Biogas Plant Design :
- Introduction :
- DEVELOPMENT OF BIOGAS TECHNOLOGY
- POTENTIALS OF BIOGAS IN BANGLADESH
- INVOLVEMENT OF LGED IN BIOGAS TECHNOLOGY
- Types of Biogas Digester
- SOME EXAMPLES of Biogas Installation by LGED
- DESIGN OF BIOGAS PLANT
- CONSTRUCTION PROCEDURE OF BIOGAS PLANT
- Introducing Grameen Shakti’s Biogas Program( Different steps of biogas plant with photos)
Introduction :
Bangladesh is densely populated country. Large proportions of rural and urban poor traditionally harvest; fire wood, Vegetation, animal excreta and agricultural residues for domestic cooking. These methods proved to be unsustainable as fire woods contributed to higher levels of deforestation. Vegetation covers only 9-10 % of total land, which is lowest as world average. Population explosion and to meet related energy demands deforestation level is higher than forestation efforts which is resulting environmental degradation. Uses of fire wood increases at rate of 2 % annually. The high cost of petroleum products, low coverage of the electricity grid, gasification and increasing scarcity of traditional fuel woods due to deforestation created an energy deficit situation in rural Bangladesh. Environmental experts predicted massive deforestation if crisis is not being met from alternative source.
Historical Background :
In 1972 Bangladesh entered into the arena of biogas technology through the first demonstration biogas plant by Dr. M A Karim at Bangladesh Agriculture University (BAU), Mymensingh campus. This plant was floating-dome type and the size was 3 cubic meter. Later on, another plant was constructed (210 cft digester volume) to serve the purpose of lighting and cooking for a family of 6 members.
In 1974, another plant was constructed at Bangladesh Academy for Rural Development (BARD), Comilla.
In 1976, IFRD constructed a family-size biogas plant at BCSIR campus at cost of TK 12,000. In 1980, another plant was setup in KBM College, Dinajpur at a cost of TK 15,000. After reduction of cost to Tk. 3000 (now raised to Tk. 10,000 because of price increase of materials ) requests from well-to-do farmers for this cheaper model have started pouring in. At the request of the owners , the experts of IFRD help set up the plants, the entire cost being borne by the owners. Over seventy gas plants of this model were installed entirely at the cost of the owners. With a view to speeding up the dissemination, the IFRD has introduced two-week-long training courses on construction, operation and maintenance of biogas plants. 60 nominees from Bangladesh Small and Cottage Industries Corporation (BSCIC), Bangladesh Rural Development Board (BRDB), the World Bank and NGOs have been trained. These trainees motivate the people and help set up biogas plants in consultation with the experts of the IFRD.
In 1980, in order to extend bio-gas technology, a department named Environmental Pollution Control Department (EPCD) was established.
In 1981, Department of Environment (DOE) started the programme under a government grant and installed 110 plants of fixed-dome model and over 150 plants of floating - dome type through hired contractors. All the plants were supplied free of cost.
Meanwhile, 24 district level officers of BSCIC were trained in the IFRD and through these trained personnel, BSCIC introduced a number of plants , the construction cost being borne by the owners. DANIDA temporarily supported installation of a few trench and bag type digesters.
In 1985, Local Government Engineering Department (LGED), under the initiative of its Chief Engineer, Quamrul Islam Siddique, started study, research, development and extension of bio-gas technology.
In 1986, LGED constructed its first bio-gas plant at Kurigram and arranged a seminar there which was attended by about 300 engineers, scientists and interested persons from different places.
Iin 1992, the IFRD of BCSIR in collaboration with Dhaka City Corporation built an experimental biogas plant of 85 cubic meter digester volume at Dholpur for treatment of city garbage. Charging of 52.5 tons of garbage produced 2000 cft biogas/day on the average over a period of two months and 40 tons of residue (biofertilizer) rich in plant nutrients. The residue had no odor.
In June 1992, LGED constructed first Chinese-type fixed-dome model bio-gas plant in Karimpur village of Begumgonj, Noakhali. In the same year LGED also constructed the first biogas plant from night soil at Faridpur Muslim Mission.
In 1993, LGED constructed the first biogas plant from water hyacinth at Madaripur.
In 1994, LGED constructed the first biogas plant from poultry droppings at Utter Khan, Dhaka and garbage-based biogas plant at 10 towns. At the end of 1994, LGED constructed about 200 biogas plants out of which eight were floating-dome type and the rest were fixed-dome type. Among the plants 73 were based on night soil, one based on water hyacinth, two based on poultry droppings, 23 based on garbage and the rest were based on cow dung.
DEVELOPMENT OF BIOGAS TECHNOLOGY
INTRODUCTION
Organic matters such as animal and human excreta, agricultural and industrial waste, water hyacinth etc. when fermented under an anaerobic condition produce a combustible gas called Biogas. It is a renewable source of energy, can be used as fuel for cooking, lighting, running vehicles and generators, etc. Other natural resources like oil, gas etc. are limited and will be exhausted in course of time. That is why, the developed countries consider their natural resources very precious and are cautious about extracting those. In Bangladesh neither the decision-makers nor the experts pay due importance on proper extraction and use of natural resources. With the present rate of consumption, natural energy resources like gas will be exhausted shortly and this is high time to derive policy and practice for exploration and use of alternative renewable sources if we want to meet energy crisis in near future. Biogas has been found to be a proven renewable energy option.
POTENTIALS OF BIOGAS IN BANGLADESH
Cattle dung available from 22 million cows and buffaloes is nearly 220 million kg. One kg. Of dung can produce 0.037 cum of Biogas. i. e. available cattle dung can produce 2.97XIO9 cum of gas which is equivalent to 1.52X106 tons of kerosene or 3.04X106 tons of coal. Besides, a substantial amount of Bio-gas can be produced from human and animal excreta, garbage and water hyacinth. If all the household can be brought under Biogas technology, it is possible to get 1.03X 109 cum of gas from the filth of human being only. A conversion of 5% of different raw materials should produce an estimated 2X108 cum/day of Biogas.
At present bangladesh meet 46.15% of its energy need by agricultural residue, 10.5 % by fule wood and 33% bt tree residue. Biogas will reduce energy deficit 15 %.
INVOLVEMENT OF LGED IN BIOGAS TECHNOLOGY
LGED has been created mainly to provide technical support to the local government institutions. This organization can play an important role in disseminating appropriate technology all over the country as it has setup at Thana level. LGED constructed it's first Biogas plant in 1986 in Kurigram and organized a seminar on Biogas technology there. By now LGED constructed 300 of Biogas plants in different districts of Bangladesh, of which 106 are on night soil, 15 on garbage, 3 on poultry droppings, 2 on water hyacinth and the rests on cow dung. Initially LGED constructed 15 floating dome type plants. Due to corrosion and leakage on steel domes, these plants did not work for long time. In June 1992, LGED constructed two fixed dome type Chinese model plants in Noakhali. These plants are working without any problem. After close monitoring of success of these two plants, LGED started wide application of this. Subsequently, based on local condition and practical situation, LGED developed its own model.
First Biogas plant based on night soil was constructed by LGED in Faridpur Muslim Mission. Before construction of this plant, load there was an apprehension about its acceptability. But after completion of the plant there was no social and cultural barrier. This plant could drew attention of all concerned. Small bore sewerage system, in conjunction with Biogas plant installed by LGED in Bauniabad slum in Dhaka proved to be cheaper and better solution for sewage disposal. Solid waste and water hyacinth based Biogas digesters of LGED also created great interest among the users. LGED has so far trained 70 professional engineers on Biogas technology, 4 of whom received higher training in China. To provide technical support to the beneficiaries, gradually all the engineers of LGED will be trained on Biogas technology.
Types of Biogas Digester :
There are three types of basic designs of biogas plants tried in Bangladesh :
(i) floating cover digester, (ii) fixed cover digester, and (iii) plastic cover digester.
(i) Floating cover digester : It works on the principle of constant pressure, changing volume. The disgester, cylindrical well, commonly made from brick and cement, is covered with a floating steel cylinder with an open bottom (Fig. A). As the cylinder has a contant weight, it moves up when gas production is higher than consumption and comes down under the reverse conditions.
(ii) Fixed cover digester : It works according to the principle, constant volume, changing pressure. When the rate of gas production is higher than that of gas consumption pressure inside the digester rises and expels some digester contents into the outlat compartment. When the consumption is higher than production, pressure inside the digester falls and the expelled materials in the outlet compartment run back to the disgester (Fig. B)
(iii) Plastic Cover digester : A long cylindrical polythene/PVC bag, half-buried longitudinally in the ground, is fed with fresh cow-dung slurry at one end and discharged at the other. With the formation of gas, the bag swells like a balloon and the gas is led out to the point of use through a pipe by putting pressure on the balloon form outside (Fig. C)
In early 80’s, the floating type design was used for biogas plant. But due to corrosion of the steel dome, the gas leakage problem happened and it could not be removed. Later on BCSIR tried with fixed done type design and it has been successful in all biogas plants. The plastic bag type design is not used in Bangladesh It is used in China. In this project, the fixed dome type design has been proposed.
Gas Generation Rate
Daily input in the digester is 221xO.5 kg. =110.05 kg. Assuming water content to be 83% the quantity of suspended solid will be 18,71 kg. For optimum gas generation, the percentage of suspended solid should be 8%. To attain this percentage, water and night soil mixing proportion should be 1:1. But in practice the users generally use more then 3 liters of water for the cleansing purpose, as a result the percentage of solid reduced to 2.5. This causes drastic reduction in gas production. This problem is no more acute where there is no water supply reduction in gas production. This problem is no more acute where there is no water supply system. To improve this situation, we have decided to add kitchen waste with night soil.
Sector-wise Energy Consumption
|
|
|
|
|
Agriculture residue |
: |
46.4% |
|
Cow dung |
: |
10.5% |
|
Natural gas |
: |
12.3% |
|
Fire Wood |
: |
12.9 % |
|
Tree residue |
: |
3.3% |
|
Petroleum |
: |
10.4 % |
|
Coal |
: |
1.8 % |
|
Electricity |
: |
2.4 % |
Comparison between the Organic Fertilizer with cow dung & city waste:
Disposal of city waste is common problem all over the world . In Developed countries 75 % of the city waste is are inorganic. But in Bangladesh 75 % of the city waste are organic, which can easily be used in a biogas digester. In Dhaka alone about 3000 tons of garbaze is being dumped every day which could meet the need of organic fertilizer and enrich our soil nutrient contents of City waste as compared to cow dung is shown below :
|
Nutrients |
Nutrients Elements |
City Waste |
Cow dung |
|
Major nutrients |
Nitrogen |
2.6 % |
1.30 % |
|
|
Phosphorus |
0.45 |
0.33 |
|
|
Potassium |
0.93 |
0.90 |
|
|
Calcium |
0.64 |
1.26 |
|
|
Magnesium |
0.75 |
0.63 |
|
|
Sulphur |
0.12 |
0.15 |
|
Micro nutrient |
Copper |
72 ppm |
45 ppm |
|
|
Iron |
39 |
30 |
|
|
Manganese Zinc |
120 |
108 |
|
|
|
45 |
33 |
SOME EXAMPLES
A) Biogas plants in Madrasa orphanage / other institution LGED has constructed 61 Biogas plants in different Madrasas, orphanages, hospitals, school/college hostels and mosques for solving the sanitation problems and getting biogas as an alternative energy source. One of these important plants is in Faridpur Muslim Mission. There are 250 students and staff in Faridpur Muslim Mission. For their night soil disposal they needed to construct a septic tank for 250 users with Tk. 60,000.LGED in mid 1992 constructed a Biogas plant with Tk. 16,000 which served the purpose of septic tank as well as a source of gas and fertilizer. This has reduced the investment by Tk. 34,000 and the mission has been saving Tk. 25,000 against fuel cost per year.
B) Bauniabad small bore sewer system The project is an innovation of environment friendly energy source and sanitation system and described in some detail elsewhere.
C) Ganaktuli Sweeper colony, Dhaka There are five buildings for sweepers and 40 families reside in each building. The latrines of the buildings were not connected with any septic tank or sewerage system. Previously, night soil was passing through surface drain creating health hazard. To connect the latrines of building No-I to the nearby sewer line Tk. 60,000 and to construct a septic tank for 221 users of the building Tk. 50,000 were necessary. Instead, LGED constructed a Biogas plant for Tk. 20,000 in 1993 which is working till today without any problem giving sufficient gas to meet fuel need of 3 families. There was some maintenance for leakage and Tk. 300 was spent. Observing the performance of the plant, residents of other 4 buildings created pressure on the city corporation to construct similar plant in those buildings. By now Biogas plants have been constructed in all the remaining 4 buildings.
D) 'Ecological Village' Amgram / Uttar Hogla in Madaripur LGED took up 'Ecovillage' project on experimental basis as pilot programme with the objectives to make the villagers aware about environment and technology, create clear, healthy and acceptable environment in the villages and inspire the people around the villages to accept such project.
There are 662 people in the village in 123 families. Besides other socio economic activities, the following facilities were also provided:
There was no latrine in the village and 95 latrines were constructed. .As an alternative source of energy 15 Biogas plants were installed, three persons were trained in the construction of Biogas plant. The Biogas plants are providing energy input to the villagers.
Acceptability
It was apprehended people would not use gas from night soil for cooking purpose. During construction of the plant in Faridpur Muslim Mission, there was hesitation among the students and staff. When they found that there is no bad smell, they readily accepted the technology. In Ganaktuli and other places LGED faced no such problem of acceptability.
Affordability
Biogas is a proven technology, There is no risk of failure if proper design and supervision can be ensured. Most of the commercial banks are now convinced and took decision to provide loan for the construction of Biogas plants. Most of the urban poor can not afford gas connection as it costs Tk 200 to Tk. 400 per month. Instead they can install Biogas plants with. bank loan and repay the loan out of their fuel savings 'domestic' size Biogas plant of 100 cft capacity cost Tk. 15,000 to Tk. 18,000 and can meet the cooking energy need for a five- member family.
Impact on health and environment
Large scale bioenergy development in Bangladesh could bring significant environmental benefits. Sustainable bioenergy development could:
· Reduce higher lavel of deforestation
· reduce net greenhouse gas emissions
· improve air quality and reduce acid deposition
· improve soil quality and reduce erosion
· reduce landfilling by adding value to residues
· reduce agricultural chemical runoff
· Improve sanitation condition
· Improve habitat for native wildlife and improve biodiversity.
· Outlining sustainable land use and improved air quality.
· Improved habitat for wildlife and reduced use of fertilizers and insecticides compared with lands used for row crops, protection of riparian areas, and erosion protection for sensitive land areas.
· Reduction of Greenhouse Gases from biomass power takes place because the carbon dioxide released during combustion is absorbed by the plants as they grow.
biomass .could play a role in reducing C02 emissions in both of these sectors. As the slurry remains in the digester for 30-40 days in anaerobic condition, the effluent becomes pathogen free and the output is smell-free combustible gas and organic fertilizer improving the environment and preventing diseases. At present Bangladesh meet 46.15% of its energy need by agricultural residue, 10.5% by cow dung, 12.9% by fuel wood and 33% by tree residue. This means that to meet our energy need we are depriving, ourselves from organic fertilizer and creating environmental imbalance by deforestation. One pragmatic estimate puts that the use of Biogas will reduce energy deficit by 15%.
BACKGROUND
A need assessment on Bauniabad slum identified that increase in supply of adequate and safe water, improvement of sanitation and solid waste services and improvement of knowledge about related hygienic practices should be addressed immediately. On the basis of this study, a pilot project was undertaken to introduce the small bore sewer system in combination with Biogas plant to solve the sanitation problem in one portion of the Bauniabad slum.
OBJECTIVE
The prime objective of this intervention is to utilise Biogas technology as low cost sanitation option for the residents. At the same time a number of families within the slum avails the advantage of using Biogas for cooking purpose by rotation. Specific objectives are to provide improved community latrine services and develop , financing operation method, optimize resource recovery from human excreta through Biogas generation and minimize environmental pollution through efficient waste disposal techniques.
DESCRIPTION
The project connects individual household pit latrines with a grid pipe line through which the sewage flows and finally accumulate in a main digester. From the main digester the effluent passes through secondary tank to the drain connected to outfall. A portion (96 houses) of the Bauniabad slum was selected for this purpose. The households of this slum were spaced in a planned manner. Since all the components of fixed dome Biogas plant like, inlet chamber, di-ester, hydraulic chamber / secondary treatment tank are installed below ground level, a 15 ft wide internal road was selected as the site for the plant. The latrines of 96 households, situated symmetrically with respect to the site for the plant were selected. The pit latrines were joined through 6" dia concrete pipe and ended into a bigger pipe. The pipe network ended up at the inspection pit. A big inlet pipe leads the human excreta from the latrines through the inspection pit towards the Biogas digester. The fermentation takes place within the Biogas digester. Temperature rises in the digester during the fermentation and most of the pathogenic bacteria die. A pipe is connected with the Biogas digester to two nearby kitchens. After fermentation, the digested residue passes into the secondary treatment tank and remains there for a longer time period. The design retention time within the secondary tank is about 30 days. The purpose of the secondary treatment tank is to destroy highly resistant group of bacteria making the effluent almost safe for human being. An outlet from the sedimentation tank is attached to the nearby drain which leads towards the outfall into the river Turag. When the secondary treatment tank will be filled up it should be cleaned. This solid residue can be used as soil conditioner.
USE OF GAS
Twelve to fifteen families are using two burners for their cooking purposes which in effect means a saving of Tk. 4000 per month and use of clean odourless gas.
Biogas digester Generator
Generator Description:
The biogas technology employs the technology of anaerobic digestion. It is based on the natural breakdown of organic material under bacteriological attack in the absence of oxygen, producing a combustible mixture of gas with up to 70 % methane. Biogas can be used in cooking stoves, piglet heaters, boilers, dryers and direct thermal heat processes. In larger systems it can run engines for mechanical power and generate electricity. The system consists of primary, secondary and post-treatment:
I) Primary treatment occurs in a low rate channel digester. The digester also functions as a separator for the liquid and solid fractions of the wastewater. For the solid fraction, a hydraulic retention time in the low rate digester from 20 to 30 days is calculated. The liquid fraction (80-90 % of wastewater) goes to the Upflow Anaerobic Sludge Blanket reactor (a high rate reactor).
II) Secondary treatment incorporates two components: an Upflow Anaerobic Sludge Blanket (UASB) reactor and a Slow Sand Bed Filter (SSBF). The liquid wastewater fraction, containing a high soluble organic matter content, is treated in the UASB reactor. The ratio of digester volume between the low rate biogas digester and the UASB is 2-3 : 1, depending on the condition of the wastewater. After passing the UASB, a remaining COD of 800-1000 mg/l is regularly achieved. The SSBF is connected to the low rate channel digester and receives the discharged fermented solid fraction slurry. The solid waste from the SSBF can be dried further or composted and sold as organic fertilizer to crop farms, landscaping businesses and golf courses.
III) Post-treatment. For this final treatment, the water is released into a natural oxidation system. This system features a small stabilization/buffer pond and a series of wetlands to enhance natural treatment of the effluent. A fishpond at the end of the wetland serves as a life indicator - providing sign of water treatment quality. Final chemical oxygen demand (COD) is less than 200-400 mg/l with biological oxygen demand (BOD) less than 60 mg/l. (The standard limits are 60-100 mg/l for pig farms and 20-60 mg /l for industrial plants. Often, untreated livestock farms have discharge with 8000-13,000 mg/l of BOD.) After flowing through the complete system, the treated water can be used to clean stables or can be released directly into a channel or river.
Major
Load(s) 1: generator Major
Load(s) 2: heater Major
Load(s) 3: motors Major
Load(s) 4: cooking
Technical Performance: It is expected that 50,000 cu.m. of digesters constructed during phase 1 and 2 of the program will annually produce 9,125,000 cu.m. of biogas, 10,950 MWh of electricity, 31,536 tons of bio-fertilizer, and displace 4,198 tons of LPG.
DESIGN OF BIOGAS PLANT
1.1 Introduction:
Biogas can be obtained from any organic materials after
anaerobic
fermentation by three main phases.
1.2 Mechanism of biogas fermentation:
A) Groups of Biogas microbes-

B) Groups of microbes involved in the 3 stages of biogas fermentation-

1.3 Design perameter:
A) Selection of materials.
B) Total solid(TS) contains calculations of organic materials Organic materials-
Solid part :- Total solid contained in a certain amount of materials is usually used as the material unit to indicate the biogas- producing rate of the materials. Most favourable TS value desired is 08%
Liquid part: As per Annexure-I
C) Favourable temperature, PH value & C/N ratio for good fermentation-
Temperature:- Mesophilic; 20o c to 35 o c ( Annexure-II).
PH value :- Neutral PH and ranges 6.8 to 7.2
C/N ration :- Ranges from 20:1 to 30:1 ( Annexure- VI )
D) Table showing discharge per day, TS value of fresh discharge and water to
be added to make favorable TS condition-
|
Kinds |
Body weight (kg) |
Discharge per day (kg) |
TS value of fresh discharge (% by wt.) |
Water to be added with fresh discharge to make the TS value 8% (kg) |
|
Human |
50 |
0.5 |
20 |
0.75 |
|
Cow |
200 |
10 |
16 |
10 |
|
Chicken |
1.5 |
0.1 |
20 |
0.15 |
|
Pig |
50 |
5 |
20 |
7.5 |
E) Hydraulic retention time ( HRT)-
For Mesophilic digestion where temp. varies from 20o c to 35o C and HRT is greater than 20 days.
1.4 Relationship between temperature, HRT & TS value of 8% :

1.5 Cross-section of a digester:

a. Volume of gas collecting chamber = Vc
b. Volume of gas storage chamber = Vgs
c. Volume of fermentation chamber = Vf
d. Volume of hydraulic chamber =VH
e. Volume of sludge layer =Vs
Total volume of digester V =Vc+Vgs+Vf+Vs
1.6 Geometrical dimensions of the cylindrical shaped biogas digester body:

1.7 Assumptions:
|
For volume |
For geometrical dimensions |
|
Vc £ 5% V Vs £ 15% V Vgs + Vf = 80% V Vgs = VH Vgs = 0.5 ( Vgs + Vf + Vs ) K Where K = Gas production rate per m3 digester volume per day. For Bangladesh K = 0.4 m3/m3d. |
D=1.3078 X V1/3 V1=0.0827 D3 V2 = 0.05011 D3 V3 = 0.3142 D3 R1= 0.725 D R2= 1.0625 D f1 = D/5 f2 = D/8 S1 = 0.911 D2 S2 = 0.8345 D2 |
1.8 Volume calculation of digester and hydraulic chamber:
A)Volume calculation of digester chamber-
Given :
6 cows of body weight 200 Kg each.
Temp. = 30OC (average)
Soln:
Let HRT = 40 days ( for temp. 30O C )
Total discharge = 10 kg X 6 = 60 Kg/day
TS of fresh discharge = 60 kg X 0.16 = 9.6 Kg.
In 8% concentration of TS ( To make favourable condition )
8 Kg. Solid = 100 Kg. Influnt
1 Kg. Solid = 100 / 8 Kg influent
9.6 Kg Solid = 100 x 9.6/ 8 = 120 Kg. Influent.
Total influent required = 120 Kg.
Water to be added to make the discharge 8% concentration of TS
=120 Kg - 60 Kg. = 60 Kg.
Working volume of digester = Vgs + Vf
Vgs + Vf = Q.HRT
= 120 Kg/day X 40 days
= 4800 Kg. ( 1000 Kg = 1 m3 ) = 4.8 m3.
From geometrical assumptions:
Vgs + Vf = 0.80 V
Or V= 4.8/0.8 = 6.0 m3. (Putting value Vgs + Vf = 4.8 m3)
& D = 1.3078 V 1/3 = 2.376 m @ 2.40 m.
Again
![]()
(Putting V3=0.3142D3)
![]()
![]()
Say H = 1.00m
Now we find from assumption as we know the value of 'D' & 'H'
f1 = D/5 = 2.40 /5 = 0.480 m
f2 = D/8 = 0.30m
R 1 = 0.725 D = 1.74 m
R2 = 1.0625 D = 2.55 m
V1 = 0.0827 D3 = 1.143 m3
Vc = 0.05V = 0.3 m3
Now the dimension of digester chamber is kown & drawn below-
B) Volume calculation of hydraulic chamber-
From assumptions:
Vc = 0.05 V = 0.3 m3
Vgs = 0.50 x (Vgs + Vf + Vs) x K ( Where K = Gas production rate per
m3digeste vol./day )
= 0.5 x 5.7x 0.4 =1.14 m3 -------------------------------------------------------------------- (A)
Again,
Vgs = 50% of daily gas yield
= 0.5 x TS x gas producing rate per Kg TS
= 0.5 x ( 60 kg x 0.16 ) x 0.28 m3/kg TS ( See Annex- III )
= 1.344 m3 ------------------------------------------------------------- (B)
From A & B let Vgs = 1.344 m3.
Vc + Vgs = 0.3 m3 +1.344 m3 = 1.644 m3
Again V1 = [{(Vc + Vgs) - {p D2 H1}/4 ]
= [1.644 - {3.14 x (2.4)2 x H1}/4]
Or, H1 = 0.110m
We have fixed h = 800 mm water volume ( I mm = 10 N/ m2 )
h = h3 + f1 + H1
Or, h3 = 0.210m.
Again we know that
Vgs = VH
Or, 1.344 m3= 3.14 x (DH)2 x h3/4
Or, DH = 2.85m
Now we know the dimension of hydraulic chamber. Moreover keeping h = 800 mm, we can choose or re-arrange the dimension considering availability of site and construction suitability. For most suitable dimensions we can select the drawing of Annexure- IX for 60 Kg cow dung per day as raw material.
Note: For ready reference 4 family type Biogas plant's drawing is shown(standared dimension's) in Annexure-VIII, Annexure-IX, Annexure-X & Annexure-X1 where 40 Kg, 60Kg, 80Kg and 100Kg cow dung is considered as raw marterial per day respectively. If bigger size plant is required ,it can be designed keeping all safety considerations in design and construction.
Annexure- 1
TABLE-1: THE TOTAL SOLID CONTENT OF COMMON FERMENTATION MATERIALS IN RURALAREAS (APPROXIMATELY)
|
Materials |
Dry matter content (%) |
Water content (%) |
|
Dry rice straw |
83 |
17 |
|
Dry wheat straw |
82 |
18 |
|
Corn stalks |
80 |
20 |
|
Green grass |
24 |
76 |
|
Human excrement |
20 |
80 |
|
Pig excrement |
18 |
82 |
|
Cattle excrement |
17 |
83 |
|
Human Urine |
0.4 |
99.6 |
|
Pig Urine |
0.4 |
99.6 |
|
Cattle Urine |
0.6 |
99.4 |
Annexure-II
TABLE-2: BIOGAS-PRODUCING RATES OF SOME COMMON
FERMENTATION MATERIALS ATDIFFERENT
TEMPERATURES (m3/Kg TS )
|
Materials
|
Medium temperature(35o C) |
Ordinary temperature (8 o ~ 25o C ) |
|
Pig manure |
0.45 |
0.25 ~ 0.30 |
|
Cattle dung |
0.30 |
0.20 ~ 0.25 |
|
Human wastes |
0.43 |
0.25 ~ 0.30 |
|
Rice straw |
0.40 |
0.20 ~ 0.25 |
|
Wheat straw |
0.45 |
0.20 ~ 0.25 |
|
Green grass |
0.44 |
0.20 ~ 0.25 |
Experimental conditions:- The fermentation period of the excrement materials lasts
60 days and that of the stalk type lasts 90 days. The
fermentation material concentration ( total solid content )
is 6%.
Annexure- III
TABLE-3: BIOGAS PRODUCING RATES OF SOME FERMENTATION
MATERIALS AND THEIR MAIN CHEMICAL COMPONENTS.
|
Materials and their main components |
Yield of Biogas m3/kg TS |
Methane content ( % ) |
|
Animal barnyard manure |
0.260 ~ 0.280 |
50 ~ 60 |
|
Pig manure |
0.561 |
|
|
Horse droppings |
0.200 ~ 0.300 |
|
|
Green grass |
0.630 |
70 |
|
Flax straw |
0.359 |
|
|
Wheat straw |
0.432 |
59 |
|
Leaves |
0.210 ~ 0.294 |
58 |
|
Sludge |
0.640 |
50 |
|
Brewery liquid waste |
0.300 ~ 0.600 |
58 |
|
Carbohydrate |
0.750 |
49 |
|
Liquid |
1.440 |
72 |
|
Protein |
0.980 |
50 |
Annexure- IV
TABLE-4 BIOGAS- PRODUCING RATES OF SEVERAL SUBSTANCES
|
Material
|
YpCMDV (m3/m3d) |
YpKgM(m3/KgTS) |
Amount of biogas produced in a period of time( as a % of the total yield) |
|||
|
|
|
|
0 ~15 (d) |
15 ~ 45 (d) |
45 ~ 75(d) |
75 ~ 13 (d) |
|
Water Hyacinth |
0.40 |
0.16 |
83 |
17 |
0 |
0 |
|
Alligator Weed |
0.38 |
0.20 |
23 |
45 |
32 |
0 |
|
Water Lettuces |
0.40 |
0.20 |
23 |
62 |
15 |
0 |
|
Cattle Dung |
0.20 |
0.12 |
11 |
33.8 |
20.9 |
34.3 |
|
Pig Manure |
0.30 |
0.22 |
19.6 |
31.8 |
25.5 |
23.1 |
|
Human Wastes |
0.53 |
0.31 |
45 |
22 |
27.3 |
5.7 |
|
Dry Grass |
0.20 |
0.21 |
13 |
11 |
43 |
33 |
|
Rice Straw |
0.35 |
0.23 |
09 |
50 |
16 |
25 |
Note: - The fermenting temperature is 30oC. It is batch-fed fermentation. YpCMDV refers to the average yield of biogas per cubic meter of the digester volume during the period of normal fermentation ( m3/ m3d) YpkgM refers to the yield of biogas per kilogram of the fermentation material (m3/kg TS)
Annexure-V
TABLE-5 : THE SPEED OF BIOGAS PRODUCTION WITH COMMON FERMENTATION MATERIALS.
|
Speed |
Amount of biogas produced in a period of time (expressed as a percentage of the total yield of biogas) |
Biogas Producing rate |
|
Time(d ) |
10 20 30 40 50 60 70 80 90 |
(m3/kg TS ) |
|
Materials |
|
|
|
Human wastes |
40.7 81.5 94.1 98.2 98.7 100 * * ** |
0.478 |
|
Pig manure |
46.0 78.1 93.9 97.5 99.1 100 * * ** |
0.405
|
|
Green grass |
- - - 98.2 - 100 ** |
0.410 |
|
Cattle dung |
34.4 74.6 86.2 92.7 97.3 100 * * ** |
0.300 |
|
Wheat straw |
8.8 30.8 53.7 78.3 88.7 93.2 96.7 98.9 100 * ** ** |
0.435 |
* Biogas production is at the highest speed.
** Amount of Biogas produced to more than 90% of the total yield of a fermentation period.
Experimental conditions: - Fermenting temperature 35oC, the total length of fermentation period being
60 days for the excrement material and 90 days for the stalk type, the materials concentration; total solid content of the fermentative fluid being 6%.
ANNEXURE- VI
TABLE -6. CARBON-NITROGEN RATIOS OF SOME COMMON FERMENTATION MATERIALS (APPROX.)
Material |
Carbon content of material (%) |
Nitrogen content of materials(%) |
Carbon-nitrogen ration (C/N) |
|
Dry wheat straw |
46 |
0.53 |
87:1 |
|
Dry rice straw |
42 |
0.53 |
67:1 |
|
Corn stalks |
40 |
0.75 |
53:1 |
|
Fallen leaves |
41 |
1.00 |
41:1 |
|
Soybean stalks |
41 |
1.30 |
32:1 |
|
Wild grass |
14 |
0.54 |
27:1 |
|
Peanut stems and leaves |
11 |
0.59 |
19:1 |
|
Fresh sheep droppings |
16 |
0.55 |
29:1 |
|
Fresh cattle dung |
7.3 |
0.29 |
25:1 |
|
Fresh horse droppings |
10 |
0.42 |
24:1 |
|
Fresh pig manure |
7.8 |
0.60 |
13:1 |
|
Fresh human wastes |
2.5 |
0.85 |
29:1 |
ANNEXURE- VII
TABLE-7 AMOUNT OF HUMAN AND ANIMAL WASTES DISCHARGED PER DAY ( APPROX.)
|
Kinds |
Body weight (kg) |
Daily amount of excrement (kg) |
Daily amount of urine (kg) |
Annual amount of excrement discharged (kg) |
Annual amount of excrement collection (kg) |
Daily yield of biogas per capita (m3) |
|
Pig |
50 |
6 |
15 |
2190 |
1752 |
0.18 ~ 0.25 |
|
Ox |
500 |
34 |
34 |
12410 |
9928 |
0.36 ~ 0.96 |
|
Horse |
500 |
10 |
15 |
3650 |
2920 |
|
|
Sheep |
15 |
1.5 |
2 |
548 |
438.4 |
|
|
Chicken |
1.5 |
0.10 |
0 |
36.80 |
29.44 |
0.0076 ~ 0.0112 |
|
Human |
50 |
0.50 |
1 |
182.50 |
146.00 |
0.028 |
Note: The annual amount of excrements collected accounts for 80% of that discharge.
CONSTRUCTION PROCEDURE OF BIOGAS PLANT
1.1 SELECTION OF SITE
First choose the site which is nearest to the place of raw materials as well as appliances to be used for the following reasons.
- Extra labour requires to feed the digester if it is too far from the source
of raw materials.
- Longer length of gas distribution pipe line will reduce the design
pressure in a considerable amount.
- Construction cost will be higher.
- Condensate could be trapped if any sag in long gas pipe line which
may block the gas pipe line.
1.2 LAYOUT
First go through the drawings of the plant in detail. For example let choose 6m3 volume digester's drawing as shown in Annexure-X.


Calculate the outer diameter of the digester from Annexure-1 or take the outer diameter from layout plan of fig-1. Then find the radius of the digester for earth cutting; outer diameter ¸ 2 = 2800 ¸ 2 = 1400mm. Measuring this radius from peg P2 make a circle C1 on the ground as shown in figure-3. Similarly mark the circle C2 on the ground for hydraulic chamber as shown. Lastly mark the inlet on the ground accordingly. Now the layout is completed.

1.3 EARTHWORK IN EXCAVATION:
A. Digester (Fermentation Chamber)-
Depth of earth excavation
=300+480+1000+300+100=2180mm as shown in figure-4. fªù¡ ew-24
Excavate around the outer diameter upto the depth of cylindrical portion that is 300+480+1000+100 = 1880mm as shown by shaded portion fig-4.

From Annexure-1 radius of curvature of the bottom dome of the digester =2600mm. Take a bamboo pole B1 of length 2660+100=2760mm as shown in figure-4.
Now erect 2 bamboo post B2 & B'2 along transverse center line of the digester up to a height which is 2760(;B1) -2180 (; total depth of excavation) = 580mm from G.L. as shown in figure-4. Now fix a straight bamboo B3 horizentally upon these posts B2 &B'2 . Mark the center point of the digester in bamboo B3 and hang bamboo pole B1 from this center point as shown in figure-4 and excavate the bottom dome as per drawing until the bamboo B1 swing freely. Now extend the excavation horizentally as per measurement of the drawing in Annexure-X by trowel which is shown by double dotted line in figure-4.
B) Hydraulic chamber & its connections-
Depth of earth excavation of hydraulic chamber = 657+75 =732mm
Depth of earth excavation of outlet hole (Inter connection of digester & hydraulic chamber) = 300+480+1000+100 = 1880 (see Annexure-1 & fig-5). Excavate hydraulic chamber around the outer circle C2 (fig-2) upto the depth of 732mm as shown by hatched line in fig-5.

Now excavate the outlet holes taking dia. = 600+(125)x2 wall thickness + (075)x2 extra clearance = 1000mm upto the depth 1880 & dia.950+(125)x2 wall thickness +(075)x2 extra clearance = 1350mm upto the depth 1283 as shown in drawing by highlighted in fig-5.
Now excavate for inlet connection as the dimension & drawing of Annexure-X as shown in fig-5. Now earthwork in excavation is completed.
1.4 CONSTRUCTION WORK:
A) Cement concrete -
Complete the casting of cc works at the bottom of the digester and at the bottom of the outlet hole as shown by highlighted in figure-6.

B) Brick work-
Fix a MS Rod-R (dia 6/8") straight upward through the center point of the digester (fermentation Chamber) as shown in fig-6. Take a longitudinal slice of bamboo-S and tie with MS rod-R as shown in fig-6 so that its length is equal to inner radius of the digester and this bamboo slice-S can rotate around the MS Rod-R. Now start brick work of cylindrical shape by rotating this bamboo slice-S. During brick work fix inlet R.C.C. Pipe as per requirement. Keep opening of required dimensions for outlet hole (Inter connection of digester & hydraulic chamber) and complete the brick work of cylindrical portion of the digester body Similarly complete the brick works of outlet hole & hydraulic chamber.
C) Ring beam-
Complete the casting of ring beam ( which is shown in figure-7).
D) Brick work of the top dome & the plastering works-
First complete the plastering and neat cement finishing works inside the completed portion of the digester before starting the top dome.
Now place a brick touching ring beam with required cement mortar giving direct support by bamboo-B4 as shown in fig-7. Here bamboo B4 = radius of curvature of the top dome =1780 mm. Subsequently place a MS hook(1/4" dia) with a counter weight brick which is placed at the other end of the hook as shown in fig-7. Now remove the bamboo-B4. Brick will remain in its position by the help of MS hook and counter weight brick. Now similarly place the adjacent brick and proceed until the circle is completed. Now remove all hooks and first layer bricks of the top dome will remain as it is placed .

Similarly complete all the circular layers of bricks & at the center of the top dome keep a 1" dia. G.I. pipe with one end threaded as shown in Annexure-1. Now complete the plastering work with neat cement finishing inside (Special type plaster = in 3 layers; 1st layer in 1:4 proportion, 2nd layer in 1:3 proportion and 3rd layer in 1:2 proportion. Normal plaster = 1 layer in 1:4 proportion ) & outside (normal plaster) Then complete the wax polishing inside as required.
FEW CONSTRUCTION STEPS IN PICTURE :
|
|
|
CC Cutting of a Dome |
|
|
|
Brick work of topof Dome of a Digester |
|
|
|
|
|
Inside Plustering of Digester |

Photo : Inside Plustering of Digester
Recent Improvements
• Mixing Device
• Turret
• Pipeline
• Hydraulic Chamber
• Burner
• Slurry Processing
• Water Drain
• Cooking Practice

A Complete Plant (Old)

A Complete Plant (New)

Digester Bottom and Wall

Digester Wall and Outlet Passage

Top Dome

Inlet (Old)

Mixing Device

Inlet (New)

Inlet (New)

Center Pipe (Old)

Turret

Turret and Valve

Pipe Line

Hydraulic Chamber

Hydraulic Chamber (New)

Slurry Pit

MoU on Slurry Processing and Marketing

Slurry Processing

Water Drain

Burner
.

Cooking with Biogas
1.5 MISCELLANEOUS WORK:
Complete inlet chamber and the cover of hydraulic chamber.
Complete back filling over the top dome.
Install gas pipe ling.
Charge the digester with raw materials so that it is full without any void & keep close the burner until gas is produce.
1.6 INITIAL CHARGING OF BIOGAS PLANT :
First keep the gas valve open. Put a mark "M" on the inside wall of the hydraulic chamber as shown in fig. below with the help of water level so that the position of this mark is the same level of the top most point of the top dome from inside .

Now charge the digester until raw material touches the mark "M". Close the valve & it is aneorobic now. Keep the burner's or appliance's knob or gas valve close after in use to keep the digester always anearobic.
2.0 Economic Worth of Bio-Gas
Bio-gas is not traded, and, therefore, has no market price. Hence it has to be valued according to the equivalents that are traded. Several fuels can be considered as alternatives, especially for cooking where cow-dung, firewood, charcoal, other gases, electricity and kerosene, and for lighting houses where kerosene, electricity have all been used. Non-nal householders in the rural areas of Bangladesh use wood as a fuel in the oven and kerosene for lighting lamp or hajack. Bio-gas can be used for both the above mentioned purposes. So in this case the output of bio-gas plant could be used for cooking replacing the equivalent firewood requirement, for lighting replacing the equivalent kerosene requirement and also as fertilizer, meeting the equivalent need of urea of a household. The prices of key inputs were estimated and the output of the bio-gas plant was estimated by considering the market price of firewood, kerosene and fertilizer.
DETAILED ESTIMATE OF FAMILY TYPE BIO GAS PLANT
PLANT TYPE-F2,DIA=2400mm,VOL=6m3FROM COW DUNG )
|
01.Earthwork in excavation Inlet chamber 1.31 x 1.00 x 0.50 = 0.66 m3 Fermentation chamber {(x(2.80)2 x 2.43}(4 = 13.42 m3 Hydraulic chamber {(x(1.71)2 x 0.732}(4 = 1.68 m3 {(x(1.35)2 x 0.548}(4 = 0.78 m3 {(x(0.84)2 x 0.60}( 4 = 0.33 m3 Manure Collecting Pit {(x(1.71)2x 0.732}(4 = 1.68 m3 RCC pipe 1.00x0.30x0.30 = 0.09 m3 Total quantity = 18.64 m3 02.Cement concrete works(1:2:4) Inlet chamber 1.64 x 0.25 x 0.075 = 0.03 m3 Fermentation chamber {(x(2..40)2x0.100}(4 = 0.45 m3 extra 20% for curvature = 0.09 m3 [(x{(2..65)2-(2..40)2} x0.15](4 = 0.15 m3 Hydraulic chamber {(x(0.725)2 x 0.075}(4 = 0.03 m3 0.75x0.20x0.075 =0.01 m3 [{(x(1.20)2 x 0.075}(4] - [{(x(0.60)2 x 0.075}(4] = 0.06 m3 [{(x(1.56)2 x 0.075}(4] - [{(x(0.95)2 x 0.075}(4] = 0.09 m3 Manure Collecting pit {(x(1.56)2 x 0.075}( 4 = 0.14 m3 Total quantity = 1.05 m3 03.Reinforce concrete works (1:2:4) Inlet chamber 0.44 x 0.26 x 0.10 = 0.01 m3 Fermentation chamber (x{2.652-2.402}x0.150(4 = 0.15 m3 Hydraulic chamber {(x(1.56)2 x 0.10}( 4 = 0.19 m3 Total quantity = 0.35 m3 04.M.S. Bar 40 grade 1% of RCC volume =27.00Kg 05.Brick work 5" (1: 4) Inlet chamber (0.75+0.55) x 2x0.50x0.125= 0.16 m3 Fermentation chamber 2(x1.325 x 1.00 x 0.125 = 1.04 m3 {(x(2.525)2 x 0.125}( 4 = 0.62 m3 Extra 20% for curvature = 0.12 m3 Hydraulic chamber 2(x0.45 0 x.362 x 0.125= 0.13 m3 2(x0.473 x 0.537 x 0.125= 0.20 m3 2(x0.78 x 0.657 x 0.125 = 0.40 m3 |
Manure Collecting pit 2(x0.717 x 0.657 x 0.125 = 0.37 m3 Total quantity =3.04 m3 06.Plastering work Inlet chamber (6mm thick 1: 4 ratio) (0.75 + 0.55)x2x0.50 x 2= 2.60 m2 Fermentation chamber {(x(2.40)2 x 3}( 4 = 13.52 m2 20% for curvature = 2.70 m2 2(x1.32 x 0.55 = 4.56 m2 2(x1.20 x1.00 = 7.54m2 Hydraulic chamber 2(x0.30 x 0.525 = 0.99 m2 2(x0.475 x 0.473 = 1.41 m2 2(x0.655 x 0.657 = 2.70 m2 {(x(1.31)2 }( 4 = 1.35 m2 Total quantity = 37.37 m 07.Special type of plastering Fermentation chamber (3 coat) (6mm thick 1:2 ratio) {(x(2.40)2 x 3}( 4 = 13.57 m2 20% for curvature = 2.71 m2 2(x1.20 x 0.40 x 3 = 9.05 m2 Total quantity = 25.33 m2 08.Wax polishing and heating 1/3 of Item No. 7 = 8.44 m2 09.RCC pipe 6"( = 1 pc. 10.G.I. pipe 1"( = 0.30 m. 11.Gas nozzle = 1 No. 12.Plastic gas pipe 3/4"( = 30.00 m. 13.Supply of 1 double burn .= 1 No. 14.Gas valve 3/4" = 1 Nos. 15.G.I. reducer 1" x 3/4 = 1 No. 16.Nipple 3/4" = 4 No. 17.Back filling [ After complition =18.91 m3 ABSTRACT OF MATERIALS 01. Earth work in excavation = 700 cft. 02. Bricks = 1275 Nos. 03. Khoa = 45 cft. 04. Sand = 60 cft. 05. Cement = 20 bags. 06. Mason = 12 Nos. 07. Labour = 15 Nos. 08.Wax. = 2 Kg. 09. RCC pipe 6"( = 1 pc. 10. G.I. pipe 1"( = 0.30 m. 11. Gas Nozzle = 1 No. 12. Plastic Gas Pipe 3/4"( = 30.00 m. 13. Supply of 1 double burner = 1 No. 14. Gas valve 3/4" = 1 Nos. 15. G.I. reducer 1" x 3/4" = 1 No. 16. Nipple 3/4" = 4 No |
: Please keep eyes on www.reein.org . More biogas plant design will be posted shortly . For further query please email reein@dhaka.net
[ Important Notice : All the papers/documents are copyright protected, if you would like to use the any part of information posted herewith REEIN, please do mention the source name- www.reein.org/ and writer name as well, otherwise you will be accused for the copyright violation. ]




