant. The additional energy will be generated during the rainy season when most of the water is spilled.

 

Micro hydro Power Programme by Bangladesh Power Development Board (BPDB)

 

 

Micro Hydro Projects:

 

BPDB has submitted the following Micro Hydro Projects to the Power Division for approval:

 

  •  25 KW Micro Hydro Project at the Teesta Barrage

  

50kWp Micro Hydro Power Project at Barkal Upazila, Rangamati District :

 

BPDB  implemented Stand-Alone Type (SAT)  Micro Hydro Power pilot project with  capacity of 50 kW at Barkal Upazilla Sadar under Rangamati District of the Chittagong Hill Tracts region of Bangladesh. The micro hydro project site having a natural waterfall as water sources. This is the first ever Micro Hydro Power Project (MHPP) in the country which having 50 kW capacity hydro turbine. The installation, commissioning of the MHPP turbine already completed. The MHPP has been tested satisfactorily in presence of the Chief Engineer (Generation) of BPDB.

 

The main specialty of this unique MHPP of BPDB is that the system generating electricity at 440V. The MHPP Turbine require no Step-Up or Step-Down Transformers. The generated electrical power being supplied to the existing 440 distribution grid line system. The MHPP generated electricity distributed directly to the localized grid lines during the evening peak hours, moreover surplus electricity(during the off-peak hours) being stored to a large battery bank which is consisted of 120 numbers of (200 Ah) batteries. Very little operation and maintenance being conducted to run system smoothly . 

 

 

 

Demonstration of Micro hydro power unit in Bamerchara lake, Banshkhali, Chittagong district in  Bangladesh ( UNDP supported) 

 

 

 

Bamerchara Micro Hydro Project :

SRE under LGED has successfully demonstrated first micro-hydro power unit at Bamerchara, Chittagong. Its installed capacity was 10kW but due to inadequate water head about 4kW power was generated. SRE has also carried out a study on prospective micro-hydro sites in the Chittagong Hill Tract reasons and eight potential sites were identified with an estimated capacity of 135kW. SRE also provided technical support to promote indigenous micro-hydro power generation unit which was developed by member of local indigenous community named Mr. Aung Thui Khoyan. 

Background: Hydropower is an eco-friendly clean power generation method. The scope of hydropower generation is very limited in Bangladesh because of its plain terrains except in some hilly region in the northeast and southeast parts of the country. However there are lot of canals, tributaries of main river  Karnafuli, Shangu, Matamuhuri as well as tiny waterfalls having good potentials for setting up mini/micro hydropower unit in Chittagong Hill Tracts(CHT) region.

Micro-hydro power is a simple technology to convert hydropower primarily to mechanical power. They are generally 5-300 kW range. It is not feasible to supply electricity to the National grid from a micro-hydro power unit. Typically they provide captive power to just one rural community. In many cases micro hydro power units do not generate electricity. They are used for grinding cereals in mills and often driven directly from the turbine shaft. Classifications of hydro power based on generated power are as follows:

Pico Hydro up to 5 kW
Micro-hydro         >5<300 kW
Mini-hydro           >300kW<3MW
Small hydro         > 3MW<10MW

A hydro power scheme requires both water flow and a drop in height (referred to as a head) to produce useful power. It is a power conservation system, absorbing power in the form of head and flow, and delivering power in the form of electricity or mechanical shaft power. Indeed no power conservation system can deliver as much useful power as it absorbs. Some power is lost by the system itself in the form of friction, heating, noise etc.

Net power generation from a hydro power unit could be obtained from the following equation:
Pnet = hgross * Q *  g  * eo
Where
Pnet   = Net power generated from the unit in kW
hgross = Gross water head in meter
Q      = Discharge in m3/sec
eo     = System efficiency
g      = gravitation force in m/sec2

A typical hydro power has about 50% power loss, out of which about  5% losses in Channel, 10% loss in Penstock, 20% loss in turbine, 15% loss in Generator, 4% losses in step-up/down transformers loss and 10% Transmission losses.

‘Bamerchara’ is basically a water storage reservoir. To facilitate irrigation in dry period earthen dam with a sluice gate was constructed by the Local Government Engineering Department in 1994. Only rainwater is stored in the reservoir during the monsoon and there is no perennial source of stream. ‘Danerchara’; another storage reservoir was also connected with ‘Bamerchara’ to provide more water storage facility. At present maximum water storage area has been increased to about three sq. km. A spill way was constructed at ‘Danerchara’ in 2000 to release extra water. In 2002 a feasibility study was conducted by an International Expert to install a micro-hydro power unit at Bamerchra. However, irrigation is the main purpose of Bamerchara project therefore only supplementary power generation is possible during monsoon and irrigation period when the sluice gate is normally kept open.

Objective of the project:

  • To demonstrate micro-hydro power unit
  • To integrate hydropower with the irrigation infrastructure
  • To explore possible replication of the model in the CHT region

Potentials of Micro Hydro power unit in Bangladesh:  To explore potential sites of micro-hydro, several studies have been conducted by Bangladesh Water Development Board (BWDB) and BPDB in 1981. List of prospective site is shown in table 1.1

Table 1.1 : Potential Small Hydro Sites identified by BPDB and BWDB

District Name River/Chara/Stream Potential of Electrical Energy in KW
Chittagong 1.   Foy’s lake 4
Chittagong 2.   Choto Kumira 15
Chittagong 3.   Hinguli Chara 12
Chittagong Hill Tracts 4.   Sealock 81
Chittagong 5.   Lungichara 10
Chittagong 6.   Budiachara 10
Sylhet 7.   Nikhari Chara 26
Sylhet 8.   Madhab Chara1500ft. from fall 78
Sylhet 9.   Ranga pani Gung 616
Jamalpur 10. Bhugai-Kongsa at 2 miles     U/S. of Nalitabari P.S 69Kw for 10 months
48 Kw for 2 months
Jamalpur 11. Marisi at Dukabad near  Jhinaigati Thana Head Quarter 35Kw for 10 months
20 Kw for 2 months
Dinajpur 12. Dahuk at Burabari 24
  13. Chawai at U/S. of Chawai L.L.P 32
  14. Talam at U/S. of Talam L.L.P 24
  15. Pathraj at Fulbari 32
  16. Tangon at D/S of Nargun L.L.P 48
  17. Punarbhaba at Singraban 11
Rangpur 18. Buri Khora Chikli at Nizbari 32
  19. Fulkumar at Raiganj Bazar 48

In 2004 Sustainable Rural Energy has explored some potential micro-hydro sites in CHT region which is listed in table 1.2  

Table1.2:  Micro-Hydropower sites identified by SRE study  in 2004


Site

Expected Power Generation

Socio-economic Infrastructure within 1 Km

House hold

School / Mosque / Bazaar / Clinic

Small Industry

Nunchari Tholipara, Khagrachari

3 KW

100

3

1

Chang-oo-Para, Bandarban

30 KW

200

5

2

Bangchari, Bandarban

25 KW

600

12

5

Liragaon, Bandarban

20 KW

500

8

3

Kamalchar, Rangamati

20 KW

150

8

9

Thang Khrue, Rangamati

30 KW

300

6

3

Monjaipara, Bandarban

7.5 KW

50

3

-

 Salient feature of Bamerchara micro-hydro power unit:

LGED through Sustainable Rural Energy (SRE) Project has implemented first micro-hydro power unit in Bangladesh at Bamerchara, Chittagong. Estimated capacity of the system was 10kW. Salient feature of the unit has been illustrated below: 

  • Turbine type                   : Corssflow
  • Penstock                         : 52m
  • Design flow                    :150 litter/sec.
  • Net head available          : 6m-10m
  • Preferred governor          : Flow control (Manual)
  • Electrical Output                          : 4-6 KW, 50Hz, 3 phase voltage, 220 V / 440 V

 

Considering water head of 11 meters and flow rate of 150 l/s it was estimated that maximum 10kW hydropower could be generated from ‘Bamerchara’ site. But when irrigation starts water head falls rapidly. Consequently full power generation was not possible. Furthermore about 41% potential energy was lost by the penstock, turbine, and generator and transmission line. Figure A illustrates relationship between water head and extractable hydropower from a stream.

water head on extractable power at Bamerchara Microhydro

Conclusions and Recommendations:

  • Primary purpose of Bamerchara project is irrigation therefore, extractable hydropower depends on nature and amount of irrigation. Most of the farmers are used to daytime irrigation so a considerable amount of power remains unutilized during this time. However this power could be stored in a Battery bank or could be used at grain mills or cooking.
  • As there is no perennial source of water at Bamerchara, the system is run out of water within a short period and then we need to wait for the next monsoon.
  • Flow rate and head are the key factors in selecting micro-hydro power unit. So Picohydro and Microhydro is suitable where there is a perennial source of flow.
  • This was the first demonstration Microhydro power unit in Bangladesh. This unit helps to get insight knowledge and practical experience in harnessing micro-hydro power.

 

 

 

 

Bamerchara Lake

 
   

 

Recently LGED setup a small hydro power unit at Bamerchara Lake, Banshkhali, Chittagong. Pictures below: 

  

 

 

 

 

 

 

 

 

 

Penstock to supply water to Bamerchara Micro Hydro Power Unit

Turbine

Power Generation

Bamerchara Micro Hydro Power Unit

 

 

 

 

Last Updated:  16 November, 2008