Skip to main content.

Clean Development Mechanism (CDM)

(First capacity building workshop on Clean Development Mechanism (CDM) under CD4CDM initiative date: 8-9 april, 2008, venue: Dhaka)

 

Financing a CDM Project                 –         DBBL’s experience

 by-

Farhad Ahmed Khan

Assistant Vice President

Syndication & Structured Finance

Credit Division, Dutch-Bangla Bank Ltd

 

 

DBBL’s Participation in Euro 12 Million Project

 

 

  • DBBL to provide to the extent of Taka eqvt. Euro 2.00 million in part funding of implementation of WWR Bio Fertilizer Ltd, a municipal organic waste-to-bio-fertilizer plant

 

  • FMO to act as Arranger and DBBL to act as Agent and Security Trustee

 

 

Project Partners

 

 

Waste Concern  Consultants (WCC) from Bangladesh. It is working in the area  of waste management in Bangladesh since 1995. It is specialized in small and medium scale waste management projects especially composting. Waste Concern is involved in design and implementation of  47 compost/recycling plants distributed in 26 cities and towns of Bangladesh. Apart from Bangladesh, WC is also involved in waste composting projects in  Sri Lanka and Vietnam.

 

World Wide Recycling BV from Netherlands.  It is also working in the areas of waste management. This company is associated with VAR a large scale waste recycling company. It is specialized in large scale waste projects including composting

 

 

 

 

 

 

 

 

The Shareholders Structure

 

 

 

 

  • WBH holds 100% less legally required local shareholding of one share of WWR Bio.

  • The shareholders of WBH are WWR (EUR 1.7m, 54.2%), WCC (EUR 0.4m, 13.6%), FMO (EUR 0.5m, 16.1%) and Triodos (EUR 0.5m, 16.1%).

 

 

About ‘VAR’/WWR

 

WWR is closely related to the VAR via Jan Boone, who is the founder of VAR, was director of VAR till July 2002, and still is main shareholder of VAR with 80% and he is chairman of the supervisory board of VAR. VAR was established in 1981 by Jan Boone. VAR is one of the largest and most innovative companies in the area of sustainable waste treatment in the Netherlands. VAR and WWR have signed a Cooperation Agreement via which VAR is obliged to provide technological support to WWR.

           

            At the end of 2006, VAR had a Balance Sheet total of EUR 83m, turnover of EUR 48m, net profit EUR 4.1m, solvency 32% and 140 staff. The following key figures of VAR in 2006:

 

        Balance sheet total: EUR 79,992,817

        Equity: EUR 27,096,302

        Turnover: EUR 47,643,755

        EBIDTA: EUR 7,300,429

        Net profit: EUR 4,122,329

 

 

 

Financing Plan of WWR Bio in million Euro

 

 

Amounts     x1m EUR

Equity to WBH*

Loan to* WBH

Loan to WWR Bio

Total

FMO

0.43

1.54

3.90

5.87

Triodos

0.43

0.43

1.50

2.36

 WWR/WCC

1.80

-  

-  

1.80

 DBBL

-  

-  

2.00

2.00

 

 

 

Total

12.03

 

 

*the amounts paid out to WBH are transferred to WWR Bio as equity

 

 

 

Investment and Financing

 

 Investment Plan (in Euro)

2007

2008/2009

2009/2010

1 Investments in intangibles

690,000

0

0

2 Land

187,198

327,273

297,521

3 Buildings + machines

1,304,035

3,899,706

3,806,134

4 Contingencies (activated)

167,903

502,112

490,064

5 Enrichment

 

550,000

413,223

6 One-off costs

225,000

 

 

Total

2,574,136

5,279,091

5,006,942

Financing Plan (in Euro)

 

 

 

7 Capital injection WWR/WC

840,000

804,900

155,100

8 Capital injection FMO

200,000

191,643

36,929

9 Capital injection Triodos

200,000

191,643

36,929

10 WBH subloan FMO

164,805

689,914

688,138

11 WBH subloan Triodos

79,305

191,643

157,623

12 WWR Bio subloan FMO

721,680

1,743,950

1,434,370

13 WWR Bio subloan Triodos

269,639

651,586

535,919

14 WWR Bio loan DBBL

372,736

900,721

740,829

Total

2,848,164

5,366,000

3,785,836

 

Projected Operating Results

 

 

Amounts in x1000 EUR

2008

2009

2010

2011

2012

2013

2014

2015

Turnover

1,537

6,323

6,178

11,293

10,986

9,367

8,852

8,365

EBITDA

412

2,541

2,447

4,550

4,584

3,313

3,122

2,942

Net profit

-129

1114

1169

2692

1767

1117

1100

1137

Operational cash flow

220

1,416

2,477

3,484

4,648

3,650

3,230

3,043

Cash at end of year

240

999

1,177

2,804

4,704

6,257

6,151

5,993

 

 

 

 

 

 

 

 

 

Balance sheet total

7,989

9,502

13,941

16,018

16,902

17,158

16,163

15,200

Solvency (%)

26%

34%

33%

42%

48%

53%

61%

71%

Risk Bearing Capital as % of TA

82%

81%

85%

88%

92%

95%

95%

95%

Debt/EBITDA

14.05

2.28

3.61

1.83

1.71

2.21

1.76

1.25

Current ratio

4.37

5.40

5.79

6.48

8.64

11.52

11.84

12.10

DSCR excl. investments

2.03

3.87

4.07

5.39

4.63

4.00

2.26

2.47

 

Tenor/Repayment Period

 

Tenor:

Tranche I – IV : for the loans, 10 years from the financial close, with a grace period of 6 years.

Tranche V: (6 years) from Financial Close with a grace period of 12 months.

Repayment Period:

Tranche I-IV: In 8 semi-annual equal installments with the first such installment due 78 months after the closing date.

Tranche V: In 20 quarterly installments with the first such installment due 15 months after the closing date.

 

 

 

 

 

Perceived Risk as assessed by DBBL:

 

  1. Feedstock risk

  2. Construction risk 

  3. Operational risk

  4. Off-take risk

  5. Land

  6. Revenue from CERs 

  7. Environmental and social risks 

  8. Key Man Risk

  9. Loan Structure

  10. Risk

 

 

 

Feedstock risk:

            Input of organic waste is guaranteed by a Concession Agreement with the municipality that allows WWR Bio to collect up to 700 ton/day waste from designated areas, like local markets.

Construction risk:

            A compost facility is a relatively easy concept. Also, the construction is done under supervision of the VAR with extensive experience and knowledge

Operational risk:

            Employees will be trained, partly at the VAR in the Netherlands. If major problems occur the VAR will give technical assistance. Management of the companies will come from WCC and WWR and thus have experience with waste management

 

Off-take risk (demand, competition and distribution):

 

            Compost can be used as a substitute for or additional to more expensive fertilizers. The compost market is only marginally developed, while the domestic fertilizer market can not foresee in total demand. So (potential) demand is high, while competition is low. Because the compost will be tailor made for different crops it can be sold during the whole year. WWR Bio negotiates on agreements with end-users directly and off-take agreements with wholesalers/distributors. Own distribution will then be considered later

Land:

            For the first 100-130 ton/day capacity land is acquired under a lease contract, which might not be sustainable. DBBL’s investment is however limited to EUR 0.372 m in the first phase and for subsequent phases it is required that land is obtained in ownership.

Revenue from CERs:

            The used methodologies are approved as CDM projects and thus CERs will be generated as soon as the compost facility is operational. The price of CERs stays, nevertheless, very insecure, but profits of the project are mainly generated by selling (enriched) compost

           

            DBBL assumed a fixed selling price of Euro 8 per unit CER

Environmental and social risks:

 

            The project has significant environmental and social positive impacts, the most important being the reduction of greenhouse gas emissions, the production of soil improving compost and the offering of livelihood opportunities and improvements for poor and marginalized people. Potential adverse impacts do exist, but are limited and manageable and they can be mitigated.

 

Key Man Risk:

            The Directors of WWR Bio are A.H. Md. Maqsood Sinha of WCC and a representative of WWR, currently Jan Boone. A.H. Md. Maqsood Sinha has experience with waste management in Bangladesh. A.H. Md. Maqsood Sinha and Jan Boone seem very capable of running WWR Bio. Nevertheless, if Jan Boone or any other key person should fall away, an important financial and business partner is lost (key man risk), especially during construction phase.

 

Loan Structure Risk:

            The tenor for the DBBL’s loans is 6 year, with a grace period of 1 year. DBBL (senior loans) receives security over all fixed and floating assets of WWR Bio.

            Another mitigant is that disbursements of the loans to expand capacity from 100 to 700 ton/day, will be considered only if the project at phase 1 has proven to be a success.

 

Milestones Achieved:

  • Concession Agreement with DCC has  been signed to collect and transport waste

  •  National CDM Board Approval has been obtained

  •  Land lease agreement for 22 years has been signed

  •  Trade licensee obtained

  •  Land use clearance obtained

  •  BOI registration obtained

  •  Third party verification of Environmental and Social Compliance  has been  done

  •  Environmental clearance obtained from DOE

  •  Work permit for the WWR engineer has been obtained

  •  Import permit has been obtained

  •  Land development completed

  •  Detailed Engineering design completed

  •  Major construction works for phase 1 completed by  March 2008

  •  The project has gone into trial operation end of March 2008

  •  Pending : Registration of compost/enriched compost

 

 

 

DBBL to finance First CDM project in Bangladesh

 

        Commercial lenders are cautious in providing new loans particularly to projects involving unfamiliar technologies.

        Technologies, equipment & processes relevant for CDM are available commercially, many of which offer viable economic returns; yet, not many of such projects are being implemented in Asia compared to what can be potentially achieved.

        Bangladesh is yet to see any lender, other than DBBL, to finance CDM project.

        DBBL wishes to extend thanks to FMO for involving it with the country’s first ever CDM project.

 

 

 

 

 

 

 

Summing up – DBBL’s Feeling

 

 

         An adequate risk-sharing structure is often difficult to put in place and almost always creates unanticipated delays in achieving financial closing.

         Risk should be allocated, by contract, to the party that is best able to mitigate or control.

         Completion risk could be avoided by implementing such project in phases.

         There should be transfer of technical know-how from Annex I country.

         Carbon Credit market development needs accelerators. Action by participating players needed – advisors, buyers, FIs, government to put in place the necessary accelerators.

         Regulatory support needed.

         Lenders should have greater oversight of the project. They should have control the application of cash flows.

         First time lenders for projects like CDM should be in  the senior loan category. Equity and quasi equity should be invested first.

         Banks need assets to back-up; however, CDM project is often not asset based but idea based.

         Documentation is lengthy and complex, and costs a great deal to put into place.

         Success of WWR Bio is crucial for other lenders to finance CDM project.

         Bangladesh is an attractive market for CDM.

         DBBL will embark on the lessons learned to take on more such viable CDM projects. Journey has just begun.