Skip to main content.
 
 
 
 
 
Biomass Programme  in Bangladesh ::

 

Biogas Programme

Improve Cook stoves programme

Biomass Gasification Programme

Electricity generation from poultry waste

Biomass Briquetting Programme in Bangladesh

Improvement of Rice Parboiling System  in Bangladesh

Biogas uses for cooking purposes at Noakhali

 

 

 

Historical Background  :

 

In 1972 Bangladesh entered into the arena of biogas technology through the first demonstration biogas plant by Dr. M A Karim at Bangladesh Agriculture University (BAU), Mymensingh campus. This plant was floating-dome type and the size was 3 cubic meter. Later on, another plant was constructed (210 cft digester volume) to serve the purpose of lighting and cooking for a family of 6 members.

 

In 1974, another plant was constructed at Bangladesh Academy for Rural Development (BARD), Comilla.

 

In 1976, IFRD constructed a family-size biogas plant at BCSIR campus at cost of TK 12,000. In 1980, another plant was setup in KBM College, Dinajpur at a cost of TK 15,000. After reduction of cost to Tk. 3000 (now raised to Tk. 10,000 because of price increase of materials ) requests from well-to-do farmers for this cheaper model have started pouring in. At the request of the owners , the experts of IFRD help set up the plants, the entire cost being borne by the owners. Over seventy gas plants of this model were installed entirely at the cost of the owners. With a view to speeding up the dissemination, the IFRD has introduced two-week-long training courses on construction, operation and maintenance of biogas plants. 60 nominees from Bangladesh Small and Cottage Industries Corporation (BSCIC), Bangladesh Rural Development Board (BRDB), the World Bank and NGOs have been trained. These trainees motivate the people and help set up biogas plants in consultation with the experts of the IFRD.

 

In 1980, in order to extend bio-gas technology, a department named Environmental Pollution Control Department (EPCD) was established.

 

In 1981, Department of Environment (DOE) started the programme under a government grant and installed 110 plants of fixed-dome model and over 150 plants of floating - dome type through hired contractors. All the plants were supplied free of cost.

 

Meanwhile, 24 district level officers of BSCIC were trained in the IFRD and through these trained personnel, BSCIC introduced a number of plants , the construction cost being borne by the owners. DANIDA temporarily supported installation of a few trench and bag type digesters.

 

In 1985, Local Government Engineering Department (LGED), under the initiative of its Chief Engineer, Quamrul Islam Siddique, started study, research, development and extension of bio-gas technology.

 

In 1986, LGED constructed its first bio-gas plant at Kurigram and arranged a seminar there which was attended by about 300 engineers, scientists and interested persons from different places.

 

Iin 1992, the IFRD of BCSIR in collaboration with Dhaka City Corporation built an experimental biogas plant of 85 cubic meter digester volume at Dholpur for treatment of city garbage. Charging of 52.5 tons of garbage produced 2000 cft biogas/day on the average over a period of two months and 40 tons of residue (biofertilizer) rich in plant nutrients. The residue had no odor.

 

In June 1992, LGED constructed first Chinese-type fixed-dome model bio-gas plant in Karimpur village of Begumgonj, Noakhali. In the same year LGED also constructed the first biogas plant from night soil at Faridpur Muslim Mission.

 

In 1993, LGED constructed the first biogas plant from water hyacinth at Madaripur.

In 1994, LGED constructed the first biogas plant from poultry droppings at Utter Khan, Dhaka and garbage-based biogas plant at 10 towns. At the end of 1994, LGED constructed about 200 biogas plants out of which eight were floating-dome type and the rest were fixed-dome type. Among the plants 73 were based on night soil, one based on water hyacinth, two based on poultry droppings, 23 based on garbage and the rest were based on cow dung.

The Key stakeholders on Biomass Technology application in Bangladesh :

 

Potential stakeholders for a national programme on domestic biogas in Bangladesh, divided into government, civil sector and private sector organizations. Bangladesh is endowed with an impressive number and variety of institutes, organizations and companies. Besides these described below, many more could be called upon to participate in the implementation of a national programme on domestic biogas. This organizational richness can be regarded as a very positive starting point for such a programme and makes the establishment of a separate programme office unnecessary.

 

Organizations involved in the dissemination of biogas plants in Bangladesh and number of plants installed: 

 

Sl no

Organization

Installation Period

Number of Biogas plants installed

1

Bangladesh Council of Scientific & industrial Research

1973-2005

22,100

2

Local Government Engineering Department

1985-2001

7,000

3

Department of Environment

1979-1983

260

4

Bangladesh Rural Advancement Committee 

1987-2005

300

5

Department of Livestock

1988-1994

70

6

Thengamara Mohila Sabuj Sangha (TMSS)

 

 

7

Bangladesh small & Cottage Industries Corporation

1983-1988

30

8

Bangladesh Agricultural Development Corporation

1983-1984

20

9

Danish International Development Agency

1982

4

10

Bangladesh Agricultural University

1971-1973

2

11

Housing & Building Research Institute

1981

2

12

Bangladesh Academy for Rural Development

1974

1

13

Bangladesh Commission for Christian Development

1978

1

14

Bangladesh Rice Research Institute 

1983

1

 

Total

 

29,789

 

Construction Partner Organization( CPO) under IDCOL

 

 

 

Grameen Shakti ( GS its own programme + IDCOL )

 

6,000

 

SOUL

 

1,000

 

Kamrul Biogas

 

517

 

Rahman Biogas

 

368

 

Hosain Biogas

 

301

 

RSF

 

205

 

Srizony Bangladesh

 

240

 

Shubashati

 

116

 

BRIDGE

 

23

 

SAPNO

 

44

 

Nirapod Engineering Ltd.

 

30

 

Sangram

 

25

 

BASA

 

20

 

Sonali Unnayan Foundation

 

35

 

DESHA

 

23

 

Practical Action

 

18

 

Nurunnabi Biogas

 

11

 

Change Maker

 

3

 

Palli Shakti

 

2

 

Jahanara Biogas

 

1

 

Total

 

4,934
(November 19 , 2008)

 

Grand Total

1971-2008

38,765

(November 19 , 2008)

 

 

Over 7,000 Biogas Plants constructed under NDBMP


Beginning from June 2006, IDCOL has constructed more than 7,000 ( until 22 March 2009) Biogas plants in rural areas through its Partner Organizations (POs) under National Domestic Biogas and Manure Programme (NDBMP). IDCOL is implementing the programme with support from GoB, SNV Netherlands and Kfw.

 

(Biogas plant under constructions)

 

Biomass Power Plant 

Plant type: Rice-husk as primary fuel for power generation

Plant Capacity: 250 kW

Project Location : Giaspurbazar, Gazipur.

Progress with Biogass Plant installation up to 29 September 2008

IDCOL installed over 7000 biogas plants under NDBMP ( September 29 , 2008)

CPO wise installation of Biogass Plants

Construction Partner Organization                                                         

Biogass Plant Completed

Grameen Shakti

1,957

SOUL

1,000

Kamrul Biogas

517

Rahman Biogas

368

Hosain Biogas

301

RSF

205

Srizony Bangladesh

240

Shubashati

116

BRIDGE

23

SAPNO

44

Nirapod Engineering Ltd.

30

Sangram

25

BASA

20

Sonali Unnayan Foundation

35

DESHA

23

Practical Action

18

Nurunnabi Biogas

11

Change Maker

3

Palli Shakti

2

Jahanara Biogas

1

Total

4,934

 

   Click here to Find More about IDCOL/SNV/GTZ Biogas Programme

 

Bangladesh Council of Scientific & industrial Research

 

Institute of Fuel Research and Development (IFRD) under BCSIR has installed large number of Biogas plants all over the country. There are 22,100 Biogas plants installed by BCSIR. BCSIR pioneered the Biogas programme in Bangladesh.  Most of the beneficiaries are meeting their energy demand from biogas plants. Popularity of this technology are gradually increasing in the country. To meet 21st centuries energy demand, elaborate programmes have been taken to supply biogas to the door steps of the common people of the country.

 

1. Type of Installation : Biogas Plant

  • No of Installation : 22,100

  • Uses of Biogas Plants : Domestic cooking & lighting generation of electricity 

  • Cost of Installation :  Tk. 15,000.00-1,00,000.00

  • Location of Installation :All over the country

  • Functional Status : 99 % of the plants are in use.

2. Type of Installation : improved stoves

  • No of Installation : about 2 lacks

  • Type of  Installation :Domes

  • Uses of Biogas Plants : Cooking to industrial heating purposes

  • Cost of Installation :  -Imp sig. mouth- $ 1-Imp double mouth $ 4 -Inst. stoves $ 28

  • Location of Installation :All over the country

  • Functional Status : about 70-80%

 

 

Click here Find More about BCSIR(IFRD) Biogas Programme

 

 

 

Local Government Engineering Department

 

 Biogas technology has been gaining popularity and importance, especially in the developing countries because of its appropriateness in the context of technical, socio-economical and resource endowments of these countries. With zeal and commitment to serve the nation, LGED has been involved in dissemination of biogas technology since 1985 and has been able to demonstrate its usefulness at more than thousand sites in different parts of the country.

 

 

 

 Find More about LGED Biogas Programme

 Grameen Shakti

 

 

By now, GS installed nearly, about 6000 biogas plant (November, 2008) of size 1.6m3-70m3 gas production capacity per day, 370 commercial and 2000 domestic improved cook stoves. Grameen Shakti installed 3 experimental wind mills and one biomass gassifier. Grameen Shakti is now installing around 4000 systems per month i.e. about 50,000 systems annually.

 

Grameen Shakti has taken a massive program for the coming years which is aiming to install more 1 million biogas plants and 10 million improved cook stoves by the year 2015.

 Find More about Grameen Shakti  Biogas Programme

 

Bangladesh Rural Advancement Committee 

 

BRAC so far  installed total 300 biogas plants with type of FBS/CBS. Capacity of installation  1.8X104 cft  in all over of Bangladesh.

 

 Find More about BRAC conducted Biogas Programme

Recently BRAC has installed 2 power Unit using Biogas :

 

The power unit using producer gas from cow dung (biomass). The DC generator is used for power generation :

1. Location :  Shaturia Upazila under Manikganj District 

Installed Capacity : 800Wp

Generator : DC

Input : Cow dung

2.  Location :  Shafipur  Upazila under Tangail  District 

Installed Capacity : 800Wp

Generator : DC

Input : Cow dung

 

 

Find Details at ; http://www.bracresearch.org    http://www.brac.net

 

 

Thengamara Mohila Sabuj Sangha (TMSS)

 

 

TMSS  so far  installed total 300 biogas plants with type of FBS/CBS. Capacity of installation  1.8X104 cft  in all over of Bangladesh.

 

 Find More about TMSS Biogas Programme

Less Privileged Peoples Emancipation Programme

 

Working in the field of RE since 2007 with partnership programme with Kamrul Biogas Co. Led. ( Rajbari). Preliminary functions is going on with biogas plant . Till to day 5 family  biogas plant implanted under IDCOL support.

 

Rural Services Foundation

Biogas Program of RSF

in Bangladesh some privileged urban people have the facility to use the natural gas but the rural are using the biomass, firewood or cow dung in a conventional way and they are just burning it in presence of air and thus it create lot of smoke in the air and which is harmful for the health, specially for children and women. To address the issue and considering the local scenario RSF is working as a Partner Organization of IDCOL & GTZ. So far RSF has constructed 221 biogas plants till July 2008.

 

Biogas is the signature programme of SNV in the region and has the potential to be scaled up within existing countries and in new ones to more than two million people by 2010.   

National Domestic Biogas and Manure Programme in Bangladesh  

 

Biogas / Biomass Programme all over the Bangladesh :

 

 

 

 

 

Please visit District wise Biogas Plants / Biomass Energy Unitizations  in Bangladesh

(District Name)

B.Baria

Gaibandha

Madaripur

Pabna

Bagerhat

Gazipur

Magura

Panchagarh

Bandarban

Gopalganj

Manikganj

Patuakhali

Barguna

Habiganj

Meherpur

Perojpur

Barisal

Jamalpur

Moulvibazar

Rajbari

Bhola

Jessore

Munshiganj

Rajshahi

Bogra

Jhalokathi

Mymensingh

Rangamati

Chandpur

Jhenaidah

Naogaon

Rangpur

Chittagong

Joypurhat

Narail

Satkhira

Chuadanga

Khagrachari

Narayanganj

Serajganj

Comilla

Khulna

Narshingdi

Shariatpur

Cox's Bazar

Kishoreganj

Natore

Sherpur

Dhaka

Kurigram

Nawabganj

Sunamganj

Dinajpur

Kushtia

Netrokona

Sylhet

Faridpur

Lalmonirhat

Nilphamari

Tangail

Feni

Laxmipur

Noakhali

Thakurgaon

 

 

 

  Last Updated:  25 April, 2009