Feasibility of a national programme on domestic biogas in Bangladesh
This report presents the finding of a study conducted by the Netherlands Development Organisation (SNV)
Member : a) Mr. Wim J. van Nes,
b)Mr.
Willem Boers andc) Mr. Khurseed-Ul-Islam
Netherlands Development Organisation Biogas Practice Team
Address : Bezuidenhoutseweg 161 2594 AG The Hague The Netherlands
E-mail: nesvliet04@yahoo.co.uk , wboers@snv.org.np , dkislam05@yahoo.com
August 2005
Acknowledgement
It was a pleasure to conduct this study on the feasibility of a national biogas programme in Bangladesh. We received full cooperation during the interviews, field visits and workshop and were amply provided with valuable information and opinions. We like to extend our gratitude to all respondents and informants for their constructive contributions and hope the outcome of this assessment will serve its purpose.

Executive summary
This report presents the finding of a study conducted by the Netherlands Development Organisation (SNV) to assess the feasibility to set-up and implement a national programme on domestic biogas in Bangladesh. This study included a mission of three weeks in Bangladesh in March 2005 making use of the following methodologies:
-
Field visits to get an impression on the performance of biogas plants and to collect more practical information on modalities of biogas projects implemented in Bangladesh so far.
-
Interviews with informants and potential stakeholders.
-
A half-day Workshop to present the findings of the field visits and interviews and to generate discussion among the stakeholders on a number of key-issues.
-
Rating of key conditions for large-scale dissemination of biogas plants in Bangladesh.
A national programme on domestic biogas in Bangladesh looks feasible as:
-
Bangladesh has already a rich history in domestic biogas with close to 24,000 units constructed throughout the country so far. ƒ The technical potential for biogas amounts to minimum one million units, while there are no strong limiting social factors.
-
The financial analysis indicates that an amount of Taka 7,000 as investment subsidy is generally sufficient to attract potential farmers resulting in a satisfactory financial rate of return (FIRR) of 15 percent for the farmer. The actual FIRR realized by the farmer, however, is largely dependent on the actual financial price for biomass. This underlines the need for an effective micro-credit facility. The economic internal rate of return (EIRR) for the biogas plant is 17 percent in the base case.
-
Bangladesh is endowed with an impressive number and variety of institutes, organisations and companies potentially able to participate in the implementation of a national programme. This organisational richness makes the establishment of a separate programme office unnecessary.
-
There is a clear will and interest among (potential) stakeholders to be engaged in a national programme.
The tentative outline for the national programme with a longer-term vision to develop a commercial, sustainable biogas sector includes the production of 36,450 biogas plants up to 2009 and will cost about Euro 14.7 million. The biogas farmers, Directorate General for International Cooperation (DGIS), Netherlands Development Organisation (SNV) and the Government of Bangladesh (GoB) are the proposed financiers of the programme, to be supplemented by a provider of a refinancing facility for the credit requirements. The cost/benefit ratio of CDM financing still needs to be determined. It has been assumed that the GoB will fully support a national biogas programme and that (potential) stakeholders will agree to up-grade the quality of products and services. The long period required for the approval of an implementation plan is considered a risk, all the more since the dissemination of biogas plants has come to a standstill in June 2004.
-
The following are the main recommendations resulting from this feasibility study: ƒ To SNV: To start with immediate effect the process of registering SNV as an international INGO in Bangladesh.
-
To SNV: To field a mission in July or August 2005 to select an implementing partner and sign a MoU with this partner for the formulation of a detailed implementation document.
-
To SNV and selected implementing partner: To formulate the detailed implementation document in cooperation with all potential stakeholders in Bangladesh in the period September to December 2005.
-
To SNV, selected implementing partner and other main involved stakeholders: To pursue approval of the detailed implementation document, to make the required preparations and to start implementation of the programme in 2006.
Table of Contents
ACKNOWLEDGEMENT .............................................................................................. I
EXECUTIVE SUMMARY ........................................................................................... II
TABLE OF CONTENTS ............................................................................................. IV
ABBREVIATIONS....................................................................................................... VI
CHAPTER 1: INTRODUCTION AND BACKGROUND..................................... 8
CHAPTER 2: OBJECTIVE, METHODOLOGY AND LIMITATIONS ............ 9
2.1 OBJECTIVE .......................................................................................................... 9
2.2 METHODOLOGY AND LIMITATIONS
.....................................................................
9
CHAPTER 3: COUNTRY BACKGROUND ........................................................ 10
3.1 AGRICULTURAL SECTOR ................................................................................... 11
3.2 ENERGY SECTOR
...............................................................................................
13
CHAPTER 4: HISTORY ON DOMESTIC BIOGAS IN BANGLADESH........ 15
4.1 INSTALLATIONS AND PROJECTS............................................................. 15
4.2 TECHNICAL ASPECTS............................................................................. 16
4.2.1 Size of the plants and retention time......................................................... 18
4.2.2 Construction materials ............................................................................. 18
4.2.3 Inlet and inlet pipe.................................................................................... 18
4.2.4 Digester .................................................................................................... 19
4.2.5 Outlet and slurry pit ................................................................................. 20
4.2.6 Pipeline and appliances............................................................................ 21
4.2.7 Overall quality management
....................................................................
23
4.3 BENEFITS OF BIOGAS
PLANTS................................................................
23
4.4 FINANCIAL ASPECTS............................................................................... 25
4.4.1 Investment costs...................................................................................... 25
4.4.2 Investment subsidy.................................................................................. 25
4.5 OVERALL
CONCLUSION..........................................................................
25
CHAPTER 5: POTENTIAL DEMAND FOR DOMESTIC BIOGAS
............... 26
5.1 TECHNICAL FACTORS........................................................................................ 26
5.2 SOCIAL FACTORS............................................................................................... 27
5.3 ABILITY TO PAY ................................................................................................ 28
5.4 FINANCIAL ANALYSIS........................................................................................ 28
5.5 ECONOMIC ANALYSIS ....................................................................................... 29
5.6 OVERALL
CONCLUSION.....................................................................................
31
CHAPTER 6: OVERVIEW OF (POTENTIAL) STAKEHOLDERS
................ 32
6.1 GOVERNMENT ORGANISATIONS ........................................................................ 32
6.1.1 Bangladesh Council of Scientific and Industrial Research ...................... 32
6.1.2 Local Government Engineering Department ........................................... 32
6.1.3 Ministry of Power, Energy and Mineral Resources ................................. 33
6.1.4 Infrastructure Development Company Limited ........................................ 34
6.1.5 Bangladesh Agricultural Research Institute ............................................ 34
6.1.6 Department of Agricultural Extension ..................................................... 35
6.2 CIVIL SECTOR ORGANISATIONS ......................................................................... 36
6.2.1 BRAC ........................................................................................................ 36
6.2.2 Grameen Shakti ........................................................................................ 36
6.2.3 Bangladesh Centre for Advanced Studies ................................................ 37
6.2.4 PKSF......................................................................................................... 37
6.3 PRIVATE SECTOR ORGANISATIONS .................................................................... 38
6.3.1 Agency holders
.........................................................................................
38
CHAPTER 7: REQUIRED FUNCTIONS AND SUITABLE ACTORS
............ 39
CHAPTER 8: OUTLINE FOR A NATIONAL BIOGAS PROGRAMME ....... 42
8.1
CONSTRAINTS FOR A NATIONAL PROGRAMME...................................................
42
8.2 OBJECTIVES OF THE PROGRAMME ..................................................................... 43
8.3 INITIAL GEOGRAPHICAL COVERAGE .................................................................. 43
8.4 IMPLEMENTING PARTNER.................................................................................. 43
8.5 PRODUCTION, BUDGET AND FINANCING ............................................................ 44
8.6 ASSUMPTIONS AND RISKS
.................................................................................
45
CHAPTER 9: MAIN CONCLUSIONS AND RECOMMENDATIONS............
46
9.1 MAIN CONCLUSIONS ......................................................................................... 46
9.2 MAIN RECOMMENDATIONS
...............................................................................
46
CHAPTER 10: REFERENCES
...............................................................................
48
ANNEX 1: TERMS OF REFERENCE
......................................................................
50
ANNEX 2: PROGRAMME OF THE MISSION....................................................... 52
ANNEX 3: BRIEF REPORT ON THE CONSULTATIVE
STAKEHOLDERS WORKSHOP ..... 54
ANNEX 4: CONTACT DETAILS OF INFORMANTS AND
RESPONDENTS ... 56
ANNEX 5: FINDINGS OF INTERVIEWS WITH STAKEHOLDERS ................. 57
ANNEX 6: INVESTMENT COSTS OF BIOGAS PLANTS.................................... 60
ANNEX 7: BASIC DATA FOR THE FINANCIAL ANALYSIS OF BIOGAS
PLANT WITH A DAILY GAS OUTPUT OF 100 CFT
........................................... 62
ANNEX 8: BASIC DATA FOR THE ECONOMIC
ANALYSIS OF BIOGAS
PLANT WITH A DAILY GAS OUTPUT OF 100 CFT
........................................... 63
ANNEX 9: KEY CONDITIONS FOR LARGE-SCALE
DISSEMINATION OF
BIOGAS PLANTS IN BANGLADESH
.....................................................................
64
ANNEX 10: BRIEF REPORT ON THE 2ND CONSULTATIVE STAKEHOLDERS
WORKSHOP
................................................................................................................
65
Abbreviations
ADB AEC ASA BARC BARD BARI BAU BBBB BBSBCAS BSCIC BCSIRBDT BIDS BIM BLRI BPDB BPC BPT BRACBRDB BRRI BSP BSTI BUET CDM Cft CIRDAP CMES COASTDAE DANIDA DGIS DLS DoE EIRR EPRC ERD FIRR FY GDP GEF GIGOB GS GTZ HSDHYVIDAIDCOL IDF Asian Development Bank Atomic Energy Commission Association for Social Advancement Bangladesh Agricultural Research Council Bangladesh Academy for Rural Development Bangladesh Agricultural Research Institute Bangladesh Agricultural University Bangladesh Bureau of Biogas and Bio-technology Bangladesh Bureau of Statistics Bangladesh Centre for Advanced Studies Bangladesh Small & Cottage Industries Corporation Bangladesh Council of Scientific and Industrial Research Bangladesh Taka (1 Euro is equal to about 85 Taka) Bangladesh Institute for Development Studies Bangladesh Institute for Management Bangladesh Livestock Research Institute Bangladesh Power Development Board Bangladesh Petroleum Corporation Biogas Practice Team (SNV) Bangladesh Rural Advancement Committee Bangladesh Rural Development Board Bangladesh Rice Research Institute Biogas Support Programme (Nepal) Bangladesh Standards and Testing Institute Bangladesh University of Engineering and Technology Clean Development Mechanism (under the Kyoto protocol) Cubic feet (28.3 litres) Centre on Integrated Rural Development for Asia & the Pacific Centre for Mass Education in Science Coastal Association for Social Transformation Trust Department of Agricultural Extension Danish International Development Agency Directorate General for International Cooperation (Netherlands) Department of Livestock Services Department of Environment Economic Internal Rate of Return Environment & Population Research Centre Economic Relations Division (MoFP) Financial Internal Rate of Return Fiscal Year Gross Domestic Product Global Environment Facility Galvanised Iron Government of Bangladesh Grameen Shakti German Technical Cooperation High Speed Diesel High Yielding Variations International Development Association Infrastructure Development Company Ltd. Integrated Development Foundation IFAD International Fund for Agricultural Development IFRD Institute for Fuel Research and Development IMED Implementation Monitoring and Evaluation Division (MoFP) INGO International Non Governmental Organisation IPP Independent Power Producer ISO International Standard Organisation KfW Kreditanstalt für Wiederaufbau (German Development Bank) kgOE Kilogram Oil Equivalent LA Line Agency LGED Local Government Engineering Department (GOB) MFI Micro Finance Institute MoA Ministry of Agriculture (GOB) MoFP Ministry of Finance and Planning (GOB) MoPEMR Ministry of Power, Energy & Mineral Resources (GOB) MoSICT Ministry of Science, Information & Communication Technology (GOB) MoU Memorandum of Understanding NGO Non Governmental Organisation NGOAB NGO Affairs Bureau PKSF Palli Karma Sahayak Foundation PO Partner Organisation PP Project Proforma PROSHIKA Proshika Manobik Unnayan Kendra PURE Promotion of the Use of Renewable Energies (GTZ) QC Quality Control RCC Reinforced Cast Concrete R&D Research & Development RE Renewable Energy REB Rural Electrification Board REDA Renewable Energy Development Agency REIN Renewable Energy Information Network REREDP Rural Electrification and Renewable Energy Development Project RET Renewable Energy Technology RNE Royal Netherlands Embassy SET Sustainable Energy Technology SEU Sustainable Energy Unit (under MoPEMR) SHS Solar Home System SKO Superior Kerosene Oil SNV Netherlands Development Organisation TAPP Technical Assistance Project Proforma TMSS Thengamara Mohila Sabuj Sangha UNDP United Nations Development Programme USAID US Agency for International Development USD Unites States Dollar WB World Bank WWF World Wildlife Foundation
Exchange rate: 1 Euro = 78 Taka (June 2005) 1 USD = 64 Taka
CHAPTER
1:
Introduction and background
Based on positive experiences with the dissemination of domestic biogas in Nepal, the Board of Directors of SNV Netherlands Development Organisation decided in June 2004 to launch an initiative for up-scaling of domestic biogas in a number of Asian countries. This initiative received financial support by the Directorate-General for International Cooperation (DGIS) of the Dutch Ministry of Foreign Affairs in the framework of the Asia Biogas Programme. The People’s Republic of Bangladesh was identified as one of the potential countries. A brief fact finding mission was conducted in November 2004 (Lam and Boers, 2005). This mission concluded that the circumstances in Bangladesh seem favourable to establish a national biogas programme and recommended commissioning of an in-depth study on its feasibility. The Terms of Reference for this feasibility study are provided as Annex 1.

This report presents the findings of the feasibility study conducted in March 2005 by two members of the Biogas Practice Team (BPT) of SNV, Wim van Nes and Willem Boers, and one independent local expert, Dr. Khurseed-Ul-Islam.
Chapter 2 describes the objective, methodology and limitations of the feasibility study. A brief background including the agricultural and energy sector of the Republic of Bangladesh is provided in Chapter 3. The history of domestic biogas in the country is summarised in Chapter
4. An assessment of the potential demand for domestic biogas including the financial and economic internal rates of return is presented in Chapter 5. An overview of potential stakeholders is provided in Chapter 6, while the functions required in a national programme and possible suitable actors are matched in Chapter 7. An outline for a national biogas programme including tentative budget and possible financiers is provided in Chapter 8. Main conclusions and recommendations of the study are mentioned in Chapter 9. More specific conclusions and recommendations are presented in the respective chapters. The references, finally, are included as Chapter 10.
CHAPTER 2: Objective, methodology and limitations
2.1 Objective
The objective of the study is to assess the feasibility to set-up and implement a national programme on domestic biogas in the Republic of Bangladesh.

2.2 Methodology and limitations
The following methodologies were used to achieve the objective of the study:
-
Preparation of the mission to Bangladesh through analyses of secondary data including documents collected during the fact finding mission in November 2004. The programme of the mission is added as Annex 2, while the contact details of the informants and respondents are included in Annex 4.
-
Field visits to get an impression on the performance of biogas plants and to collect more practical information on the different modalities of biogas projects implemented in Bangladesh so far. The mission team was facilitated by BRAC (one day), LGED (two days) and BCSIR (two days), see Annex 2 for information on the visited areas. A check-list was prepared for the collection of data during the field visits.
-
Interviews with informants and potential stakeholders for a national programme on domestic biogas. To structure the interviews with the stakeholders, a check-list was prepared. The main findings of the interviews with the respondents are summarised in Annex 5.
-
A half-day Workshop to present the findings of the field visits and interviews and to generate discussion among the stakeholders on a number of key-issues. A brief report on this Workshop including the list of participants is included as Annex 3.
-
Rating of key conditions for large-scale dissemination of biogas plants in Bangladesh. These conditions are included as Annex 9.
Prior to the mission, it proved to be quite difficult to get into contact with the stakeholders already approached during the fact finding mission in November 2004. Hence, it was not easy to compose in advance the mission programme. After arrival in Dhaka however, the team received a maximum of cooperation from stakeholders and informants and the programme could be planned and implemented without any problem.
The results of the study were presented to the (potential) stakeholders in a second Consultative Workshop on 24 July 2005 at Dhaka, see Annex 10.
CHAPTER 3: Country background
Bangladesh, officially People's Republic of Bangladesh, borders on the Bay of Bengal in the south; on the Indian states of West Bengal in the west and north, Assam and Meghalaya in the northeast, and Tripura and Mizoram in the east; and on Myanmar in the southeast. Dhaka is the capital and largest city; the nation's other major city is Chittagong. A humid, low-lying, alluvial region, Bangladesh is composed mainly of the great combined delta of the Ganges, Brahmaputra, and Meghna rivers. Except for the Chittagong Hills along the Myanmar border, most of the country is no more than 90 m above sea level. Bangladesh is laced with numerous streams, distributaries, and tidal creeks, forming an intricate network of waterways that constitutes the country's main transportation system. Along the south-western coast is the Sundarbans, a mangrove swamp area with numerous low islands.

Bangladesh has a tropical monsoon climate with a distinct dry season in the winter. It receives an average annual rainfall of about 2,000 mm, with most falling during the summer monsoon period; the Sylhet district in the northeast is the wettest part of the country, having an annual average rainfall of 3,560 mm. The low-lying delta region is subject to severe flooding from monsoon rains, cyclones, and storm surges that bring major crop damage and high loss of life. The cyclones of 1970 and 1991 and the monsoon floods of 1988, 1998, and 2004 were particularly devastating.
Bangladesh is one of the world's ten most populated countries with an estimated current population of 144 million and has one of the highest population densities (almost 1,000 people per sq km) with an annual growth of 1.7%. The great majority of Bangladesh's population is Bengali, although Biharis and several tribal groups constitute significant minority communities. About 88% of the population is Sunni Muslim and over 10% is Hindu. Bengali is the nation's official language, and English is used in urban centres. Bangladesh has a predominantly rural population, with over 60% of the workforce engaged in agriculture.
Bangladesh is one of the world's poorest nations, with overpopulation adding to its economic woes, and it is heavily reliant on foreign aid. The country's economy is based on agriculture. Rice, jute, tea, sugarcane, tobacco, and wheat are the chief crops. Fishing is also an important economic activity, and beef, dairy products, and poultry are also produced. Except for natural gas (found along its eastern border), limited quantities of oil (in the Bay of Bengal), coal, and some uranium, Bangladesh possesses few minerals.
Dhaka and Chittagong (the country's chief port) are the principal industrial centres; clothing and cotton textiles, jute products, processed food, steel, and chemical fertilizers are manufactured. In addition to clothing, textiles, jute, and jute products, exports include tea, leather, fish, and shrimp. Remittances from several million Bangladeshis working abroad are the second largest source of foreign income. Capital goods, petroleum, and textiles are major imports. Western Europe, the United States, India, and China are the main trading partners. Economic performance has been relatively strong in the past decade, with annual GDP growth averaging five percent. The gross national income per capita in 2003 amounted to USD 400 (World Bank, April 2005).
After its independence in 1971, Bangladesh is governed by the constitution of 1972 (amended several times). The president is chief of state, a largely ceremonial position, and the prime minister is head of government. There is a 330-seat national assembly, with most members popularly elected (30 seats are reserved for women). The major political parties are the Bangladesh Nationalist party, the Awami League, and the Jatiya party. The nation is per 2001 administratively divided into 6 divisions, 64 districts, 507 upazila’s (sub-districts), 4,484 unions and 59,990 mouza’s.
3.1 Agricultural sector
Bangladesh, a predominantly agrarian economy, is characterized by small-scale, fragmented farming. Though the country has achieved near self sufficiency, the majority of the population lack food security. Agriculture serves as the mainstay of the population contributing about half of the Gross Domestic Product (GDP) and employing over 60% of the total labour force. All the cultivable land is in use and the increasing population pressure dramatically reduced the average farm size holdings to less than a hectare. The role of agriculture in economic development is declining. From 1972/73 to 1993/94 (a 22 year span), the agricultural growth rate was about 3.1% while the industrial and service sector growth rates were much higher, 8.8% and 8.6%, respectively.
Though the basic aim of agricultural development policies over the last four decades remained at increased food production, the program components underwent vast changes shifting from one category to the other. In the early 1960s, flooding during the monsoon and lack of irrigation facilities during the dry periods were identified as the major constraints hindering use of modern agricultural inputs. As such, the government aimed at building large scale irrigation and drainage facilities. In the late 1960s, when major thrust was given in promoting "green revolution", the program strategies shifted from building large scale irrigation installations to more divisible and modern techniques of irrigation coupled with increased distribution of highly subsidized chemical fertilizer and HYVs of rice. In the early 1970s, HYVs of wheat were introduced. During the initial years until the early 1970s, HYVs of rice used to be imported directly. However, subsequently the Bangladesh agricultural research system adapted and indigenously developed different varieties of rice and wheat which were then multiplied and released for farm production.
Most of the farm households keep livestock but usually their quality is poor. Cattle and buffalo are fed principally on agricultural by-products, such as crop residues. They are grazed on natural pastures of non-arable land. During the day, they are allowed to graze on communal grazing land, natural pasture, homestead forest or fallow land. Sometimes, cows with calves are kept tethered just outside the house. Since no arable land is available for livestock feed production, non-arable land contributes most of the green fodder for ruminant animals. Using shrub and tree leaves, and tender shoots and twigs as fodder is traditional in the villages.

In rural Bangladesh, women are major but largely unrecognised contributors to agricultural and economic productivity. The involvement of rural women in decision-making activities (independently or as part of a group), in particular in decisions relating to feeding, breeding, management, veterinary health care and marketing products of dairy is considerable (Islam et al, 1999). Paul and Saadullah (1991) reported that women carry out 25% of crop, 17% of cattle, 21% of goat and 52% of milk sales.
Rearing of dairy cattle has been increasingly viewed as a means of alleviating poverty in Bangladesh and is believed to improve the livelihoods of landless and small households. Many non-governmental organisations (NGOs), such as Proshika Manobik Unnayan Kendra (PROSHIKA), BRAC (Bangladesh Rural Advancement Committee), Grameen Bank and Aftab Dairy, are involved in the promotion of micro-credit for small livestock enterprises including dairy cattle production.
As an input to cropping systems, dung continues to be an important link between crop and animal production in Bangladesh. The yearly total cattle dung production in Bangladesh in 2000 was estimated to be 80 million tonnes of which 68 and 52% is used as manure in rural and urban areas, respectively. The use of dung as fuel is mostly on small farms and represents 25% of total production (DLS 2000). Hossain (June 2003) mentioned somehow different figures on the use of dung: 46% as fertiliser, 34% as cooking fuel and 5% as building material, while 15% is not used at all.
Depletion of soil fertility in Bangladesh is mainly due to exploitation of land without proper replenishment of plant nutrients in soils. The problem is enhanced by intensive land use without appropriate soil management. The situation is more grave in areas where HYVs are being cultivated with little or no organic recycling. Depletion of organic matter is an important factor in the process of soil fertility decline. A good soil should have an organic matter of more than 3.5%. Most soils in Bangladesh have less than 1.7%, and some soils have even less than 1% organic matter. Crop residues and dung are widely used as fodder and fuel rather than fertiliser. Over the past 20 years, the average organic matter content of top soils (high land and medium highland situation) has gone down from 2% to 1%. Lower land might be less affected due to annual flooding.
3.2 Energy sector
Bangladesh has small reserves of oil and coal, but potentially very large natural gas resources. Commercial energy consumption is around 66% natural gas, with the remainder mostly oil and limited amounts of hydropower and coal. Only around 30% of the population (25% in urban areas and 10% in rural areas) has access to electricity, and per capita commercial energy consumption of about 200 kg of Oil Equivalent (kgOE) is among the lowest in the world.
The total recoverable reserves of natural gas are 439 billion m3 (i.e. 15.5 trillion cft) of which 110 billion m3 was produced up to June 2000. The gas is being used for the manufacturing of fertiliser, generation of electricity, for direct use in some industries and as cooking fuel in major urban areas. Economically, it will not be feasible to supply the gas to the rural areas through pipelines. Petroleum products like High Speed Diesel Oil (HSD) and Superior Kerosene Oil (SKO) are predominantly used for transport and rural lighting. The total consumption of petroleum in 2000 was 3.23 million ton, all of which was imported. The yearly consumption of coal in the country is over 1 million tonne, almost exclusively used for brick burning and met by imports. The total coal deposits located in North Bengal are 1.75 billion tonnes. Mining has started on a small scale by Baropukuria Coal Mines under Petrobangla, the national agency for exploration and production of oil, gas and minerals under the Ministry of Power, Energy and Mineral Resources (MoPEMR). The coal from this mine will be used in a power plant currently under construction. The total peat deposits of the country are about 150 million tonnes, but the costs of mining with the current technology are high. Bangladesh, being a rather flat country, is not very much endowed with hydro-electric potential. The total potential is estimated to be 755 MW with a total installed capacity of 230 MW.
Biomass or traditional fuels are estimated to account for over half (about 55%) of the country's energy consumption. They comprise of agricultural residues, mainly from rice and wheat plants, paddy hush and bran, bagasse, jute sticks; materials of tree origin like twigs, leaves and fuel wood; charcoal; and animal (cattle) dung. The total amount of biomass fuels consumed in the year 2000 was approximately 45 million tonnes. Most of the people in Bangladesh live in rural areas and use traditional stoves for cooking of three meals (morning, afternoon and evening) and other heating purposes. Biomass fuels are commonly available in and around the family compound. During the raining period (flooding), it becomes more difficult to collect sufficient quantities of biomass fuels making more well-to-do families to purchase firewood. The stove used for cooking is usually a mud-built cylinder with three raised points on which the cooking pot rests. One opening between these raised points is used as the fuel-feeding port and the other two for flue gas exit. The stove may be built under- or overground. In some cases, two potholes are joined together and a single fuel-feeding port is made for common use. The efficiencies of these stoves are quite low and vary between 5 and 15%.

Dasgupta et al. (September 2004, October 2004) investigated indoor air pollution, more in particular respirable airborne particulates from cooking in Bangladesh. Biomass fuels caused as expected much more pollution than clean fuels like natural gas and kerosene. It also appeared however that household specific factors like cooking locations, construction materials and ventilation processes matter more than fuel choice in determining the concentration of the particulates.
Use of biomass fuels for cooking purposes rather than for its use as an organic fertiliser maintaining the fertility of the soil has obvious disadvantages. Biogas technology is therefore an attractive alternative for farmers keeping cattle in rural areas. In those areas, natural gas, coal and electricity do not qualify as cooking fuel for various reasons. Kerosene and LPG could be considered as alternatives as well, but are quite expensive (Taka 25 per litre respectively Taka 500 to 600 per cylinder depending on distance) and not everywhere and/or always available.
CHAPTER
4: History on domestic biogas in Bangladesh
Based on the field visits, interviews and publications, this Chapter provides a brief overview of the history of domestic biogas in Bangladesh with respect to number of plants installed and projects (paragraph 4,1), technical aspects (paragraph 4.2), benefits of biogas plants (paragraph 4.3) and financial aspects (paragraph 4.4). The overall conclusion is provided in paragraph 4.5.
4.1 Installations and projects
The Institute for Fuel Research and Development (IFRD) of Bangladesh Council of Scientific and Industrial Research (BCSIR) has been the main actor for the dissemination of domestic biogas plants in Bangladesh till date. Other organisations being involved at different stages have been BRAC, Local Government Engineering Department (LGED), Department of Environment (DoE), Grameen Shakti (GS), Bangladesh Agricultural University (BAU), Bangladesh Small & Cottage Industries Corporation (BSCIC), Danish International Development Agency (DANIDA) and Department of Livestock Services (DLS). In total, close to 24,000 family-sized biogas plants of different designs have been installed throughout Bangladesh so far. Due to termination of projects, installation of biogas plants has been stopped almost completely since June 2004. Table 4-1 presents a summary of the number of plants disseminated by the different organisations. A chronological narrative description is provided below this table.
|
Table 4-1 Organisations involved in the dissemination of biogas plants in Bangladesh and number of plants installed1 Organisation |
Period |
Number of plants installed |
|
Bangladesh Council of Scientific & Industrial Research |
1973-2005 |
22,100 |
|
Local Government Engineering Department |
1985-2001 |
1,142 |
|
Department of Environment |
1979-1983 |
260 |
|
Bangladesh Rural Advancement Committee |
1987-2005 |
80 |
|
Department of Livestock |
1988-1994 |
70 |
|
Grameen Shakti |
1987-2005 |
70 |
|
Bangladesh Small & Cottage Industries Corporation |
1983-1988 |
30 |
|
Bangladesh Agricultural Development Corporation |
1983-1984 |
20 |
|
Danish International Development Agency |
1982 |
4 |
|
Bangladesh Agricultural University |
1971-1973 |
2 |
|
Housing & Building Research Institute |
1981 |
2 |
|
Bangladesh Academy for Rural Development |
1974 |
1 |
|
Bangladesh Commission for Christian Development |
1978 |
1 |
|
Bangladesh Agricultural Research Institute |
1983 |
1 |
|
Bangladesh Rice Research Institute |
1983 |
1 |
|
Total |
1971-2005 |
23,784 |
In 1972, BAU set up a first floating-drum plant in the University campus to study the characteristics of gas production, followed later by a plant that provided gas for cooking and lighting for a family of six members. In the campus of BCSIR, another plant was constructed by IFRD in 1976, followed by a plant at the KBM College in Dinajpur in 1980. As the construction costs were high and no subsidy available, only few plants (72) were constructed by well-to-do farmers with technical assistance by IFRD. In 1981, DoE started its programme through which about 150 floating-drum and 110 fixed dome plants were installed by contractors free of cost. Other efforts were undertaken by BSCIC (a number of plants), DANIDA (few trench and bag
1 This table has been on request compiled by BCSIR. Some of the plants mentioned under BCSIR were installed by other parties like BRAC.
type digesters), LGED (over 200 plants) and DLS (about 70 plants). Also the Grameen Bank installed 17 plastic bag digesters. Under the “Fuel Saving Project” implemented from 1989 to 1991, IFRD trained local youths who constructed in total 146 plants in the premises of well-to-do farmers. The gas holder was supplied free of cost. In 1994, LGED supported the establishment of an ecological village (Amgram in Madaripur district) among others by converting 95 open latrines into family plants.
An important dissemination push was delivered by the “Biogas Pilot Plant (1st phase) Project” implemented by BCSIR in the period July 1995 to June 2000. In total 4,664 fixed dome plants were constructed throughout the country. BCSIR employed and trained 128 diploma civil engineers who were assigned responsibilities for motivation, installation and after sales service throughout the country. In addition, 898 youths were trained to support the project. The biogas farmers received an investment subsidy of Taka 5,000 under the project. MoUs were signed between BCSIR and several other institutes like BRAC, LGED and DLS for research, training and dissemination of the biogas technology. The cooperation with BRAC was the most successful as this organisation managed to motivate about 1,200 farmers. An interim evaluation report in 1999 reported 99% of the plants installed under the project in operation, while 91% of the owners could meet their household fuel demand through biogas. Bio-slurry from the biogas plants was used in horticulture, pisciculture and agriculture. The average saving per plant amounted to Taka 759 per month (BCSIR, June 2001).
As the 1st phase was successfully completed and the potential for biogas in Bangladesh considered huge, BCSIR implemented the 2nd phase of the Biogas Pilot Plant in the period July 2000 to June 2004. The target for this phase was put on 20,000 biogas plants, out of which 17,194 plants were finally realised. The investment subsidy for the owner was increased to Taka 7,500 per plant. In addition to the diploma civil engineers employed and paid on a monthly basis by BCSIR, an agency system was introduced on incentive basis. About 50 agencies were recognised in defined areas (mostly districts) and received a lump sum fee of Taka 5,000 per plant as service charge. About 1,000 masons and youths were trained under the project as well.
In the period from October 1998 to June 2003, the LGED implemented a parallel biogas project aiming to install 1,900 domestic plants. As the investment subsidy for this project amounted to Taka 5,000 only, it proved to be rather difficult to motivate farmers during the implementation of the 2nd phase of the Biogas Pilot Plant Project when BCSIR was providing a subsidy of Taka 7,500 to farmers. Therefore, the LGED project was terminated prematurely, after having constructed about 1,120 biogas plants. Under the Secondary Town Infrastructure Development Project-II, another 20 domestic plants were installed using human excreta only.
Of more recent date is the initiative of GS aiming to construct not less than 200,000 biogas plants within a period of five years. This initiative is still in the preparatory phase; at the time of the mission a total of 10 plants were installed or under construction. Agency holders also continued to construct plants without any subsidy in very limited numbers after the termination of the 2nd phase of the BCSIR pilot project in June 2004.
4.2 Technical aspects
All main categories of designs for domestic biogas plants have been applied in Bangladesh, but like in other Asian countries the fixed-dome digester has become the most popular design. The model promoted by BCSIR in both phases of the Biogas Pilot Project originates from a Chinese fixed dome model and has a manhole through the outlet, see Figure 4-1.

LGED made some modifications of the BCSIR model, among others by revising the shape of the outlet (from rectangular to round) and by putting a RCC ring beam, see Figure 4-2.
4.2.1 Size of the plants and retention time
So far, rather big domestic biogas plants have been promoted in Bangladesh. The minimum size is a plant with a daily gas production of 100 cft (2.83 m3) with an intended retention time of 40 days and a daily feeding rate of 60 kg of dung per day2. Respondents explained that this amount of gas would be required by the user to cook three meals a day. Such plants do require quite a large amount of dung for feeding, corresponding with the dung production of approximately six cows. It may be considered:
|
ƒ |
To increase the retention time from 40 to 50 days by increasing the digester (and gas |
|
|
|
storage) volume. This will increase the daily gas production and meet the demand for biogas |
|
|
|
by farmers rearing less heads of cattle. The negative effect will be an increase in the cost of |
|
|
|
the plant with a larger volume. |
|
|
ƒ |
To promote smaller-sized plants with a daily gas production of 2 m3 or even 1 m3. Such |
|
|
|
plants might not fully solve the cooking fuel requirements of the household, but if the |
|
|
|
farmers are provided with reliable information prior to their investment decision, such |
|
|
|
plants will meet their expectations to solve their fuel problem for at least 60 or 70% in a |
|
|
|
cost-effective manner. Smaller-sized plants could significantly increase the market for |
|
|
|
domestic biogas as many farmers in Bangladesh raise a more limited number of cattle. |
|
|
|
4.2.2 |
Construction materials |
Through the field visits and the interviews with different technical staff, an impression was gathered on the quality of the construction materials required for the construction of the biogas plant like cement, sand and aggregate. In Bangladesh, cement is easily available at local markets in both good quality and quantity. Sand is commonly available and in most cases supplied to the construction site. In very few cases, biogas farmers had shovelled up and transported sand by themselves. The observed sand was clean and of good quality. Natural stones and gravel are very scarcely available in Bangladesh and therefore ‘khoa’ is widely used as an acceptable substitute. This ‘khoa’ is produced by crushing class I clay bricks by hand or mechanically. Clean water for construction is commonly available through shallow wells and during flood period also available in local ponds. Water from these ponds might require basic treatment like filtering through a cloth. Also regular shaped bricks from good quality (class I) are commonly available at local markets and transported to the site by the supplier.
4.2.3 Inlet and inlet pipe
Inlet tanks observed during the field visits were constructed of bricks and finished with plaster. None of the inlets was equipped with a fixed mixing device. The dimensions of the inlets varied, most of them were rectangular or square shaped, while some of them had a small extension in which the inlet pipe was situated. This pipe could not at all times be penetrated with a stick or bamboo rod to de-block any solid matter. Also the height of the inlet varied and was in some cases inconvenient for the user while mixing dung and water. A self-made garden rake-a-alike device was sometimes used for mixing.
One RCC pipe with a diameter of 15 cm was installed to connect the inlet with the digester. It was not compulsory or common practice to install a second inlet pipe for (future) connection of a toilet to the digester. On technical drawings of both BCSIR and LGED model,
2 This assumes a biogas production of 47 litres per kg of dung which is at the rather optimistic side. 3 It is assumed that one cattle head produces about 10 kg dung per day that can be collected for biogas production.
the inlet pipe for the input of dung is positioned exactly on the longitudinal centre line of the biogas plant with no variation on this position referred to. However, during the field visits it was often observed that the position of the inlet pipe was approximately 90 degrees versus the centre line. By fitting the inlet pipe under such an angle, the hydraulic retention time might be shorter than intended.

On the technical drawings of the LGED model, the position of the inlet pipe inside the digester seems to be higher than the top of the manhole at the outlet side. This would mean that excess gas will be released through the inlet pipe rather than the outlet. This assumption could not be verified during the field visits. Also, it could not be checked whether the end of the inlet pipe in the digester was level with the wall. It may be considered: ƒ To redesign the inlet by considering a round shape with an appropriate height and a mixing
device for easy operation. ƒ To determine the optimum position of the inlet for dung input versus the longitudinal centre line of the digester. ƒ To position the level of the inlet pipe in the digester below the top of the manhole to ensure undisturbed flow of excess biogas.
4.2.4 Digester
Unfortunately, it was not possible during the field visits to inspect digesters from the inside. Hence, this paragraph is based on publications and interviews. The shape of the floor of both BCSIR and LGED model is spherical and seems appropriate for area with high water table like Bangladesh. There is however a difference in the materials to make the floor. In the BCSIR model both brickwork and cast concrete is used, while the LGED model prescribes the use of cast concrete only. The wall in both designs is made of bricks (125 mm thick).
Also the dome is spherical shaped and made of bricks. The outside of the dome is either finished with a layer of plaster (LGED model) or with a 5 mm layer of cast concrete (BCSIR model). At the edge of the dome of the LGED model, a RCC ring beam is placed for extra strength. A small GI pipe (25 mm) is fitted in the centre of the dome, but not protected by a turret on top of the dome. In most cases, this top is exposed and not covered with compacted earth. The inside of the dome is finished with three layers (cement/sand and waxing) to ensure complete gas tightness.
Figure 4-4 Domes were often not covered with compacted earth, outlets not covered with cast concrete slabs (right) and dome pipes always not protected
It may be considered:
-
To review the materials used for the construction of the dome, making a choice between bricks (finished with a layer of plaster) or cast concrete. A combination of both materials like in the BCSIR model results in unnecessary costs.
-
To review the wax method for making the dome gas tight, as this method is cumbersome for the mason. More labour-friendly methods are available, for example by using acrylic emulsion paint.
-
To drop the RCC ring beam in the LGED model for small-sized digesters with a volume of maximum 20 m3.
-
To double the diameter of the GI dome pipe to 50 mm making it possible to de-block this pipe with a bamboo stick, to protect this pipe on top of the dome with a turret and to cover the dome with a layer of minimal 20 cm compacted earth for protection and reduction of heat losses in the wintertime.
4.2.5 Outlet and slurry pit
The outlet wall towards the dome is constructed either on the dome (BCSIR model) or on top of a beam situated above of the manhole (LGED model). During the field visits, it was observed that the shape of the outlet varied from rectangular to circular. The circular shaped outlet is supposed to be less prone to cracks. On technical drawings of both BCSIR and LGED models, the long side of the rectangle of the outlet is designed parallel to the longitudinal centre line of the biogas plant. However, it was found in the field that the short side of the rectangle of the outlet was parallel to this centre line. No specific reference was made for the required position of the outlet overflow. During the field visits, this overflow was found positioned at will. This will increase the risk of ‘dead areas’ and thus sedimentation in the outlet.
The users were left with the responsibility to decide on putting a reinforced cast concrete outlet slab or a self made outlet cover. In most of the observed biogas plants, the farmers explained that they opted for an improvised cover as concrete slab would result in extra costs. A single slurry pit was observed in most cases. However, the dimensions of the slurry pit seemed to be too small to collect and compost all digested slurry. Also, the pits were not protected from direct sunlight and leaching.
Figure 4-5 Outlets were found rectangular (left) and circular (right) shaped
It may be considered: ƒ To review the shape and positioning of the outlet. ƒ To make it compulsory to put a reinforced concrete slab for covering of the outlet. ƒ To further increase awareness among biogas farmers on the relevance of a proper slurry pit.
4.2.6 Pipeline and appliances
During the field visits, various types and models of main gas valves were observed on top of the GI dome pipe. Teflon tape was commonly used to make this connection gas tight. On the other side of the main valve, a nozzle was fitted for easy connection of the plastic gas pipe, however without a hose clamp. Main gas valves were often wrapped in plastic and showed signs of natural wear, while in some cases the valve was turned black due to gas leakage.
Figure 4-6 Main gas valves were sometimes wrapped in plastic (left)
Biogas was transported to the point of application through flexible plastic gas pipes with a diameter of ¾ inch. Nearby trees and/or houses supported these pipelines, making condensed water at low points to block the pipeline in between the points of support. Although it is easy to take out the water form the pipeline, the recurring nature of this kind of maintenance will discomfort the user. The pipeline is hanging in the open air and is exposed to direct sunlight making the plastic brittle and prone to frequent replacement. The pipeline is vulnerable from damage for example from falling branches, storm and animals. The user him/herself, however, will be able to repair the damage or – if required – even to replace the entire pipeline.

Various types of gas stoves have been observed like stoves with (a) single or double burner(s) and stoves with double burners fitted in galvanised iron, metal or casted frames. Most of the stoves were manufactured in Bangladesh and supplied to the user by the organisation responsible for installing the biogas plant. Biogas stoves seemed not to be available at the local markets. Many users were not satisfied with the lifetime of the stoves. In one case, the user claimed he had to purchase a new stove every year. Corrosion of the burner head was found the main problem of the stoves seen during the field visits. Another common default was the malfunctioning of the gas-regulating knob (internal gas tap). It was also observed that the lit of the burner cup could not be removed for cleaning purposes. Burners were fitted with many small openings, without primary gas–air intake regulating device. The performance of the gas lamps could not be observed during the field visits.

It may be considered:
-
To further increase awareness among biogas users on the importance of closing the main gas valve after having used the gas.
-
To review the different methods of gas transport to the point of application including the installation of a water drain to optimise ease of use in relation to recurring costs.
-
To review the design features of the current biogas stoves and identify areas of improvement in cooperation with users and manufacturers.
-
-
To consider pre-qualification of biogas stoves to ensure a minimum quality.
4.2.7 Overall quality management
For the disbursement of the investment subsidy, name and location of the owner of the biogas plant were properly recorded. However, at the time of completion of the construction of the plant, no formal and recorded (technical) inspection and handing over formalities have been performed by the organisation responsible for construction. Records with (technical) information could not be observed during the field visits.
During or after construction, no independent quality control was conducted to monitor the compliance with specified quality standards. From both users and constructors, it was learnt that contact could be established between each other in case the plant was not functioning properly. After sale service was conducted by negotiation, not on the basis of already agreed terms and conditions for a specified period of time. It may be considered: ƒ To further standardise the design, construction and after sale service of biogas plants and to
further enforce these standards by formal recording and independent quality control.
4.3 Benefits of biogas plants
Domestic biogas plants typically provide benefits (e.g. energy, gender, environment, health) at different levels (household, local, national and global). The LGED Project Proforma (2003) explains in this respect that “benefits may be divided into tangible and intangible benefits. Tangible benefits may be quantified only indirectly through compensation principle, prospective beneficiary being ready to pay towards the cost of the project for the psychological satisfaction, one would have to forego had the project been shelved. These are projects which provide only service benefits which can hardly be quantified. Such benefits may accrue either to an individual or to a community.”

The evaluation of biogas plants established under the first and second phase of the Biogas Pilot Plant Project conducted by DPC Group (June 2004) is the most reliable source of for an overview of the benefits provided by biogas plants. A total of 620 plants were sampled for this evaluation, 400 being first phase plants and 220 second phase plants. The sources of primary data were the (male) owners and the (female) users of the plants. The study covered all six divisions of Bangladesh. The most significant positive and negative effects of biogas plants are summarised in Table 4-2.
Table 4-2 Positive and negative effects of biogas plants constructed under the Biogas Pilot Plant Project as evaluated by the DPC Group
Positive effects of biogas plants:
. • Reduction in bad smell of raw materials presently fed to the biogas plant mentioned by 91% of the owners
. • Produced biogas was used for cooking by 95% of the owners and for lighting by 10% of the owners. Most of the female users (88%) mentioned that the amount of gas was sufficient to meet the cooking needs. The other female users (12%) indicated they used wood, straw and leaves to meet the deficit in biogas supply
. • Bio-slurry used by 81% of all biogas plant owners, mostly as fertiliser (77%), but also as fish feed (23%). Remaining owners drained the slurry (6%), sold it (6%) or gave it to others (7%). Those who sold the slurry, earned between Taka 325 (1st phase owners) and Taka 374 (2nd phase owners) per month.
. • Increased crop production through use of bio-slurry was reported by 60% of the owners. They claimed an increase in crop production of 23% (1st phase owners) to 27% (2nd phase owners). The other owners (40%) did not notice an increase in crop production
. • Increased fish production through use of bio-slurry was reported by only 9% of the owners. Most of them (62%) claimed an increase of 10%, while others (26% and 12%) claimed an increase of 20 and 30% respectively.
. • Average saving in expenditures for cooking between Taka 661 (1st phase owners) and Taka 774 (2nd phase owners) per household per month as a result of the use of biogas for cooking and other household activities. Agency holders united in the BBBB estimated the monthly savings much lower, about Taka 400 per month.
. • Biogas plants save time (mentioned by 66% of all female users) now spent especially on education of children (mentioned by 46% of all female users), household works (mentioned by 29% of all female users) and gardening (mentioned by 27% of all female users)
. • Biogas plants save time of cooking (mentioned by 97% of all female users)
. • No smoke during use of biogas stoves (mentioned by 17% of all female users)
. • Cooking utensils do not become dirty (mentioned by 40% of all female users)
. • Use of biogas for cooking is safe (mentioned by 13% of all female users)
. • Biogas helps to keep the environment hazard free and hygienic
. • Use of biogas helps to keep kitchen and clothes clean
. • Use of biogas does not irritate eyes
. • Biogas plants have encouraged people to rear more cattle heads
. • Bio-slurry is used in sericulture
• Biogas plants save forests and trees
Negative effects of biogas plants:
. • Problems with operation were reported by 10% of the owners, being shortage of raw materials to feed the plant, low gas production, gas leakage through the hydraulic chamber and filling of plant with small parts of snails and oysters requiring frequent cleaning
. • Problems with operation were reported by 11% of the female users, being problems with the burner, blockage of the pipe, construction fault, insufficient feedstock, lack of manpower to feed the plant, gas leakage in the dome and filling of plant with small parts of snails and oysters requiring frequent cleaning
. • Poultry as feedstock often blocks the plants
. • Occasionally, the plant spreads bad smell
. • It is difficult to charge the plant everyday
. • Sometimes, the expected amount of gas is not produced
. • Sometimes, the outlet help growth of flies and mosquitoes
Information collected during the field visits indicated that biogas stoves were used for 5 to 8 hours per day for cooking. Other sources of energy than biogas were required for cooking on special occasions only. Cooking with biogas was appreciated by all users being quick and clean, while the stoves did not soot the cooking pots and pans.
As all benefits of biogas plants have not yet been sufficiently investigated in a quantitative manner, also with respect of the application of bio-slurry, it may be considered:
ƒ To conduct an independent and detailed biogas users’ survey to collect quantitative information on the positive and negative effects of biogas plants installed in Bangladesh under the 1st and 2nd phase of the Biogas Plant Pilot Project.
4.4 Financial aspects
This paragraph provides an estimate of the investment costs of an average biogas plant as well as a consideration of the investment subsidy provided under the last phase of the Biogas Pilot Plant Project.
4.4.1 Investment costs
Quotations for a biogas plant with a gas production of 100 cft and a total plant volume of about 6 m3 have been collected from LGED, BCSIR and GS. These quotations exclude the costs of a cast concrete slab for the outlet and the fee for construction and after sale service. The total investment costs amount to Taka 15,500, see Annex 6. This figure was confirmed by the evaluation conducted by the DPC Group finding an average of Taka 15,768 for a sample of 220 biogas plants constructed during the 2nd phase of the Biogas Pilot Plant Project.
4.4.2 Investment subsidy
During phase II of the Biogas Pilot Plant project implemented by BCSIR, the biogas farmer was provided with a direct investment subsidy of Taka 7,500. In addition, agency holders constructing and maintaining biogas plants received a fee of Taka 5,000 per unit. Hence, the total investment subsidy amounted to Taka 12,500 for every biogas plant.
It may be considered: ƒ To include for reasons of transparency the fee for construction and after sale service in the quotation for the biogas plant. ƒ To limit for reasons of ownership by the biogas farmers the amount of investment subsidy to approximately 35% of the investment costs.
4.5 Overall conclusion
The history of domestic biogas in Bangladesh is rather rich. So far, BCSIR has been the main actor in the dissemination of biogas plants. In total, close to 24,000 family-sized biogas plants of different designs have been installed throughout the country. The fixed dome model has become the most popular design. A number of design aspects are eligible for revision to upgrade quality. Also more emphasis will be required to enforce quality of construction and after sales service. Due to ending dates of projects, installation of biogas plants has come to a standstill almost completely since June 2004.
The approach followed so far can be characterised as a single actor project approach. It appears to be the proper time now to initiate a multiple actor programme approach with the longer-term vision to develop a commercial, sustainable biogas sector.
CHAPTER 5: Potential demand for domestic biogas
A number of technical, social and financial factors were investigated to arrive at an estimate of the potential demand for domestic biogas in Bangladesh.
5.1 Technical factors
Climatic conditions for the production of biogas in Bangladesh are favourable, as rather high temperatures remain throughout the year. It is rather difficult to get up-to-date data about the number of farmers keeping sufficient heads of cattle for biogas production as the latest census in Bangladesh was conducted in 1996. By then, 8.17 million holdings (45.8% of all holdings) reported to keep 21.57 million of cattle (an average of 2.64 cattle per holding), while 0.27 million households (1.5% of all holdings) reported to keep 0.72 million of buffaloes (an average of 2.67 buffaloes per holding). The numbers of cattle in the agricultural census of 1983-84
(21.49 million) and 1977 (20.50 million) were slightly lower. It becomes not clear from the 1996 census data to which extent holdings with cattle also kept buffaloes. There was a positive correlation between the average number of cattle and buffaloes per holding and the size (acreage) of the holdings. An interesting classification of holdings with cattle is provided in Table 5-1 (Bangladesh Bureau of Statistics, June 2004, page 232).
|
Table 5-1 Classification of holdings with cattle in Bangladesh as per the 1996 census |
Number of holdings |
Number of cattle |
Average number of cattle per holding |
|
Holdings with 1-2 heads |
5,106,994 |
7,838,641 |
1.53 |
|
Holdings with 3-4 heads |
2,111,498 |
7,198,421 |
3.40 |
|
Holdings with 5 heads and above |
952,872 |
6,535,129 |
6.85 |
|
Total |
8,171,364 |
21,572,191 |
2.64 |
About 950,000 holdings in 1996 kept five or more heads of cattle and could be regarded as potential biogas farmers. If all dung produced by minimum five heads of cattle could be collected, this amount would be sufficient to feed a biogas plant with a gas output of say 100 cft per day. The 2.1 million holdings keeping three or four cattle heads could be regarded as a bigger market segment, but as the amount of dung is limited to 30 to 40 kg per day, they would need to be supplied with smaller-sized biogas plants, e.g. with a gas output of 50 cft per day.

It is not very clear what happened with the number of farmers keeping sufficient heads of cattle since 1996. Most of the informants interviewed during the feasibility study suggested that the cattle population is rather stagnant; with other words, the number of cattle nowadays will be more or less the same as in 1996. The number of holdings (assumingly also with cattle) however has increased over this period with about 20%, which means that the average number of cattle heads per holding has decreased with the same factor. Rough estimates by experts from Bangladesh Bureau of Statistics (BBS) and Bangladesh Agricultural Research Council (BARC) on the present number of households with three or more cattle heads range from 575,000 to 1,925,000. Gofran4 made a small survey in Kazipur union of Patuakhali district in December 2003 and found 700 households keeping four or more cows. If this union would be representative for the whole country and assuming a total of 4,500 unions in the country, the total number of households keeping four or more cattle heads would amount to 3,150,000. The informants provided also the following qualitative information: ƒ Reduction in the keeping of cattle as draught animal has been caused by the massive
introduction of power tillers and tractors.
-
Reduction of the acreage for grazing caused by an increase in the number of households and an increase in the acreage used for cultivation of paddy. As a result, farmers face difficulties in the collection of fodder for the cattle.
-
Increase in the number of dairy cattle, especially in the urbanised areas with an increasing demand for milk. Investment capacity in the rural areas is increasing due to the availability of credit facilities and income earned my migrant workers abroad.
-
There is an inflow of cattle from India, estimated to be 700,000 to 800,000 heads per year, especially for slaughtering on the occasion of the festival called Qurbani5.
A limiting factor for the technical potential of domestic biogas could be flooding as Bangladesh forms the largest delta in the world. The vast plain is washed by big rivers like the Meghna, the Padma, the Jamuna and the Karnafuli. Tropical monsoon rains drench the land and the rivers. Onrush of rain waters in summer (July and August) overflows their banks flooding low and outlying areas every year and could damage the structure of the plant or disturbing its operation through in-flow of water in the outlet. However, as households have already avoided building their homesteads in low and very low land, it is believed that flooding will not significantly reduce the technical potential. Proper site selection requires careful attention when constructing the plant. Due to high water tables, the season for construction might be limited to six or seven months only. On the positive site, flooding might also promote the installation of biogas plants as they provide fuel for cooking in a convenient manner, while collection or purchase of alternative (biomass) fuels in the flooding period is quite problematic.
Water required for mixing cow and/or buffalo dung prior to feeding into the biogas plant is in general not a problem in Bangladesh. Tube-wells form the main source of water in the rural areas.
5.2 Social factors
Biogas produced from cattle and buffalo dung is widely accepted as cooking fuel in Bangladesh. However, resistance exists to attach a toilet to the biogas plant as this will create hesitation among people to handle the bio-slurry. This phenomenon would need special attention in future extension and promotion campaigns. It may be considered to make the installation of a second inlet pipe to the digester compulsory, even if the biogas farmer does not (yet) consider attaching a latrine.
4 Abdul Gofran, personal communication, 29 March 2005 5 This festival remembers Abraham’s sacrifice of his son Ishmael, celebrated with the slaughter of a cow, sheep or goat. During the week preceding the festival, open-air fairs do a brisk trade in cattle and goats.
As mentioned in paragraph 3.1, women have a say in the decision-making process at household level. This is important as the women are the main direct beneficiaries of the biogas plants.
5.3 Ability to pay
The latest household expenditure survey conducted in 2000 comprising a sample of 5,440 rural households provides figures on their average income and expenditure (Bangladesh Bureau of Statistics, March 2003). These figures might be suitable proxies for potential biogas farmers. The average income of a rural household in 2000 amounted to Taka 4,816 per month. Professional wages and salaries contributed for 27.7% to this income, followed by agriculture (25.5%) and business & commerce (22.4%). The average expenditure per rural household amounted to Taka 4,257 per month, out of which Taka 3,879 (91.1%) spent on consumption (of goods and services) and Taka 378 (8.9%) on non-consumption (taxes, pension and social security contributions and related insurance premium, gifts and other transfers). The average rural expenditure by household on food was equal to Taka 2,300 per month.
5.4 Financial analysis
The financial analysis is based on the data for a biogas plant with a daily gas production of 100cft. The investment cost is assumed to be Taka 25,000 to include the fee for construction and after sale service as well as measures to increase the quality of the biogas plant (caste concrete slab for the outlet, GI gas pipes, turret on top of the dome to protect the dome gas pipe and better quality of biogas appliances), see Annex 6.
The basic data for the financial analyses is presented in Annex 7. The benefits associated with the use of the biogas plant derive primarily from the savings in expenditures for biomass fuels. The base price for these fuels is assumed to be 1.0 Taka per kg. The value of the saved labour and the recovered nutrients in the biogas slurry are assumed to be zero. The base analysis indicates a financial internal rate of return (FIRR) of 15 percent. Figure 5-2 presents the results of a sensitivity analysis on the assumed price of biomass. The data indicates that the resulting FIRR is extremely sensitive to this price.
FIRR vs. Biomass Price FIRR
70%
60%
50%
40%
30%
20%
10%
0%

0 0,2 0,40,6 0,81,0 1,21,4 1,61,8
Biomass Price (Taka)
Figure 5-2 The Financial Internal Rate of Return (FIRR) is very sensitive to the price of biomass
The FIRR becomes negative when the price of biomass is below 0.4 Taka/kg and 64% when the price of biomass is 1.8 Taka/kg. The actual price of biomass in Bangladesh varies considerably from one area to another. The perception of many rural farmers is that the price of biomass is near zero since it can be collected by household labour which is not valued highly by the farmer.
A sensitivity analysis on the amount of the subsidy provided is presented in Figure 5-3. The data indicates that the FIRR is not as sensitive to the percentage change in the level of the subsidy as it is to the price of biomass. The FIRR becomes less than 10 percent when the subsidy is Taka 3,000 or lower per biogas unit and is 88 percent when the subsidy is Taka 17,000 per unit.
Figure 4: FIRR vs. Amount of Subsidy

0
1000300050007000
900011000130001500017000
Amount of Subsidy (Taka)
Figure 5-3 The Financial Internal Rate of Return (FIRR) is less sensitive to the amount of investment subsidy
The financial analysis indicates that an amount of Taka 7,000 as investment subsidy is generally sufficient to attract potential farmers while not being significantly excessive as to result in relatively high FIRRs for the farmer. The actual FIRR realized by the farmer is largely dependent on the actual financial price for biomass. It may be considered: ƒ To recalculate the FIRR and the required amount of subsidy after obtaining the results of the
detailed biogas users’ survey, see paragraph 4.3.
5.5 Economic Analysis
An economic analysis of a biogas plant with a daily gas production of 100 cft was undertaken to assess the benefits to society of the use of biogas plants. Due to the scope of this study, the economic analysis had to rely on data presented in a publication of a large-scale biogas programme in Nepal (Mendis and Van Nes, July 1999). These data provide a reasonable basis for the economic analysis.
The principal assumptions relate to the conversion from financial prices to economic prices. A summary of the conversion factors and resulting economic prices for the costs and benefits associated with the analysis is presented in Annex 8. Economic benefits resulting from improved sanitation through toilet attachment and employment generation were left out of consideration. The analysis is based on calculating the economic internal rate of return (EIRR) for the net annual benefits associated with the biogas plant. All investment costs for the plant were assumed to be expended in the first year and all maintenance costs and all resulting benefits were assumed to be constant over the 15 year life of the plant. A summary of the resulting EIRR for the biogas plant is presented in Figure 5-4. The EIRR for just the economic benefits derived from the savings of biomass that result from the use of a biogas plant is estimated at 17 percent. This EIRR, as in the financial case, is very sensitive to the assumption of the economic price for biomass. The economic price of biomass is assumed to be Taka 1.0 per kg. If the economic price of biomass is Taka 0.5 per kg, the resulting EIRR is 1 percent and if the price is Taka 1.5 per kg, the resulting EIRR is 32 percent.
Working with the base economic price for biomass of Taka 1.0 per kg and adding a saving of 1.0 hours a day of domestic labour valued at Taka 1.5 per day results in increasing the EIRR to 20 percent. Assuming an annual value of Taka 1,971 for the nutrients in the dung that are saved and returned to the land as a result of the biogas plant, the EIRR increases to 39 percent. When the economic value of smoke reduction is added at Taka 400 per year (Reid, 1986), the resulting EIRR increases to 43 percent. Finally, if the reduced carbon emissions associated with the use of a biogas plant are valued at US$ 5 per tonne CO2-eq., the resulting EIRR increases to 62 percent.

Based on the assumptions used for this economic analysis, it is clear that there is an economic justification for the subsidy of Taka 7,000 per plant proposed in this study. Furthermore, it is unlikely that the Bangladeshi farmers would have sufficient financial incentives to adopt the biogas plants. The earlier financial analysis clearly indicated how sensitive the FIRR is to the price of biomass. As most farmers do not directly purchase biomass, their perception is that the price of biomass is at or near zero. As a result, their perceived FIRR is negative. Alternately, if the economic value of biomass is Taka 1.0 per kg, then the resulting EIRR for the biogas plant is 17 percent. When the other principal non-market benefits of the biogas plant are added, the EIRR rises to 62 percent. This provides an additional justification for the subsidy for the biogas plants. It may be considered: ƒ To recalculate the EIRR and the required amount of subsidy after obtaining the results of
the detailed biogas users’ survey, see paragraph 4.3.
5.6 Overall conclusion
Based on the number of households keeping sufficient number of cattle, there is a rather substantial technical potential of minimum one million biogas plants in Bangladesh. To further increase this potential, it is important to promote smaller-sized biogas plants. Flooding will not be a strong limiting factor, but site selection needs to be done very carefully. High water table will limit the construction season to six to seven months per year. Apart from hesitation to attach a toilet to the digester, there are no limiting social factors for domestic biogas. The ability of most farmers to invest in a biogas plant with a total cost of say Taka 17,000 will be limited due to their low income. This underlines the need for an effective credit facility in a future national programme on domestic biogas. The financial analysis indicates that an amount of Taka 7,000 as investment subsidy is generally sufficient to attract potential farmers while not being significantly excessive as to result in relatively high financial rate of return (FIRR) of 15 percent for the farmer. The actual FIRR realized by the farmer, however, is largely dependent on the actual financial price for biomass. The economic internal rate of return (EIRR) for the biogas plant is 17 percent in the base case.
CHAPTER
6: Overview of (potential) stakeholders
This Chapter provides a brief overview of the main (potential) stakeholders for a national programme on domestic biogas in Bangladesh, divided into government, civil sector and private sector organisations. Bangladesh is endowed with an impressive number and variety of institutes, organisations and companies. Besides these described below, many more could be called upon to participate in the implementation of a national programme on domestic biogas. This organisational richness can be regarded as a very positive starting point for such a programme and makes the establishment of a separate programme office unnecessary.
6.1 Government organisations
6.1.1
Bangladesh Council of Scientific and Industrial Research
The Bangladesh Council of Scientific and Industrial Research (BCSIR, www.bcsir.org) was established in 1973 with its head office at the Dhaka Laboratories campus. In 1983, the Institute for Fuel Research and Development (IFRD) was established under BCSIR. The Council is part of the Ministry of Science, Information and Communication Technology (MoSICT).
BCSIR is conducting R&D in 38 main areas among which biogas technology since 1976. Through the Biogas Pilot Plant Projects (1st and 2nd phase) implemented since 1995, BCSIR also played a very central role in the dissemination of biogas plants, see Chapter 4.
6.1.2
Local Government Engineering Department
The Local Government Engineering Department of the Ministry of Local Government, Rural Development & Cooperative is playing a pivotal role in rural infrastructure development in Bangladesh. The main functions of LGED are to provide technical support to the rural and the urban local government institutions and to plan and implement infrastructure development projects in rural and urban areas. Almost all the bilateral and multi-lateral development partners operating in Bangladesh are involved with the development projects of Local Government Engineering Department (LGED).
Training has been widely recognized as an essential means to acquire knowledge, skill and motivation. As such, LGED has given due importance to training. All the training programmes of LGED are coordinated and implemented through the LGED HQ Training Unit and 10 Regional Training Centres at District level. About 30 types of courses are offered to different categories of LGED officials/staff. The courses include technical, managerial, financial, environmental and socio-economic issues. In addition, training courses are also offered to the contractors, representatives of the local government institutions, project beneficiaries, community groups etc.
The Chief Engineer acts as the chief executive of LGED. He is assisted at the headquarters by two Additional Chief Engineers, six Superintending Engineers (SE), six Executive Engineers (XEN) including one Executive Engineer (Mechanical), one Assistant Chief Engineer and four Assistant Engineers (AE) including one Assistant Engineer (Mechanical). Including these engineers a total number of 89 employees are working at the LGED headquarters. The total number of employees at the district level is 762 including the Executive Engineer and one Assistant Engineer in each district and one Assistant Engineer (Mechanical) in each greater district. 8,785 persons including 469 Upazila Engineers are working at the sub-district level. At present, LGED's total number of employees is around 9,347 under the revenue budget. Besides, there are six more Superintending Engineers at regions and ten District Training Engineers at ten regional training centres under the revenue budget.
LGED was involved in the dissemination of more than 1,100 domestic biogas plants in the period from October 1998 to June 2003, see Chapter 4.
6.1.3
Ministry of Power, Energy and Mineral Resources
The Ministry of Power, Energy and Mineral Resources (MoPEMR) has overall responsibility for the country's energy sector, with policy formulation and investment decisions under its control. This Ministry has two distinct divisions, the Power Division and the Minerals Division.
The Bangladesh Power Development Board (BPDB) is an agency under the Power Division of MoPEMR responsible for generation and transmission of electricity in the country. This agency distributes also to urban consumers through other GoB agencies like the Dhaka Electric Supply Company (DESCO). Distribution of electricity to rural consumers is planned, implemented, operated and managed by the Rural Electrification Board (REB).
The Minerals Division of MoPEMR deals not only with the exploration, production, transport and distribution of natural gas, petroleum, coal and other minerals available in the country, but also with the import, refining and distribution of crude oil and petroleum products including LPG. The corresponding implementing agencies are Petrobangla (with several companies working under this corporation) and Bangladesh Petroleum Corporation (BPC). There are three state-owned oil marketing companies under BPC: Jamuna Oil Company Limited former CALTEX), Meghna Petroleum Company Limited (former ESSO Eastern Inc.) and Padma Petroleum Company Limited (former Burmah Eastern Limited)6.
Within MoPEMR, the "Power Cell" acts as a single point of contact to facilitate the electricity reform and restructuring process including formulation, implementation and monitoring of GoB policy as well as promotion and monitoring of private power generation by Independent Power Producers (IPPs). Power Cell is also charged with the responsibility to further develop renewable energy sources in the country. It is planned by GoB to establish a rather autonomous apex body called Renewable Energy Development Agency (REDA), but until its formation the Power Cell will look after all issues related to renewable energy.
The Bangladesh Rural Electrification Program under the MoPEMR was founded with a Presidential Ordinance in October 1977 that established the Rural Electrification Board (REB) as the semi-autonomous government agency reporting to the Ministry. Since its inception, the purpose of the program has been to use electricity as a means of creating opportunities for improving agricultural production and enhancing socio-economic development in rural areas. Today there are close to 70 operating rural electric cooperatives called Palli Bidyuit Samity (PBS).
So far, the MoPEMR has not been involved in the dissemination of biogas plants in Bangladesh.
6 These companies were nationalised following the independence of Bangladesh.
6.1.4
Infrastructure Development Company Limited
The mission of Infrastructure Development Company Limited (IDCOL, www.idcol.org) is to promote economic development in Bangladesh by encouraging private sector investment in infrastructure projects. IDCOL was created by the Government of Bangladesh (GOB) with assistance from International Development Agency (IDA). IDCOL was registered as a public limited company under the Company’s Act 1994 and licensed by the Bangladesh Bank as a nonbank financial institution in January 1998. IDCOL’s share capital is fully subscribed by the GOB.
Its specific development objectives are the following:
-
Participate in the financing of privately-owned infrastructure projects by providing structured finance in the form of senior and subordinated loans;
-
Mobilise third-party limited resource lending to privately-sponsored infrastructure projects, either at financial closing, or post-commissioning stages, of project development;
-
Provide investment advisory services to developmental projects that are led by private Bangladeshi developers;
-
Provide refinancing for small infrastructure projects implemented by non-governmental organizations (NGOs)/microfinance institutions (MFIs) and other private entities;
-
Arrange technical assistance for private sponsors and executing agencies promoting small infrastructure and renewable energy projects.
IDCOL is managed by an independent Board of Directors. The Board of Directors of IDCOL comprises senior government officials and prominent entrepreneurs from the private sector nominated by the shareholders of the Company, and an appointed full time Chief Executive Officer.
IDCOL had initial access to resources of US$ 225 million, which was provided by the GOB and the World Bank and of which an amount of USS$ 154 million has been reallocated for the rehabilitation of infrastructure damaged by 2004 floods. In addition, IDCOL has access to another US$20 million (divided into IDA credit and Global Environment Facility (GEF) grants) to channel grant and provide refinancing for promotion of renewable energy under the Rural Electrification and Renewable Energy Development Project (REREDP). Under this Project, IDCOL promotes photo-voltaic solar home systems (SHSs). These SHSs are to be purchased by households and business entities in the rural areas of Bangladesh. All the stakeholders have to contribute their shares in the purchase of SHSs, such as, households are required to put an upfront payment and NGOs/MFIs have to finance the remainder of the cost of SHSs in the form of micro-credit. IDCOL channels GEF grants to buy down the SHSs cost as well as supports the operational costs of NGOs/MFIs promoting SHSs, provides the latter a refinancing facility in local currency, and puts in place other related arrangement, designed to promote conditional sales of SHSs. IDCOL intends to finance an estimated 50,000 SHSs over the period January 2003 to June 2008. As of 30 April 2005, ten NGOs/MFIs have already installed about 40,000 SHSs in rural areas over Bangladesh.
So far, IDCOL has not been involved in the dissemination of biogas plants in Bangladesh.
6.1.5
Bangladesh Agricultural Research Institute
Bangladesh Agricultural Research Institute (BARI) is an autonomous organisation under the Ministry of Agriculture and responsible for conducting research on all crops except rice, jute, sugarcane, and tea for which there are separate institutes. It was established in 1908 as Agricultural Research Laboratory, Bengal at Dhaka. In 1968, the Department of Agriculture was bifurcated into two separate directorates, namely, the Directorate of Agriculture (Extension and Management), and the Directorate of Agriculture (Research and Education). The latter was converted to Bangladesh Agricultural Research Institute (BARI) in 1976. During the early sixties, BARI was shifted to Joydebpur to allow rebuilding of its research facilities. The shifting was completed in 1980. In addition to the central station of Joydebpur with an area of 165 ha, BARI has six regional stations and 24 sub stations. The institute has six crop-based research centres (Tuber Crops Research Centre, Wheat Research Centre, Horticultural Research Centre, Pulse Research Centre, Oil Crops Research Centre, Spice Research Centre) to ensure a multidisciplinary approach. The number of mandated crop in these centres exceeds 100; variety improvement and production have received priority. It has made good contribution towards the development of wheat, potato, mustard and vegetables. The institute has released 172 improved varieties of different crops. The overall management of the institute is vested on a 12-member Board of Management. The chief executive of the institute is the Director General, assisted by three Directors who are specifically responsible for three main areas of activities, namely, research, support services, and training and communication.
BARI could play a role in a national biogas programme through conducting applied R&D on the proper use of bio-slurry.
6.1.6 Department of Agricultural Extension
The Department of Agriculture Extension (DAE, www.bangladeshgov.org/moa/dae) is part of the Ministry of Agriculture (MoA) and responsible for carrying out extension services at the grassroots level throughout the country. The main functions of DAE are:
-
To motivate and help farmers in adopting improved production practices to increase their
-
productivity, meet national consumption requirements, maximise export and minimise import.
-
To provide farmers with the latest results of research and farm techniques for their socioeconomic betterment.
-
To help develop self-reliance and cooperation by training local leadership for organised group action.
-
To provide channels for service and information from the MOA and its different departments to the farm people and in turn relay the problems and needs of the farmers that require national level intervention.
-
To provide an effective linkage between the various research institutes and the farmers so that along with the flow of technology to the farmers, the farmer's level problems are also brought to the relevant research institutes for investigation and solution.
-
To serve as liaison agency between farmers and other organizations, both public and private concern with overall socio-economic development of rural people, including the credit and input supply agencies.
At present the Department provides its services through eight wings. The Field Services Wing is responsible for providing extension services to farmers throughout the country and maintains offices at regional, district, upazila and block level. The total number of employees of DAE amounts to about 24,000.
DAE could play a role in a national biogas programme through extension on the proper use of bio-slurry to farmers operating a biogas plant.
6.2 Civil sector organisations
Besides these described in this paragraph, many other civil sector organisations in Bangladesh could play a role in a national biogas programme like COAST, CMES, SRIZONY and TMSS.
6.2.1 BRAC
BRAC (www.brac.net), formerly known as Bangladesh Rural Advancement Committee, was established as a relief and rehabilitation organisation in 1972 after the Bangladesh Liberation War by Mr. Fazle Hasan Abed. Over the years BRAC has gradually evolved into a large and multifaceted development organisation with the twin objectives of alleviation of poverty and empowerment of the poor with over 26,000 regular staff and 34,000 part time teachers, working in 60,627 villages in all the 64 districts of Bangladesh. Related companies and institutes are among others BRAC Bank, BRAC University and BRAC Industries Ltd. The projected annual expenditures for 2003 amounted to USD 174 million out of which 18% to be financed by donors.
BRAC was involved in the dissemination of about 1,200 domestic biogas plants as part of the 1st phase of the Biogas Pilot Plant Project, see Chapter 4.

6.2.2 Grameen Shakti
Grameen Shakti (GS, www.grameen-info.org/grameen/gshakti/), an
organization of the
Grameen family of companies, has been working as a company in the
renewable energy sector
in Bangladesh since 1996 aiming at:
-
Popularising and delivering renewable energy to the rural households.
-
Marketing solar, biogas and wind energy on commercial basis, focusing on rural areas.
-
Providing services that alleviate poverty and protect environment through applied research
-
and development of renewable energy based technologies.
-
Undertaking a project to progressively manufacture and market efficient and affordable household based photovoltaic systems.
-
Implementing projects to generate electricity from wind in the coastal belts and offshore islands; operate mini and micro hydro-plants in the hilly areas.
-
Developing and implementing special credit, savings and investment programs for generation, storage, and utilization of renewable energy for the benefit of rural people.
-
Testing the new and appropriate technologies to provide more cost effective energy services at affordable price to the non-electrified areas.
-
Providing capital, technology and management services to energy enterprises. GS has established a large network in Bangladesh with over 100 offices and 400 field staff, mostly engineers, covering 54 out of 64 districts.
Recently, GS has launched an ambitious initiative aiming to construct 200,000 biogas plants within a period of five years. At the time of the mission, a total of about 10 plants were
under construction or completed. For biogas farmers, GS has
introduced a soft financing system
for the customers consisting of three different options:
-
Option 1: The customer has to pay 25% of the total price as down payment. The remaining 75% of the cost are to be repaid within 24 months with 10% service charge.
-
Option 2: The customer has to pay 20% of the total price as down payment. The remaining 80% of the cost are to be repaid within 36 months with 14% service charge.
-
Option 3: Biogas farmer has to pay Taka 1,000 for supervision and technical assistance by
GS, but constructs for the remaining the plant on his/her own cost. It still remains to be seen in future whether these options will fully recover the costs incurred by GS. The very ambitious initiative of GS is encouraging, but is typically a single actor project approach. The challenge is to incorporate the ambitions of GS in a national programme, in which this company could play a significant role, especially with respect to the functions of construction, after sales service and provision of credit, see Chapter 7.
6.2.3 Bangladesh Centre for Advanced Studies
Bangladesh Centre for Advanced Studies (BCAS, www.bcas.net) is an independent, non-profit, non-government, policy, research, and implementation institute working on sustainable development at local, national, regional and global levels. BCAS addresses sustainable development through four interactive themes: (a) environment-development integration, (b) good governance and people’s participation, (c) poverty alleviation and sustainable livelihoods, and (d) economic growth and public-private partnership. It was established in 1986, and over the years has grown to become a leading institute in the non-government sector in Bangladesh and South-Asia. It works on the above issues using interactive approaches and multiple methodologies. BCAS has been registered with Social Welfare Department as well as NGO Affairs Bureau of Government of Bangladesh.
BCAS has a core management unit guided by a board of directors, two dozens of senior professionals and scientists and more than three dozens of mid-level professionals and researchers.
BCAS being an independent institute could play a role in a national biogas programme through conducting external monitoring and evaluation.
6.2.4 PKSF
Palli Karma Sahayak Foundation (PKSF, www.pksf-bd.org ) has been working since its inception in 1990 as an apex micro-credit funding and capacity building organisation for eradicating poverty by providing micro-credit to the poor through its Partner Organisations (POs). PKSF, in English, means “Rural Employment Support Foundation”. However, PKSF has expanded its operation to urban areas also. PKSF’s vision is to alleviate poverty and improve the quality of life of the poor – the landless and the assetless people by providing them with resources for creation of employment for enhancing economic conditions. The major objectives of PKSF are:
-
To provide various types of financial help and assistance to POs, so that they can undertake activities that generate income and employment opportunities among the economically most disadvantaged groups in the society.
-
To assist in strengthening the institutional capacity of POs, so that they can manage their programme in a sustainable manner.
PKSF reaches its target groups – the landless and the assetless people – through its POs, it does not directly lend money to its target people. PKSF provides loanable funds to its 199 POs, 3 big, 189 small and medium, and 7 pre-PKSF POs. PKSF gives special emphasis on micro-enterprise development with the goal of making micro-credit more growth-oriented.
Legally PKSF is a “company limited by guarantee” meaning “company not for profit” and is registered under the Companies Act of 1913/1994 with the Registrar of Joint Stock Companies. The legal structure of PKSF allows flexibility, authority and power to take programmes and implement them throughout the country and managing its affairs as an independent organisation. The PKSF mandate authorises PKSF management to mobilise funds in the forms of grants, loans and contributions from a wide variety of sources which include the Government of Bangladesh (GOB), private individuals and organisations, foreign governments, international donors and lending agencies and capital markets. So far PKSF has received funds from the GOB, the IDA/World Bank, the USAID, the Asian Development Bank (ADB) and the International Fund for Agricultural Development (IFAD).
So far, PKSF has not been involved in the dissemination of biogas plants in Bangladesh.
6.3 Private sector organisations
6.3.1 Agency holders
The 2nd phase of the Biogas Plant Pilot Project aimed to establish approximately 50 agencies for the marketing, construction and after sales service of biogas plants. These agencies worked under the direct control and supervision of the Project Director from BCSIR. The evaluation reported by the DPC Group in June 2004 as well as the field visits have made clear that some of these agency holders have done a very good job. The owners of the agencies engaged officers and workers to conduct the activities. The agency holder employed at Dhaka and Narayanganj district engaged 18 motivators and managed to construct 277 plants in FY 2001/02, 386 plants in FY 2002/03 and more than 500 plants in FY 2003/04. In Comilla district, the holder with the help of 10 motivators, 25 masons and one motor-cycle constructed more than 500 plants within two years. In Gazipur district, the agency holder constructed 59 plants in FY 2001/02, 221 plants in FY 2002/03 and 165 plants in FY 2003/04 and engaged five motivators and 20 masons. In total, all agency holders constructed 9,776 biogas plants in the 2nd phase of the Project, being 2,349 units (31%) more than the number constructed by the civil engineers directly employed by BCSIR.
Agency holders originating from the Pilot Project have united themselves in the Bangladesh Bureau of Biogas and Bio-Technology (BBBB). After the closure of the project, construction activities have come almost to a standstill and in this respect they are eager to continue their businesses through participation in a national biogas programme.
CHAPTER 7: Required functions and suitable actors
National programmes require multiple actors to conduct distinguished functions in a coordinated manner, see Figure 7-1, rather than single actors conducting all functions on their own.

During the interviews, selected stakeholders were invited to propose suitable actors to conduct these functions, see Annex 5. In this chapter, a provisional match between required functions and suitable actors is presented. Some of the functions are supposed to be conducted by one actor only; others by multiple actors only, with a third category of functions that could be executed by both single or multiple actors, see Table 7-1.
|
Table 7-1 Suitable actors proposed by respondents to execute functions in a national biogas programme Function |
Suitable actor(s) |
|
Operation & |
Eligible farmers having sufficient cattle dung at their disposal will operate and |
|
maintenance |
maintain the biogas plants. |
|
(multiple actor) |
|
|
Promotion (single/multiple actor) |
Various actors from the government and civil society sector at central and local level will be able to promote the use of biogas including the dissemination of reliable information on the costs and benefits of biogas plants towards eligible farmers. One respondent suggested a newly to be established Biogas Programme Office (BPO) to conduct this function, but it is preferred to make use of already existing capable institutions. |
|
Construction & after sales service (multiple actor) |
Based on a level playing field enabling fair competition, different kind of actors could very well construct and service biogas plants like private companies including agency holders and NGOs like BRAC and GS. Though LGED and BCSIR were mentioned as possible actors as well, it is not recommended to involve government organisations in conducting this function. |
|
Provision of credit (multiple actor) |
NGOs like BRAC and GS as well as scheduled banks could very well provide loans to eligible farmers to finance the installation of biogas plants. It is not likely that these actors will be able to refinance these loans by their own sources and therefore a refinancing facility might be required. PKSF was also mentioned as a possible provider of credit to farmers, but being an apex organisation this would not qualify. |
|
Administration of (subsidy) fund (single actor) |
IDCOL was most often suggested to be the most appropriate institute to handle the administration of investment subsidy, with respondents often referring to their current role in the SHS programme. Also the BPO was mentioned in this respect, but again it is preferred to make use of already existing capable organisations |
|
Quality control (single actor) |
Quality control is closely related to the administration of investment subsidy which was perhaps the reasons that also for this function IDCOL was most often suggested. Independent consultants were mentioned as well, but even these need to be assigned by the responsible actor. |
|
Training (multiple actor) |
Various actors could be involved in conducting training activities, depending on the kind of training. Some of the required trainings are (female) user training, mason training, supervisor training, business development training and loan officer training. Possible actors most often mentioned by respondents were BCSIR and LGED. |
|
Extension on use of bio-slurry (single/multiple actor) |
Proper use of bio-slurry needs to be promoted through extension programmes to be executed at local level. Extension agents from the DAE or NGOs could be well placed to provide these services. |
|
Applied R&D (single/multiple actor) |
Also with applied R&D, various actors could be involved in executing activities, depending on the nature of the R&D. BCSIR was most often mentioned, but also BUET and BARI were proposed for agricultural research. |
|
Monitoring & evaluation (single/multiple actor) |
Multiple actors could qualify for execution of monitoring & evaluation activities on the condition that they are independent. Private consultants and BCAS were most often mentioned as potential actors. |
|
Coordination at implementation level (single actor) |
Only one single actor could be involved for the day-to-day coordination or management of the national programme. A newly to be established BPO was most often mentioned, but it is preferred to make use of already existing capable organisations. IDCOL respectively LGED were mentioned next and could both qualify despite being very different organisations. BCSIR and the MoPEMR were not preferred by the respondents due to unsuitable mandate (BCSIR is a R&D institute) respectively motivation (MoPEMR looks at commercial energy only). |
|
Coordination at government/policy level (single actor) |
For the coordination at government/policy level, the establishment of a separate steering committee with broad representation from all sectors was proposed most often. This committee could be facilitated by the coordinating body at implementation level. |
The suitable actors are presented in Figure 7-2. Eligible farmers will operate and maintain biogas plants constructed and serviced by private sector and NGOs, while NGOs and scheduled banks provide them – if required – with a micro-credit. Promotion, training, R&D, extension and M&E are functions that will be conducted by various institutes. IDCOL and LGED are identified as possible suitable organisations to coordinate the programme at implementation level, to administer public funds and likely also to arrange for quality control. A Steering linked to the national government will need to be established to coordinate the programme at policy level.

CHAPTER
8: Outline for a national biogas programme
This Chapter provides a rough outline for a national programme on domestic biogas. The majority of the conditions for large-scale dissemination of biogas plants in Bangladesh are fully or just met (see Annex 9), with a few other conditions doubtful, not (yet) met or falling short. The latter conditions need attention during the formulation of a detailed implementation plan. Also respondents mentioned a number of constraints for a national programme. These are first of all dealt with in paragraph 8.1.
8.1 Constraints for a national programme
Stakeholders mentioned in the interviews a big number of constraints for a national programme on domestic biogas, see Annex 5 and Table 8-1. This table also provides possible manners to address these constraints in a national programme. Most of the constraints can be effectively addressed through properly designing and implementing a national programme.
|
Table 8-1 Constraints for a national biogas programme as mentioned by stakeholders and possible manners to address these constraints Type of constraint |
Constraint (number of times |
Possible manners to address this constraint |
|
|
mentioned by respondents) |
|
|
Technical |
Lack of after sales service (4x) |
In the quotation of constructors a fee for specified |
|
|
|
after sales service could be included, and a strict |
|
|
|
observance of this service could be enforced |
|
|
Insufficient dung available and decreasing cattle number (4x) |
The technical potential number of biogas plants is still minimum one million. Potential customers could be provided with reliable information prior to taking an investment decision |
|
|
Lack of training and trained |
A national programme could cater for well trained |
|
|
manpower (1x) |
manpower |
|
|
Technical failures (1x) |
Enforced quality standards could reduce the |
|
|
|
number of technical failures |
|
Financial and |
Lack of funds for grants and |
A national programme could be fully financed |
|
economic |
credit (4x) |
|
|
|
High investment cost (2x) |
A national programme could have a facility to provide credit to biogas farmers |
|
|
Early adopters not taking care of plant operation (2x) |
Such customers could be less if (investment) subsidies are reduced to reasonable levels |
|
|
Lack of cost recovery by |
Constructors and credit providers could include all |
|
|
constructors and credit providers |
costs including a profit margin in their prices |
|
|
(2x) |
|
|
Social |
Hesitation among farmers to handle dung and to use biogas (1x) |
Farmers could be provided with reliable information, but should never be forced to install a biogas plant |
|
|
Preference of male heads of |
Both male and female members of potential |
|
|
households to invest in other |
customers could be provided with reliable |
|
|
things than a biogas plant (1x) |
information, but are of course free in their final |
|
|
|
investment decisions |
|
Promotional |
Lack of awareness (4x) and promotion (2x) |
A national biogas programme could create awareness and cater for effective promotional activities |
|
|
No critical mass achieved (1x) |
A national biogas programme could be a first step |
|
|
|
to achieve a critical mass |
|
Institutional |
Wrong type of organisation engaged in dissemination (3x) |
Most functions could be executed in competition by multiple actors on a level playing field, while few functions could be executed by one, carefully |
|
|
|
to be selected single actor only |
|
|
Lack of dedicated institute (2x) |
See above |
|
|
Lack of institutional arrangements (1x) |
A national programme could formulate and enforce effective institutional arrangements |
|
|
Time consuming procedures of GOB (1x) |
Unnecessary delays could be limited as much as possible by proper planning |
|
Political |
Lack of political commitment and will (3x) |
A national programme could be properly linked to national policies through a national biogas committee |
|
|
Technology felt outdated by the politicians (1x) |
Effects and impacts of biogas plants could to be reliably documented and presented to politicians |
|
|
Interference by politically backed businessmen (1x) |
Important decisions could to be taken by committees rather than individuals |
|
Programmatic |
Lack of monitoring and follow-up (1x) |
A national programme could cater for sufficient monitoring and follow-up, see Figure |
8.2 Objectives of the programme
The
overall objective of the proposed national programme is to further
develop and disseminate
domestic biogas in rural areas of Bangladesh. The specific
objectives contributing to its overall
objective are:
-
To develop a commercially viable, market oriented biogas industry.
-
To further strengthen institutions for sustainable development of the biogas sector.
-
To stimulate internalisation of all benefits of the biogas plant.
-
To increase the number of quality biogas plants by 36,4507.
-
To ensure the continued operation of all biogas plants installed under the programme.
-
To conduct applied Research and Development (R&D) in order to optimise plant operation
and use of bio-slurry.
8.3 Initial geographical coverage
In order to firmly found and test the modalities and institutional arrangements of the national programme, it was proposed to the stakeholders to limit the geographic coverage initially to say 16 districts (25% of all districts). Such approach was found very reasonable, but it was advised for political reasons to include districts from all six divisions. Criteria proposed by the stakeholders for the selection of the districts are high cattle population, small risk of flooding, high income of farmers, good availability of construction materials and easy communication. Other mentioned, sometimes contradictory criteria were the remoteness of the district and the absence of a connection to the electrical grid, see Annex 5.
8.4 Implementing partner
Despite being very different organisations, see Table 8-2, both IDCOL and LGED have come out from Chapter 7 as potential implementing partners for SNV.
|
Table 8-2 Comparison of some characteristics of LGED and IDCOL LGED |
IDCOL |
|
|
Registration and |
Department under the Ministry of Local |
Public limited company under the |
|
management |
Government , Rural Development & |
Company’s Act 1994, managed by an |
|
|
Cooperative |
independent Board of Directors |
This rather detailed number originates from the proposal for the Asia Biogas Programme and is used here as an indication for the production rate of a national biogas programme in Bangladesh. This rate might be revised during the formulation of the implementation plan.
|
Function |
To provide technical support to the rural and urban local government institutions and to plan and implement infrastructure development projects |
To promote economic development by encouraging private sector investment in infrastructure projects |
|
Organisational |
Offices at national, regional, district and |
One office in Dhaka with about 15 |
|
structure and size |
sub-district level with over 9,300 |
employees |
|
|
employees |
|
|
Leadership |
Chief Engineer, supported at the headquarters by two Additional Chief Engineers, six Superintending Engineers and other engineers |
Chief Executive Officer |
|
Relevant experience and success record |
Project for production and use of biogas and organic fertiliser for maintaining environmental balance with mixed results |
Renewable energy development project very successfully disseminating SHSs in a programmatic approach and with proper institutional arrangements |
|
Interest shown to |
Positive |
Positive |
|
participate in the |
|
|
|
national programme |
|
|
Based on the current data and information, IDCOL is slightly preferred above LGED based on their effective role in and experience with the SHS-project. Also the small size of IDCOL allowing more flexibility might be an advantage at one side, though its personalised leadership might be a risk at the other side. It may be considered:
ƒ To field a short mission to Bangladesh in July or August 2005 to select either IDCOL or LGED as a partner for the implementation of the programme. A Memorandum of Understanding (MoU) needs to be formulated between this partner and SNV for the preparation of the programme, in particular the formulation and approval of the detailed implementation document.
8.5 Production, budget and financing
It is proposed to have two different phases of the national biogas programme, a preparation and an implementation phase. The preparation of the programme could start after the approval of this feasibility report and would include the formulation and approval of a detailed implementation plan. This phase would also include the installation of a limited number of biogas plants (2,100) already in 2006. The implementation phase could run for a period of three years from 2007 up to and including 2009 and aim at the construction of another 34,350 plants. Hence, the total production of the programme would amount to 36,450 biogas plants.
The total indicative budget for the national biogas programme amounts to Euro 14.7 million, see Table 8-3.

The cost/benefit ratio of CDM financing needs to be determined during the formulation of the implementation plan. Based on experiences to mobilise carbon credits for large-scale biogas programmes in Nepal and Vietnam, it might be possible by that time to estimate the cost/benefit ratio for a smaller-scale programme in Bangladesh.
It may be considered: ƒ To finance the subsidy component and the programme cost out of the budget allocated by
DGIS for the Asia Biogas Programme. In addition, the Government of Bangladesh will need
to be requested to provide an appropriate contribution to the financing of the subsidy
component and/or programme cost. ƒ To finance the SNV technical assistance out of the core subsidy provided by DGIS to SNV. ƒ To explore the availability of funds, in-country and abroad, required to refinance the credit
requirements of the programme.
8.6 Assumptions and risks
It will be of great importance for the national biogas programme to get the full support from the Government of Bangladesh (GoB). So far, representatives of different stakeholders showed a clear interest and will to participate and/or support such a programme, and thus it is assumed that the GoB support will materialise also formally. The multiple benefits of the proposed biogas programme have clear linkages to the poverty reduction strategy (Government of the People’s Republic of Bangladesh, March 2003) and the attainment of the millennium development goals (World Bank, February 2005) envisioned by the GoB.
Another assumption is that the (potential) stakeholders will agree to upgrade and standardise the quality of products and services. Once the potential user has decided to install a biogas plants, he/she needs to be ensured to get the stipulated quality with respect to construction, after sales service and also financing.
A risk not yet mentioned in this report will be the period of time required to start implementing the national programme. First of all, SNV needs to be registered in Bangladesh as an INGO. The process required for such registration could take about six months. At the same time, the formulation of the detailed implementation plan could be already carried out for a period of four months, starting from September 2005. The approval of this plan by the GoB might take another nine months, making it likely that the first biogas plants under this programme can be only constructed in the last quarter of 2006, more than two years after the end of the Biogas Pilot Plant Project. It will also take time to arrange for a likely required refinancing facility that could fulfil the credit requirements of the programme. It is assumed, however, that this arrangement can be made within the 13 (4+9) months preparation time indicated above.
It may be considered: ƒ To start the registration process of SNV as an INGO in Bangladesh from July 2005 onwards.
CHAPTER 9: Main conclusions and recommendations
This Chapter only presents the main conclusions and recommendations. One is referred to the various chapters for more specific conclusions and recommendations.
9.1 Main conclusions
A national programme on domestic biogas in Bangladesh looks feasible as:
-
Bangladesh has already a rich history in domestic biogas with close to 24,000 units constructed throughout the country so far.
-
The technical potential for biogas amounts to minimum one million units, while there are no strong limiting social factors.
· The financial analysis indicates that an amount of Taka 7,000 as investment subsidy is generally sufficient to attract potential farmers resulting in a satisfactory financial rate of return (FIRR) of 15 percent for the farmer. The actual FIRR realized by the farmer, however, is largely dependent on the actual financial price for biomass. This underlines the need for an effective micro-credit facility. The economic internal rate of return (EIRR) for the biogas plant is 17 percent in the base case.
· Bangladesh is endowed with an impressive number and variety of institutes, organisations and companies with a large potential to participate in the implementation of a national programme. This organisational richness makes the establishment of a separate programme office unnecessary.
· There is a clear will and interest among (potential) stakeholders to be engaged in a national programme.
The tentative outline for such a programme with a longer-term vision to develop a commercial, sustainable biogas sector includes the production of 36,450 biogas plants up to 2009 and will cost about Euro 14.7 million. The biogas farmers, DGIS, SNV and GoB are the proposed financiers of the programme, to be supplemented by a provider of a refinancing facility for the credit requirements. The cost/benefit ratio of CDM financing still needs to be determined. It has been assumed that the GoB will fully support a national biogas programme and that (potential) stakeholders will agree to up-grade the quality of products and services. The long period required for the approval of an implementation plan is considered as a risk, all the more since the dissemination of biogas plants has come to a standstill in June 2004.
9.2 Main recommendations
The following are the main recommendations resulting from this feasibility study:
-
To SNV: To start with immediate effect the process of registering SNV as an international INGO in Bangladesh.
-
To SNV: To field a mission in July or August 2005 to select an implementing partner and sign a MoU with this partner for the formulation of a detailed implementation document.
-
To SNV and selected implementing partner: To formulate the detailed implementation document in cooperation with all potential stakeholders in Bangladesh in the period September to December 2005.
-
To SNV, selected implementation partner other main involved stakeholders: To pursue approval of the detailed implementation document, to make the required preparations and to start implementation of the programme in 2006.
CHAPTER 10: References
Aktaruzzaman, K., Biogas Pilot Plant Projects. Background, Objective and Achievements. Bangladesh Council of Scientific and Industrial Research, Dhaka, June 2003.
Aktaruzzaman, K., Operation and maintenance of biogas plants. Production of biogas and generation of electricity (PL).Paper prepared for the National Training Workshop on Renewable Energy Education in Bangladesh, 3-8 August 2003, Bangladesh Council of Scientific and Industrial Research, Dhaka.
Alam, M. et al.. Diffusion potential of renewable energy technology for sustainable development: Bangladeshi experience. Energy for Sustainable Development, Volume VII No.2, June 2003, page 88-96.
Bangladesh Bureau of Statistics, Report on the Household Income & Expenditure Survey 2000. Dhaka, March 2003.
Bangladesh Bureau of Statistics, Yearbook of Agricultural Statistics of Bangladesh 2001. Dhaka, June 2004.
Bangladesh Bureau of Statistics, 2002 Statistical Yearbook of Bangladesh 23rd Edition. Dhaka, November 2004.
Bangladesh Bureau of Statistics, Statistical Pocketbook of Bangladesh 2003. Dhaka, January 2005.
Bangladesh Council of Scientific & Industrial Research and Directorate of Livestock Services, Memorandum of Understanding for Research, Training and Dissemination of Biogas Technology. Dhaka, 20 March 1994.
Bangladesh Council of Scientific & Industrial Research and Local Government Engineering Department, Memorandum of Understanding for Research, Training and Dissemination of Biogas Technology. Dhaka, 8 October 1997.
Bangladesh Council of Scientific and Industrial Research, Project Proforma for Project: Biogas Pilot Plant (2nd Phase). Dhaka, June 2001. Biswas, W.K., Bangladesh’s Energy Sector: The Past, Present, and Future of Renewable Energy Technologies, School of History and Philosophy of Science, Australia, undated. BRAC, Project Proposal for Biogas Pilot Project. A Renewable Energy Initiative. Dhaka, September 2001. Chowdhury, S.S. and Aktharuzzaman, K., Biogas Users Survey 1983/84. DANIDA, Dhaka, Coordinated by W. Kock, August 1984.
Dagupta, S. et al., Indoor Air Quality for Poor Families. New Evidence from Bangladesh. The World Bank, Development Research Group, Policy Research Working Paper 3393, September 2004.
Dagupta, S. et al., Who Suffers from Indoor Air Pollution? Evidence from Bangladesh. The World Bank, Development Research Group, Policy Research Working Paper 3428, October 2004.
DLS (Department of Livestock Services), Department of Livestock Services; An overview. Dhaka, 2000.
DPC Group, Evaluation of Biogas Plants established at the Field Level under the Biogas Pilot Plant (First and Second Phase) Projects and Project Activities. Final Report. June 2004.
Eusuf, M., et al., Biogas from Cowdung: Effect of Urea as an Additive. Bangladesh J. Sci. Ind. Res., XVIII (1-4), 1983, page 127-135. Eusuf, M., An Approach to the Economic Evaluation of Family-Size Biogas Plants. Bangladesh
J. Sci. Ind. Res., XIX (1-4), 1984, page 220-238.
Eusuf, M., State of the Art in Utilization of Agricultural Residues and Other Biomass and Identification of Priority Projects in Bangladesh. Paper prepared for the Regional Workshop on Human Resources Development for Utilization of Agricultural Residues as Energy Source in Beijing and Huangzo, China, 4-13 May 1993, Bangladesh Council of Scientific and Industrial Research, Dhaka.
Eusuf, M., Dissemination of Renewable Energy Technologies in Bangladesh. Paper prepared for the Workshop on Renewable Energy Sources: Social Acceptance and Economical Prospects in Bangladesh, Dhaka, 8-11 January 1995, Bangladesh Council of Scientific and Industrial Research, Dhaka.
FAO, Livestock Information, Sector Analysis and Policy Branch, Livestock Sector Brief Bangladesh, October 2004.
Grameen Shakti, Construction of 200,000 Biogas Plants to Save the Health, Wealth and Environment. Dhaka, undated.
Government of the People’s Republic of Bangladesh, Bangladesh. A National Strategy for Economic Growth, Poverty Reduction and Social Development. Bangladesh, March 2003.
Hossain, M.M.G., Improved cookstove and biogas programmes in Bangladesh. Energy for Sustainable Development, Volume VII No.2, June 2003, page 97-100.
Islam, M.H. et al., Women’s participation in dairying. Bangladesh Journal of Animal Science, 28, 1991, page1–2.
Lam, J. and Boers, W., Report (draft) on the First Fact Finding Mission for a Biogas Support Programme in the Republic of Bangladesh. SNV, The Hague, February 2005.
Local Government Engineering Department, Project Proforma for Production and Uses of Biogas and Organic Fertiliser for Maintaining Environmental Balance (1st Revision). Dhaka, June 2003.
Mendis, M.S., and Van Nes, W.J., The Nepal Biogas Support Program: Elements for Success in Rural Household Energy Supply. Ministry of Foreign Affairs, the Netherlands, July 1999.
Ministry of Energy and Mineral Resources, Power Cell, Status of Renewable Energy in Bangladesh. Country Report. Bangladesh, undated.
Paul D.C. and Saadullah M., Role of women in homestead of small farm category in an area of Jessore, Bangladesh. Livestock Research for Rural Development, 2(3), 1991, page 23– 29
Rahman, M.A., Country Paper Bangladesh. Paper prepared for the Regional Seminar on Commercialisation of Biomass Technology in Guangzhou, China, 4-8 June 2001, Ministry of Electricity, Energy and Mineral Resources, Bangladesh.
Rahman, M.H. et al., A study on biogas technology in Bangladesh. Proceedings of the 22nd WEDC Conference, New Delhi, India, 1996.
Reid, H.F., et al, Indoor Smoke Exposures from Traditional and Improved Cookstoves: Comparison Among Nepali Women, Mountain Research and Development, Volume 6, No. 4, 1986.
Saadullah M. and Hossain M.M., Report on the quantification of locally available feed resources and feeding systems of animal in different regions of Bangladesh. Bangladesh Agricultural Research Council, Dhaka, and Bangladesh Agricultural University, Mymensingh, 2000.
SNV, Asia Biogas Programme: Access to sustainable energy for 1,300,000 people. A proposal (draft) prepared for DGIS/DMW. Den Haag, 22 November 2004.
World Bank, Attaining the Millennium Development Goals in Bangladesh .Human Development Unit, South Asia Region, February 2005.
Word Bank Group, World Development Indicators database. Washington, April 2005.
Annex 1: Terms of Reference
1. Introduction and background
In the framework of its Asia Biogas Programme co-financed by DGIS, SNV aims to set-up a large-scale biogas programme in the Republic of Bangladesh. A brief fact finding mission was conducted in November 2004 and reported in February 2005. The mission report concluded that the circumstances in Bangladesh seem favourable to establish a national biogas programme and recommends commissioning an in-depth study on its feasibility. This document presents the Terms of Reference (ToR) for this study.
2. Objective of the study
-
The objective of the study is to thoroughly assess the feasibility to set-up and implement a
national biogas programme in the Republic of Bangladesh.
More specifically, the study will address the following areas: -
Country background including agricultural & livestock sector, energy demand and supply,
-
energy policy and plans;
-
History of domestic biogas;
-
Potential demand for domestic biogas;
-
Possible supply of services for domestic biogas; and
-
Outline for a national programme on domestic biogas.
3. Activities and methodologies
The following activities and methodologies are proposed:
A. Preparation of a mission to Bangladesh by using the fact finding mission report, collecting secondary information, contacting key respondents and informants in Bangladesh and abroad, and drafting checklists for biogas plant visits and interviews;
B. Mission to Bangladesh to visit biogas plants constructed by various programmes in the past, to meet key respondents and informants for interview and discussion. The mission shall include a workshop to discuss with the main stakeholders the roles of the different actors in Bangladesh and the outline of a possible national biogas programme;
C. Formulation of the draft study report and submission for comment to SNV/Nepal and members of the Biogas Practice Team (BPT) of SNV;
D. Submission of the final study report by incorporating the comment from SNV/Nepal and members of the BPT.
4. Time schedule
The mission to Bangladesh shall be completed within a period of three weeks in March 2005. The draft report shall be submitted before 15 April 2005. SNV/Nepal and members of the BPT will provide within 10 working days comment on the draft report. After that, the final study report will be presented within five working days.
5. Budget
The costs of this study will mainly consist of expenses for travelling and DSA of the team members, a consultancy fee for a local expert and some other local expenses if deemed required for example for the collection of baseline data. All costs will be borne by the budget for the up-scaling of biogas in Asia.
6. Expected output The report on the feasibility study shall be well-structured and clearly written not exceeding 50 pages excluding annexes and provide informed recommendations on the possibilities for SNV to set-up a national biogas programme in Bangladesh.
7. Composition of the team
The mission team shall consist of three members: a team leader, an engineer and an independent, external local or regional expert. The team leader and the engineer will be members of the BPT of SNV, while the external expert will be recruited in the region.
8. Further arrangements
Prior to the mission to Bangladesh, the team leader will come up with an itinerary for the mission to Bangladesh. The mission team is free to discuss any matter concerning the assignment with any institution or individual, but is not authorised to make any official commitments on behalf of SNV.
9. References
[1] Jan Lam and Willem Boers, Report (draft) on the First Fact Finding Mission for a Biogas Support Programme in the Republic of Bangladesh. SNV, February 2005.
Annex 2: Programme of
the mission
|
Thursday, 10 March 2005: |
|
||
|
|
Arrival of Wim van Nes and Willem Boers in Dhaka by air |
|
|
|
|
|
|
|
|
Friday, 11 March 2005: |
|
||
|
|
Preparation |
|
|
|
|
|
|
|
|
Saturday, 12 March 2005: |
|
||
|
09.30-11.15 |
Meeting with possible local team member |
|
|
|
|
Preparation |
|
|
|
|
|
|
|
|
Sunday, 13 March 2005: |
|
||
|
|
Preparation |
|
|
|
11.00-13.00 |
Meeting with Mr. Md. Nurul Islam |
LGED, Superintending Engineer |
|
|
11.30-12.15 |
Meeting with possible local team member |
|
|
|
15.00-17.00 |
Meeting with Mr. Otto Gomm and |
GTZ, Coordinator PURE |
|
|
|
Mr. Syed A.F.M. Sajedul Huq |
GTZ, Senior Renewable Energy Specialist |
|
|
|
|
|
|
|
Monday, 14 March 2005: |
|
||
|
09.30-12.45 |
Meeting with Mr. Kazi Aktaruzzaman |
BCSIR, Project Director & Principal Scienti |
fic |
|
|
|
Officer |
|
|
13.30-15.00 |
Meeting with Engr. B. Rahmatullah and |
Director Power Cell, MoPEMR |
|
|
|
Dr. A.K.M. Masood |
Director General Power Cell, MoPEMR |
|
|
|
|
|
|
|
Tuesday, 15 March 2005: |
|
||
|
09.00-17.00 |
Field visit with Mr. Sudip Kumar Saha to |
BRAC, Engineer (Solar) |
|
|
|
biogas plants in Gazipur district |
|
|
|
|
|
|
|
|
Wednesday and Thursday 16 and 17 March 2005: |
|
||
|
09.00-17.00 |
Field visit with Mr. Md. Sharful Anam Khan |
LGED, Assistant Engineer |
|
|
|
and Mr. Shamaresh Ghosh to biogas |
LGED, Biogas Specialist |
|
|
|
plants in Manikganj, Faridpur and |
|
|
|
|
Madaripur district |
|
|
|
|
|
|
|
|
Friday and Saturday 18 and 19 March 2005: |
|
||
|
09.00-17.15 |
Field visit with Mr. Kazi Aktaruzzaman, Mr. Jafora Shabbir Ahmed, Mr. Jasim Uddin Chowdhury, and Mr. Mosammel Hoque Mollah, to biogas plants in respectively Narayanganj, Comilla and Gazipur district |
BCSIR, Principal Scientific Officer Agency holder, Narayanganj district Agency holder, Comilla district Agency holder, Gazipur district |
|
|
|
|
|
|
|
Sunday, 20 March 2005: |
|
||
|
10.00-12.45 |
Meeting with Mr. Dipal C. Barua, |
GS, Managing Director |
|
|
|
Mr. Abser Kamal, |
GS, General Manager, |
|
|
|
Mr. Abdul Gofran, |
GS, Biogas Consultant |
|
|
|
Engr. Md. Quamrul Haque, |
GS, Assistant General Manager |
|
|
|
Mr. Khandaker Nazmul Hoque, and |
GS, Sub-Assistant Engineer |
|
|
|
Mr. Kazi Mahmud Ullah |
GS, Assistant General Manager |
|
|
14.00-16.00 |
Meeting with Mr. Md. Nurul Islam, Mr. Shamaresh Ghosh and Mr. Saleh Ahmed |
LGED, Superintending Engineer LGED, Biogas Specialist LGED, Assistant Engineer (Environment) |
|
|
|
|
|
|
|
Monday, 21 March 2005: |
|
||
|
10.00-11.30 |
Meeting with Dr. M. Fouzul Kabir Khan and |
IDCOL, Executive Director & CEO |
|
|
|
Ms K. Farah Nayer Zabeen |
IDCOL, Investment Officer |
|
|
12.30-14.15 |
Visit to IFRD of BCSIR |
|
|
|
15.00-17.00 |
Meeting with Dr. M. Eusuf, |
BCAS, Senior Fellow |
|
|
|
Dr. Moinul Islam Shariff and |
BCAS, Fellow |
|
|
|
Mr. Khandaker Mainuddin |
BCAS, Fellow |
|
|
|
|
|
|
|
Tuesday, 22 March 2005: |
|
||
|
12.00-13.30 |
Meeting with Dr. M.A. Rashid Sarkar |
|
BUET, Professor |
|
15.00-16.00 |
Meeting with Mr. Gunendu K. Roy and |
|
BRAC, Coordinator Developm. Programme |
|
|
Mr. Sudip Kumar Saha |
|
BRAC, Engineer (Solar) |
|
|
|
|
|
|
Wednesday, 23 March 2005: |
|
||
|
09.00-17.00 |
Preparation of Workshop |
|
|
|
|
|
|
|
|
Thursday, 24 March 2005: |
|
||
|
09.30-14.00 |
Consultative Stakeholders Workshop at LGED |
|
See Annex 4 for brief report and list of participants |
|
15.00-15.30 |
Meeting with Mr. Zahir Uddin Ahmad |
|
RNE, Advisor Water Management Sector |
|
|
|
|
|
|
Friday, 25 March 2005: |
|
||
|
|
Departure of Willem Boers from Dhaka by air |
|
|
|
09.00-17.00 |
Recapitulation and reporting |
|
|
|
|
|
|
|
|
Saturday, 26 March 2005: |
|
||
|
|
Reporting |
|
|
|
|
|
|
|
|
Sunday, 27 March 2005: |
|
||
|
09.30-10.45 |
Meeting with Dr. Bilqis Amin Hoque and |
|
EPRC, Executive Director & Head Research |
|
|
Mr. Md. Shoriful Islam |
|
EPRC, Programme Manager |
|
13.00-14.00 |
Meeting with Mr. Habibur Rahman |
|
KfW, Local Expert |
|
|
|
|
|
|
Monday, 28 March 2005: |
|
||
|
10.30-11.30 |
Meeting with Mr. Md. Abdus Sobhan Miah |
|
BLRI, Additional Director |
|
|
and Dr. Khan Shahidul Huque |
|
BLRI, Chief Scientific Officer & Head Animal |
|
|
|
|
Production Research Division |
|
12.30-13.00 |
Meeting with Mr. A.K.M. Musa |
|
BBS, Director General |
|
14.00-14.30 |
Meeting with Dr. Jahangir Alam |
|
BARC, Member Director |
|
14.45-15.30 |
Meeting with Mr. Abul Kalam Azad and |
|
NGOAB, Director |
|
|
Mr. Mohammed Walid Hossain |
|
NGOAB, Assistant Director, Registration |
|
15.45-16.30 |
Meeting with Mr. M. Khaliquzzaman |
|
WB, Environmental Scientist (Consultant) |
|
|
|
|
|
|
Tuesday, 29 March 2005: |
|
||
|
09.30-11.00 |
Meeting with Mr. Abdul Gofran |
|
GS, Biogas Specialist |
|
15.15-15.45 |
Meeting with Dr. Kazi Aktaruzzaman |
|
BCSIR, Project Director & Principal Scientific |
|
|
|
|
Officer |
|
16.00-16.45 |
Meeting with Mr. Gazi Nasir Uddin Borham |
|
BBBB, Coordinator |
|
|
|||